Whatcom County

SR 9 Tawes Creek and Two Tributaries to Tawes Creek - Fish Passage - #9380

Highway: SR 9    Region: Northwest    County: Whatcom    Location: Milepost(s) 77.30 - 78.19
Contact: Gabe Ng, Project Engineer, 360-788-7403
Description: In 2019, Washington State Department of Transportation contractor crews will remove three fish barriers under State Route 9 in the community of Van Zandt in Whatcom County.
Project webpage
Work schedule:

  • Until further notice - SR 9 near Potter Road is reduced to a single lane with a temporary signal alternating traffic.

SR 542 I-5 to Britton Road - Paving and ADA Compliance - #9362

Highway: SR 542    Region: Northwest    County: Whatcom    Location: Milepost(s) 0 - 2.81
Contact: Gabe Ng, Project Engineer, 360-788-7403
Description: In 2019, WSDOT contractor crews from Granite Construction will repave and improve pedestrian crossing areas on SR 542 from I-5 to Britton Road through Bellingham.
Project webpage
Work schedule:

  • Monday, Oct. 14 - Eastbound and westbound lane reduction between I-5 and Hannegan Road from 8 a.m. to 4 p.m.
  • Wednesday, Oct. 16 - Eastbound and westbound lane reduction between Hannegan Road and Britton Road from 8 a.m. to 4 p.m.

SR 542 Bellingham to Kendall Area Resurfacing - #9372

Highway: SR 542    Region: Northwest    County: Whatcom    Location: Milepost(s) 2.98 - 19.27
Contact: Gabe Ng, Project Engineer, 360-788-7403
Description: In 2019, WSDOT contractor crews will resurface nearly 16 miles of SR 542/Mount Baker Highway from Britton Road near Bellingham to Markel Road near Kendall. Travelers should expect 20-45 minute delays behind this work zone, which requires daytime closures and warm and dry temperatures.
Project webpage
Work schedule:

  • No lane closures are currently scheduled.

SR 542 Hazard Tree Removal

Highway: SR 542   Region: Northwest    County: Whatcom    Location: Milepost(s) 36 to 47
Contact: Andrea E. Petrich, communications, 360-757-5963
Description: Crews will remove 75 hazard trees from along SR 542/Mount Baker Highway.
Work schedule:

  • No lane closures are currently scheduled.

SR 547 Peaceful Valley/Sumas Area Resurfacing - #9372

Highway: SR 547    Region: Northwest    County: Whatcom    Location: Milepost(s) 1.87 - 8.90
Contact: Gabe Ng, Project Engineer, 360-788-7403
Description: In 2019, WSDOT contractor crews will resurface nearly seven miles of SR 547/Kendall Road from Peaceful Valley Drive to Saar Creek/Hillview Road. Travelers should expect 20-45 minute delays behind this work zone, which requires daytime closures and warm and dry temperatures.
Project webpage
Work schedule:

  • No lane closures are currently scheduled.

SR 548 Ferndale/Birch Bay Area Resurfacing - #9372

Highway: SR 548    Region: Northwest    County: Whatcom    Location: Milepost(s) 3.46 - 5.81
Contact: Gabe Ng, Project Engineer, 360-788-7403
Description: In 2019, WSDOT contractor crews will resurface nearly 16 miles of SR 548/Grandview Road from North Starr Road to the Blaine Road roundabout. Travelers should expect 20-45 minute delays behind this work zone, which requires daytime closures and warm and dry temperatures.
Project webpage
Work schedule:

  • No lane closures are currently scheduled.

Skagit County

Anacortes - Superload move

 

Highway: SR 20 Spur/SR 20    Region: Northwest    County: Skagit    Location: Milepost(s) 50.47 to 47.89 (SR 20 Spur) and 47.87 to 48.40 (SR 20)
Contact: Andrea E. Petrich, communications, 360-757-5963
Description: A superload will move from Port of Anacortes to the Marathon Refinery.
Work schedule:

  • Tuesday, Oct. 15, to the morning of Wednesday, Oct. 16 - Travelers will experience brief traffic holds and slowdowns on SR 20 Spur and SR 20 from 11:59 p.m. and 4 a.m. between R Avenue and March's Point Road during a superload move.
SR 530 Sauk-Suiattle Confluence - CED Retrofit - #9436

Highway: SR 530    Region: Northwest    County: Skagit   Location: Milepost(s) 55.68 - 55.91
Contact: Shane Spahr, Project Engineer, 360-848-7103
Description: In 2019, WSDOT contractor crews will use a combination of logs and rocks to stabilize this bank between the Sauk River and SR 530.
Project webpage
Work schedule:

  • Tuesday, Oct. 15, through Thursday, Oct. 17 - Crews will close one lane of SR 530 from 7 a.m. to 5 p.m. for planting work. Flaggers will alternate travelers through the open lane.

Island County

SR 20 Deception Pass Bridge and Canoe Pass Bridge - Painting and Special Repair - #9344

Highway: SR 20    Region: Northwest    County: Island    Location: Milepost(s) 41.80 - 42.10
Contact: Shane Spahr, Project Engineer, 360-848-7103
Description: In 2019, WSDOT contractor crews from Eagle Industrial Painting will start at two year bridge painting and special repair project.
Project webpage
Work schedule:

  • Until further notice - Parking along SR 20 is limited during bridge painting work.
  • Until further notice - Loud sandblasting work could happen daily Monday through Saturday from 8 a.m. to 10 p.m. Visitors to the area and Deception Pass State Park should prepare for this noise and consider packing hearing protection for young children.
  • Until the morning of Friday, Oct. 18 - Crews will close one lane of SR 20 over Deception Pass and Canoe Pass bridges nightly from 8 p.m. to 6 a.m. for bridge painting work. Flaggers will alternate traffic through the open lane.
  • Sunday, Oct. 13, to the morning of Friday, Oct. 18 - Crews will close one lane of SR 20 over Deception Pass and Canoe Pass bridges nightly from 8 p.m. to 6 a.m. for bridge painting work. Flaggers will alternate traffic through the open lane.