Latest Program News

  • Temporary Alaskan Way taking shape near tunnel’s south portal

    For decades, surface Alaskan Way stretched along the downtown waterfront, connecting travelers to the waterfront piers and providing north-south passage through downtown.

    Streetview of Alaskan Way from 2008 showing western position relative to viaduct

    Alaskan Way north of Seneca Street from 2008, via Google Streetview

    Since 2011, the street has been neatly squeezed in between the Alaskan Way Viaduct’s concrete footings. It was shifted to this alignment to clear space for SR 99 tunnel and other construction along the waterfront, but this location was always meant to be temporary. Eventually, the land Alaskan Way currently occupies would need to be cleared to allow for viaduct demolition.

    With demolition now on the horizon, we’ve begun restoring the street to its traditional location. Crews will continue this work over the summer and shift the street back to the west of the viaduct later this year, before the new SR 99 tunnel opens. The preparation for this shift is becoming visible as crews rebuild the roadway.

     

    The restored Alaskan Way will look much like it did the first time around. It will generally have two lanes in each direction, providing access to Colman Dock and waterfront businesses and buildings. Near the viaduct demolition work zone, the road may be narrowed to one lane in each direction, but access to Colman Dock and other properties will always be preserved.

    This configuration will remain in place until the Waterfront Seattle Project builds a new, permanent Alaskan Way in the footprint of the viaduct.

    South portal update

    A little farther south of this stretch of new pavement, an aerial view captures work building the roadways near the tunnel’s south portal. This view from the Columbia Tower shows the alignment of ramps and roadways coming into focus.

    Aerial view of the tunnel south portal

    The future ramps at the tunnel’s south portal cross what is today southbound SR 99 (click for bigger version)

    You can watch this road work from the construction camera we have mounted atop the tunnel’s south operations building. This south portal work is part of the SR 99 Connections Project, which is currently performing utility and roadwork on East Frontage Road South, between South Royal Brougham Way and South Atlantic Street.

    Crews hope to complete as much work as possible before the tunnel is ready to open. The final ramp connections, as you can tell from that map above, will go across the SR 99 mainline. So when the tunnel is ready, we will need to close SR 99 for approximately three weeks to realign the highway and connect it to the tunnel. We do not have a date for the closure yet, but we will be able to provide notice four to six weeks in advance.
     

    — more —

    Order: 9.0

  • Kiewit wins contract to demolish the viaduct

    Today, Kiewit Infrastructure West Co. was named the apparent-best-value contractor for the project that will demolish the viaduct, decommission the Battery Street Tunnel and reconnect city surface streets just north of the new SR 99 tunnel.

    The project’s design-build contract, which includes both design and construction services, is valued at $93.7 million. Kiewit submitted the apparent-best-value bid – a combination of points received for their technical proposal and their price.

    Timelines for the work will emerge after the contract is finalized and the contractor receives approval to begin design work. After that point, WSDOT will be able to share more specifics about how demolition and decommissioning will proceed.

    Last year we combined three projects into one in order to save construction time and reduce risk, so this project entails more than just demolishing the Alaskan Way Viaduct. Kiewit will be responsible for:

    • Removing the Alaskan Way Viaduct.
    • Removing the Columbia Street and Seneca Street ramp structures.
    • Decommissioning the Battery Street Tunnel, removing utility and mechanical systems, sealing the entrances and filling the tunnel.
    • Raising Aurora Avenue North to grade between Harrison Street and Denny Way, rebuilding the street, and reconnecting Thomas and John streets across Aurora Avenue North.
    • After viaduct demolition is complete, restoring waterfront roadways, sidewalks, street lighting and other elements to a temporary condition until the City of Seattle builds the new waterfront.

    Demolition cannot start until the tunnel opens to drivers, which could be as soon as this fall.

    — more —

    Order: 9.1

  • Sprucing up the north portal

    As we’ve mentioned before, the area surrounding the SR 99 tunnel’s north portal has changed a lot over the course of the project. Nearby cranes indicate that there’s still lots of construction in the area, but Seattle Tunnel Partners’ work is beginning to wind down.

    Last month, following years of utility and other construction, STP began restoring surface streets near the north portal. This work is occurring south and west of STP’s work zone, and includes sidewalk and street restoration.

    Closeup view of two crew members installing form work on Thomas Street
    Crews set up forms in preparation for paving Thomas Street near the tunnel's north portal.

    As roadway restoration continues, crews are building the remaining section of the tunnel’s north operations building. After building out the space that previously housed the tunneling machine’s disassembly pit, crews built the framework for the tunnel’s north operations building. They’re now working on the interior of the building.

    View of the tunnel's north operations building with street restoration in front
    Crews rebuild the tunnel's north operations building behind Thomas Street restoration.

    The latest notification for street restoration is available on our construction notifications page. You can also follow progress at the north portal on our construction cameras page.

    — more —

    Order: 9.2