Sam Hill - Biggs Rapids Bridge to Re-Open Today, May 19, at 6 p.m.

Moving Washington

Jobs Now

Date:  Monday, May 19, 2008

Contact: Chris Tams, WSDOT Columbia Gorge Project Engineer, (866) 279-0730
Jeremy Wright, WSDOT Communications, (360) 905-2078

GOLDENDALE – After a near five-month closure, Washington State Department of Transportation (WSDOT) is pleased to announce the re-opening of the US 97, Sam Hill – Biggs Rapids Bridge, to all traffic for the 2008 summer vacation season, beginning May 19 at 6 p.m. The bridge will remain open throughout the entire summer season, until September 3, 2008, when it will close again for the remainder of construction activities. All previous weight restrictions have also been lifted.

“I am happy to report that the Sam Hill – Biggs Rapids Bridge will be opening on May 19, several days ahead of our planned May 23rd opening” said WSDOT’s Columbia Gorge Project Engineer Chris Tams. “It was necessary for us to close the bridge entirely due to safety concerns for the construction crews and the traveling public, to minimize the length of impacts to the surrounding communities, and to ensure the highest quality construction,” said Tams. “We appreciate the community’s patience, as the crews worked hard to ensure that the bridge is safely open for traffic before the Memorial Day weekend,” concluded Tams.

Despite periodic work stoppages for unsafe conditions due to extremely high winds and a one-week work suspension due to the fatal work-zone accident, construction continued on schedule and on budget throughout the winter and spring of 2008.

Originally scheduled to take place in 2010, the repair work was accelerated to start in 2007 due to the increased rate of deterioration. In addition to accelerating the project start date, the construction duration was shortened by the decision to fully close the bridge during construction so the work could be completed as quickly as possible, minimizing impacts to the people who depend on the bridge. A full closure of the bridge during the deck reconstruction also eliminates vibration due to passing traffic ensuring a better concrete cure and a longer-lasting bridge deck.

Since the complete closure in January, WSDOT contractor Mowat Construction Company of Woodinville, WA has completely replaced the concrete deck on the Washington bridge approach and the truss span. The bridge rail has also been upgraded to meet current design standards for vehicles and bicycles and to match the historic context of the bridge. Work began on the Washington approach, which was the most deteriorated section, in order to lift all weight restrictions on the bridge when the bridge reopened for the summer.

In response to community feedback, the bridge is being reopened in time for the Memorial Day weekend, the start of summer tourism and harvest seasons. After Labor Day, the bridge will close again for the replacement of the bridge deck on the Oregon bridge approach. Construction is expected to conclude and the bridge is expected to fully reopen in winter 2008/2009.

For information regarding the US 97, Biggs Rapids-Sam Hill Bridge Deck Replacement project, please visit http://wsdot.wa.gov/projects/US97/BiggsBridge/.

Media wanting tours of the site prior to opening the bridge to traffic can contact Jeremy Wright in the WSDOT Communications Office at 360-905-2078.