Define the construction sequence timeline.

Item Description
Construction Sequence Timeline Grid listing the timeline events. Press [Edit] to edit event details.
[Add] Press to add an event to the timeline
[Remove] Select an event and press to remove it from the timeline.

Construction Sequence Timeline Grid

This grid lists the Construction Events in the Construction Sequence Timeline. You can edit the following fields in the grid by clicking in the cell and entering the appropreate information:

  • Occurance - Enter the day when the construction event begins
  • Elapsed Time - Enter the elapsed time to the next construction event. The minimum elapsed time is the duration of the longest activity in the event.
  • Description - Enter a description for the construction event.

NOTE: Changing the occurance or elapsed time of one event to will cause the other events to be automatically adjusted.

See Construction Sequence in the User Guide for more details about modeling the construction sequence timeline.