US 2 - I-90 to Euclid - Paving - Complete October 2018

Project news

Awarded to CPM Development Corporation/DBA Inland Asphalt of Spokane Valley with a construction bid of $4,046,000.  

Needs & benefits

This project consists of grinding out an existing layer of asphalt on Division Street, Ruby Street and Browne Street, then resurfacing with hot mix asphalt. The job includes some ADA sidewalk ramp improvements and other work.  When completed, the roadway surface will be smooth.

Timeline

All work was completed in October 2018.

Funding

Financial Data for PIN 600228I, 600228R
Amount ($ in thousands)

  • Pre-Existing Funds (PEF) - $4,597
  • Total - $4,957

Contact

Beth Bousley, communications, 509-324-6015
Chad Simonson, project engineer, 509-324-6252

WSDOT Eastern Region
2714 N. Mayfair
Spokane, WA  99207

US 2/I-90 to Euclid-Small Project Map