Eastern Region 2018 Chip Seal

Project news

Awarded to Central Washington Asphalt, Inc. of Moses Lake, WA with a construction bid of $8,887,511.

Needs & Benefits

Approximately 144 miles of rural highways will be "chip-sealed" in northeast Washington.

Timeline

Work should start in early May, depending on weather, and be completed in 2018.

Funding

Financial Data for PIN 600045E, 602102E, 602107E, 602110X, 602508V, 602509O, 626104Y
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $8,885
CWA $1,373
Total $10,258

Contact

Chad Simonson, project engineer
WSDOT Eastern Region
2714 N. Mayfair
Spokane, WA  99207
509-324-6000
 