South Central region construction and travel advisory

March 27 to April 5, 2020

No construction activities planned this week

 

Asotin County

Maintenance/Utility Operations:

SR 128 & SR 193 – CenturyLink - Utility Work

Highway: SR 128 / SR 193 Region: South Central County: Asotin/Whitman Location: SR 128 milepost 0 to 1 and SR 193 milepost 0.51 to 1
Contact: Jamil Anabtawi, WSDOT Utility Engineer, 509-577-1785

Project Description: CenturyLink will be performing utility work near the SR 128/SR 193 Intersection and the Red Wolf Bridge between milepost 0 and 1 and SR 193 from the intersection with SR 128.  

Current Week Traffic Advisory:
SR 128 and SR 193: Monday through Friday between 7 a.m. and 6 p.m., drivers should prepare for short delays as flaggers direct traffic through the work zone.  

 

Benton County

US 395 Pioneer Memorial Bridge – Bridge Painting Stage 1
Project # 9366


Highway: US 395 Region: South Central County: Benton & Franklin Location: 18.75 to 19
Contact: Alex Sanguino, Project Engineer, 509-222-2403
Project Description: This project provides for the improvement of US 395 MP 18.75 to MP 19 in Benton and Franklin Counties, by cleaning and painting the metal surfaces of the bridge and other work.
This project is due to be completed by Fall 2020

Current Week Traffic Advisory: 
Work activities are taking place under the bridge and will not affect traffic flow.  

I-82/SR 397 Interchange EB – Emergency Bridge Repair
Project # 9513


Highway: I-82 Region: South Central County: Benton Location: I-82 MP 114
Contact: Alex Sanguino, Project Engineer, 509-222-2403
Project Description: This project provides for the improvement Bridge 82/268 on I-82 from MP 114.39 to 114.41 in Benton County. This work shall include but is not limited to providing temporary traffic control and temporary detour as needed, installing concrete barrier, and an impact attenuator, installing delineation, removing one damaged girder, a portion of the concrete bridge deck and the concrete traffic barrier over that girder and other work.
This project is due to be completed by Fall 2020

Current Week Traffic Advisory:
This project on hold until April.
No significant traffic impacts anticipated this week.


SR 224 MP 5 (east of Keene Rd.) - City of West Richland – Paradise Way intersection and Utility extension
 
Contact:
Drew Woodruff, City of West Richland (509) 967-5434
Project Description: This is a developer project within the City of West Richland. Work includes widening the highway and constructing a new at-grade intersection along SR 224 with right- and left-turn channelization, illumination, sidewalk, and new utility installations.
 
Current Week Traffic Advisory: 
Drivers can expect trucks crossing the highway at MP 5 intermittently during daylight hours.

 

Maintenance/Utility Operations:
No significant traffic impacts anticipated this week.

 

Columbia County

Maintenance/Utility Operations:
No significant traffic impacts anticipated this week.

 

Franklin County

US 395 Safety Corridor Improvements & E Elm Rd to SR 17 SB  Paving
Project # 9451
Highway:
US 395 Region: South Central County: Franklin Location: US 395 milepost 24.64 to milepost 46.10
Contact: Alex Sanguino, Project Engineer, 509-222-2403
Project Description: This projects provides for the improvement of US 395 in Franklin County from MP 24.64 to MP 46.10 by rehabilitating the existing roadway, including crack sealing, planing, paving, illumination, ITS, furnishing and installing one cantilever sign structure, permanent signing, constructing acceleration and deceleration lanes, recessed pavement markers, rumble strips, roadway delineation, traffic control.
This project is due to be completed by Late July 2020. 

Current Week Traffic Advisory:

Approximately six miles north of Pasco:

US 395 NB and SB Milepost 25 to 26, Foster Wells Rd:
No significant traffic impacts anticipated this week.

US 395 NB Milepost 28 to 31, Phend Rd to Crest Loch Rd both:
No significant traffic impacts anticipated this week.

US 395 SB Milepost 29 to 30, Selph Landing Rd:
Right lane closure with reduced speed will remain in effect 24 hour a day, seven days a week for the roadway work added lanes, electrical and other miscellaneous work activities.

US 395 Milepost 31 to 33, Sagemoor Road: 
No significant traffic impacts anticipated this week.

US 395 Milepost 35 to 37, Eltopia Intersection: 
No significant traffic impacts anticipated this week. 

US 395 Milepost 36 near Elm Road to Milepost 45 near the SR 17: 
No significant traffic impacts anticipated this week.

US 395 / SR 17 Junction Southbound to Eltopia: 
No significant traffic impacts anticipated this week. 

 

US 395 Pioneer Memorial Bridge – Bridge Painting Stage 1
Project # 9366


Highway: US 395 Region: South Central County: Benton & Franklin Location: 18 to 19 
Contact: Alex Sanguino, Project Engineer, 509-222-2403
Project Description: This project provides for the improvement of US 395 milepost 18 to milepost 19 in Benton and Franklin Counties, by cleaning and painting the metal surfaces of the bridge and other work.
This project is due to be completed by Fall 2020
 
Current Week Traffic Advisory:
Work activities are taking place under the bridge and will not affect traffic flow.

Maintenance/Utility Operations:
No significant traffic impacts anticipated this week.

 

Garfield County

Maintenance/Utility Operations:
No significant traffic impacts anticipated this week. 

 

King County

I-90 MP 33 to 52 468th Ave SE to W Summit RD - Westbound Rehab Concrete 
Project # 9319

Highway:
I-90 Region: South Central County: King Location: I-90 milepost 33 to 52
Contact: Scott Golbek, WSDOT Project Engineer, 509-577-1810
Project description: This project is two seasons and will rehabilitate concrete panels and shoulders along this section of I-90. This project is to be completed sometime in late fall of 2020.

Bicycle detour is in affect for this project.  Detour starts at MP 54 WB Exit (SR 906/Hyak Interchange).  Detour maps can be found on a post just after turning left at the end of the exit ramp.

Current Week Traffic Advisory:
I-90 milepost 33 to milepost 52 westbound:

No significant traffic impacts anticipated this week. 


I-90 - 468th Ave SE to W Summit Rd Concrete, Deck & Culvert Rehab Eastbound 
Project # 9036


Highway: I-90 Region: South Central County: King Location: I- 90 milepost 34 to 52
Contact: Scott Golbek, WSDOT Project Engineer, 509-577-1810
Project description: This project repairs several sections of the eastbound lanes and repairs several bridge decks in the westbound lanes between North Bend and the summit of Snoqualmie Pass. This project is scheduled to be complete by Fall of 2020. 

Current Week Traffic Advisory:
I-90 eastbound milepost 34 near North Bend to milepost 52 near the summit of Snoqualmie Pass:

This project is shut down for the winter.

Maintenance/Utility Operations:
No significant traffic impacts anticipated this week.

 

Kittitas County

I-90 Hyak to Keechelus Dam Phase 1C-Add Lanes/Replace Snowshed
Project # 8127

Highway:
I-90 Region: South Central County: Kittitas Location: I-90 milepost 54 to 59
Contact: Jerry Wood, Project Engineer, 509-577-1859
Construction Began: Spring 2009
Scheduled Completion: Late Summer 2020
Project Description: Crews are building a wider and more reliable five-mile stretch of I-90 from Hyak to Keechelus Dam by adding lanes, replacing and adding bridges, stabilizing rock slopes and replacing the snowshed with avalanche bridges.

Weekly work schedule:
This project is shut down for the winter.

 

I-90 Bullfrog Rd Vic-Concrete Rehab, Bridge Deck Rehab and Painting
Project # 9385

Highway:
I-90 Region: South Central County: Kittitas Location: I-90 milepost 79 to milepost 82
Contact: Jerry Wood, Project Engineer, 509-577-1859

Project Description: This project provides for the improvement of I-90 by cleaning and painting the metal surfaces of the Cle Elum River Bridges, eastbound and westbound, heat straightening, steel repair, pier concrete spall repair, modifying expansion joints, scarifying concrete surfaces, further deck preparation, furnishing, placing, curing and texturing concrete overlay, also including non-bridge work by constructing and removing temporary roadway, constructing and removing temporary bridge replacing PCCP lanes and panels, cement concrete pavement grinding, weigh-in-motion replacement, guardrail installation, paving HMA shoulders, and roadway delineation. This project is due to be completed by Summer, 2021.

Current Week Traffic Advisory:
I-90 eastbound MP 79 to MP 81, Single Lane Closure:
No construction activities that affect travel. 

I-90 westbound MP 80 to MP 81, Single Lane Closure:
No construction activities that affect travel. 

 

I-90 - Yakima River Bridges Deck Repair 

Project # 9214
Highway:
I-90 Region: South Central County: Kittitas Location: I-90 milepost 86 and milepost 102
Contact: Jerry Wood, WSDOT Project Engineer, 509-577-1859
Project description: This project repairs the bridge decks in both directions near Cle Elum and Ellensburg. This project is scheduled to be completed Fall of 2020. 
Current Week Traffic Advisory:
I-90 Eastbound at MP 86 (Cle Elum Vicinity):

No scheduled traffic impacts this week.

I-90 Eastbound at MP 102 (Ellensburg Vicinity):
No scheduled traffic impacts this week.
 

I-90 and I-82 Ellensburg to Vantage Paving
Project # 9390

Highway:
I-90 and I-82 Region: South Central County: Kittitas Location: I-90 Milepost 121 to 136 and I-82 Milepost 0 to MP 4
Contact: Jerry Wood, Project Engineer, 509-577-1859
Project Description: This project provides for the improvement of 3.65 miles of E/B I-90, MP 121 to MP 126, 10.83 miles of W/B I-90, MP 125 to MP 136, 2.85 miles of of E/B I-82, MP .6 to MP 3.5, and 2.6 miles of W/B I-82, MP .6 to MP 3.2 by planning bituminous pavement, shoulder repair, crack sealing, paving with HMA pavement, pavement markings, guideposts; and .10 miles of I-90 from MP 136.6 to MP 136.7, by removing 3-strand cable barrier from the median and installing 4-strand cable barrier. This project is due to be completed by Fall of 2020. 

Current Week Traffic Advisory:

I-90 Eastbound Lane Closures:
No significant traffic impacts anticipated this week.

I-90 Westbound Lane Closures: 
No significant traffic impacts anticipated this week.

I-82 Eastbound and Westbound:
No significant traffic impacts anticipated this week.

 

SR 903 MP 1.6 - 2.0 (Peoh Ave to Billings Ave) – City of Cle Elum – First Street Stormwater & Billings Ave Intersection 
Contact: 
Mike Engelhart, City of Cle Elum (509) 674-2262
Project Description: This is a local agency project within the City of Cle Elum.  Work includes new stormwater and utility facilities, including new curb, gutter, sidewalk, HMA paving, and landscaping. 
Current Week Traffic Advisory: This project is suspended until further notice. 

Maintenance/Utility Operations:
No significant traffic impacts anticipated this week.

 

Lewis County

Maintenance/Utility Operations:
No significant traffic impacts anticipated this week.

 

Walla Walla County

Maintenance/Utility Operations:
No significant traffic impacts anticipated this week.

 

Yakima County

 

I-82 South Union Gap Interchange – Construct Ramps 
Project # 9247

Highway:
I-82 Region: South Central County: Yakima Location: I-82 milepost 37 
Contact: 
Scott Golbek, Project Engineer, 509-577-1810
Project Description:
This design build project will provide for the construction of a new eastbound off ramp, a new westbound on ramp and other work to complete the interchange of I-82 and US 97.
Construction Begins: Spring 2019
Scheduled Completion: Spring 2020

Current Week Traffic Advisory:

I-82 Eastbound:
No significant traffic impacts anticipated this week.

I-82 Westbound:
No significant traffic impacts anticipated this week.

US 97 northbound off ramp to Union Gap 
No significant traffic impacts anticipated this week

Exit 38 Westbound Off-Ramp:
No significant traffic impacts anticipated this week

Eastbound On-Ramp from Main Street:
No significant traffic impacts anticipated this week

 

US 97 – MP 61.28 to MP 71.47 & SR 223 – MP 0.36 to MP 0.64
Project # 9495

 

Highway: US 97 & SR 223 Region: South Central County: Yakima Location: US 97 – MP 61 to MP 71 & SR 223 – MP 0.36 to MP 0.64 
Contact:  
Scott Golbek, Project Engineer, 509-577-1810
Project Description:
This Contract provides for the improvement of US 97 from MP 61 to MP 62 at the intersection with SR 22, by installing “prepare to stop when flashing” beacons; US 97 from MP 66.35 to MP 66.64 at the intersection with Progressive Road and US 97 from MP 71.19 to MP 71.47 at the intersection with Lateral 1 Road, by installing “watch for entering traffic” beacons along US 97 and vehicle detectors on the intersecting road; SR 223 from MP 0.36 to MP 0.64 at the BNSF railroad crossing by installing advance warning bacons and guardrail and other work.
Construction Begins: Winter 2020 Scheduled Completion: Spring 2020

Current Week Traffic Advisory:

Lateral 1 Rd – US 97 MP 71.19 to MP 71.47
No significant traffic impacts anticipated this week

Progressive Rd – US 97 MP 66
No significant traffic impacts anticipated this week

SR 223 – MP 0.36 to MP 0.64
No significant traffic impacts anticipated this week

 

Maintenance/Utility Operations:
No significant traffic impacts anticipated this week