SR 20 - Republic to US 395 - Chip Seal - Complete September 2019

Project news

This project was awarded to Central Washington Asphalt Inc.

Needs & benefits

These sections of the chip seal will rehabilitate existing bituminous pavement to preserve and maintain pavement structure. All sections will receive bituminous surface treatment, fog seal and rumble strips. Not all sections, but most will receive crack seal, pavement repair, prelevel, and guardrail.

Timeline

Project expected to start May 28 and be completed in September 2019.

Funding

Financial Data for PIN 602030W
Amount ($ in thousands)

  • Pre-Existing Funds (PEF) - $4,914
  • Total - $4,914

Contact

Ryan Overton, communications
2714 N. Mayfair St.
Spokane WA, 99207
(509) 324-6014

Location of Chip Seal along SR 20 from Republic to US 395.