WSDOT Projects

text size: T T T

SR 283 - Winchester Wasteway - Bridge Deck Repair - Complete April 2006

Project completed April 28th, 2006
View entire map This bridge deck rehabilitation is located at Mile Post 9.2 in Grant County, 9 miles north of I-90, between George and Ephrata.

 Click to enlarge
View entire photo 
A new smoother bridge deck, following construction.
  
View entire photo 
An example of the deterioration of the old bridge deck.
Project Facts
  • Construction  began March 13th and was complete April 28th, avoiding the Memorial Day traffic.
  • A detour was required for about 2 months to safely repair the narrow (26 foot wide) bridge deck.
  • A deck overlay does what just patching could not, preserving the life of the structure.

Project Status

This project was completed April 28th, 2006.

 

This Structure Preservation Program Project rehabilitated the deteriorating bridge deck on the SR 283 Winchester Wasteway Bridge in Grant County.

Why is WSDOT rehabilitate this bridge deck?
The bridge was constructed in 1953.  The deck was experiencing cracking and spalling concrete, and exposed reinforcing steel.  In March 2004, testing showed approx. 41% of the deck area experiencing deterioration, with 2% being the threshold to consider repair and/or overlay.  Deck repair and overlay were required to preserve the deck.

The End Result
The deck repair will removed approximatley 1/2" of deteriorating concrete, and added a 1-1/2" deep concrete overlay to provide a smoother, safer ride.

Project Benefits

  • Preserves bridge life while minimizing ongoing repair costs
  • Reduces likelihood deck replacement will be required in the future
  • Replaced current cracked, patched, spalling surface with new smooth surface
  • Provides additional cover over reinforcing steel to decrease surface cracking
  • Improves structural integrity

What is the project timeline?
Construction began April 4th and was complete on April 28th, 2006.

Public Involvement
Your thoughts and ideas are important to us.  If you have questions or concerns about this project, please the project engineering office listed below.

Environmental Protection
All applicable environmental laws and guidelines were followed.  A Biological Assessment was completed on September 1st and determined there would be no environmental effect and the NEPA (National Environmental Policy Act) MOU (Memorandum of Understanding) was signed on October 12th, permitting the project.
Please visit the WSDOT Environmental Services Web site for more information.

Increasing safety is one of our priorities
Besides the safety benefits of the project itself, safety for the public and the construction workers is paramount while the work is underway. A comprehensive traffic control plan and a work zone safety plan was prepared to protect travelers and workers.  The narrow structure required a detour to reroute traffic to allow the project to be completed safely and efficiently.

Will this project impact tribal resources?
Following consultation with the Colville Tribes, no impacts were identified.  WSDOT addresses the concerns of tribal nations using the process outlined in Section 106 of the National Historic Preservation Act and the WSDOT Tribal Consultation Policy adopted in 2003 by the Transportation Commission as part of the WSDOT Centennial Accord Plan.

Financial Information

Two bids were opened on December 15th, 2005.  On December 19th, contract #7069 was awarded to Concrete Barrier, Inc. of Mukilteo for $416,134.00, 10% under the engineering estimate.  This project was combined with the US 97 South of Omak Bridge Deck Repair project and the contract covered both.
This project was funded through the following sources:

  • Pre-Existing Gas Tax - $325,000
  • Total funding from all sources - $325,000

How can I get more information?
Contact:
Project Engineer Mike Fleming
WSDOT North Central Region
P.O. Box 98
Wenatchee, WA 98807
Phone:  (509) 667-2870 or toll free (888) 461-8816
Email:  fleminm@wsdot.wa.gov

back to top