Operation restoration: Eastbound I-90 goes under the knife between Issaquah and North Bend

Wednesday, May 2, 2018 - 09:43

Lisa Van Cise, communications, 206-440-4702

ISSAQUAH – More than 15 miles of cracked and damaged concrete on Interstate 90 between Issaquah and North Bend will soon be a distant memory as crews begin work on a new two-year project.

Washington State Department of Transportation contractor crews from Acme Concrete Paving Inc. will preserve this critical east-west route by repairing cracked and chipped pavement and replacing the concrete damaged beyond repair. Work on the $21.7 million project begins Monday, May 7.

“The concrete here is more than 40 years old and 73,000 vehicles use it each day,” said WSDOT Project Engineer Aleta Borschowa. “It’s critical we preserve and take care of the infrastructure, to keep vehicles and freight moving on this vital highway.”

Over the next two years, crews will also pave the outside shoulder, 10 on- and off-ramps and lay down new concrete on the eastbound I-90 Winery Road bridge and the westbound I-90 Raging River bridge.

Lane closures
Drivers should plan for the following during the project:

  • Single and double lane closures during the day.
  • Up to three lanes closed overnight.
  • Around-the-clock shoulder closures.
  • Overnight ramp closures.
  • Speed limit reduced to 55 mph.

Check the King County construction page for upcoming I-90 closure details.

Summer travel on I-90
This project is one of four on I-90 between Issaquah and Ellensburg. Travelers should plan for construction delays:

Tools for trip planning
Travelers can check the state travel map or follow WSDOT on Twitter and Facebook for the latest traffic information.