US 395 - North Spokane Corridor - Construction staging

Timeline of remaining North Spokane Corridor construction:

  1. Under construction: Columbia to Freya
  2. BNSF 2nd Railroad Realignment - Construction starts 2019
  3. Spokane River to Columbia - Construction starts 2020
  4. Wellesley Ave. Improvements - Construction starts 2020
  5. Sprague Ave. to Spokane River Phase 1 - Construction starts 2020
  6. Spokane River Crossing - Construction starts 2021
  7. Sprague Ave. to Spokane River Phase 2 - Construction starts 2022
  8. I-90 to Sprague Ave. - Construction starts 2023

NSC Construction Staging to I-90

Construction staging of the North Spokane Corridor to I-90.