SR 240 - Richland Corridor Improvements

Project news

  • Design for this project is expected to start fall 2018.

Needs & Benefits

SR 240 in Richland is experiencing increased congestion at several existing intersections. This project will improve safety and operational effiiciency by adding acceleration and deceleration lanes, adding double-left turn lanes and upgrading traffic signals.

Timeline

Fall 2018 - Design work begins
Spring 2020 - Construction begins
Fall 2020 - Scheduled completion

Funding

Financial Data for PIN 524003O
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $0
CWA $5,000
Total $5,000

Contact

Alex Sanguino
WSDOT Project Engineer
509-222-2403

Meagan Lott
WSDOT Communications
509-577-1618

Project map of planned improvements on SR 240 near Richland.