US 2 - I-90 to Euclid - Paving

Project news

Awarded to CPM Development Corporation/DBA Inland Asphalt of Spokane Valley with a construction bid of $4,046,000.  

Needs & Benefits

This project consists of grinding out an existing layer of asphalt on Division Street, Ruby Street and Browne Street, then resurfacing with hot mix asphalt. The job includes some ADA sidewalk ramp improvements and other work.  When completed, the roadway surface will be smooth.

Timeline

Work is planned to start in spring 2018, depending on weather.  The work should take about 14 weeks to complete.

Funding

Financial Data for PIN 600228I, 600228R
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $4,597
CWA $0
Total $4,597

Contact

Al Gilson, communications, 509-324-6015
Chad Simonson, project engineer, 509-324-6252

WSDOT Eastern Region
2714 N. Mayfair
Spokane, WA  99207

US 2/I-90 to Euclid-Small Project Map