I-90 - SR 21 to Ritzville - Paving - Complete November 2019

Needs & benefits

This project will restore 9.9 miles of the existing asphalt pavement by grinding and placing 0.15 foot depth of asphalt on the driving lanes and shoulders. The project will extend between the Lind and Ritzville interchanges.

Timeline

Construction began on April 15. All contract work was completed the week of June 10. Minor items remain.

Funding

Financial Data for PIN 609020I
Funding Source Amount ($ in thousands)

  • Pre-Existing Funds (PEF) - $8,036
  • Total - $8,036

Contact

Tom Brasch, project engineer
2714 N. Mayfair St.
Spokane, WA 99207
(509) 323-8411

Location of paving from SR 21 to Ritzville