US 2 - Hayford Road to Deer Heights Road - Median Channelization

Project news

The project was awarded to Cameron-Reilly, LLC on March 15. The center two-way, left-turn lane in the vicinity of the project will be closed for the duration of the project. Expect single lane closures and access impacts between the hours of 7 p.m. and 6 a.m.

Needs & benefits

Revises the channelization and illumination near Hazelwood Road in Airway Heights.

Timeline

Work began April 15 and will last through early summer 2019.

Funding

Pre-Existing Funds (PEF) - $329,706

Contact

Tom Brasch, project engineer
2714 N. Mayfair St.
Spokane, WA 99207
(509) 323-8411