October 14, 1994
TO: C. C. Ruth/J. E. McMurry
Bridge and Structures Office, 7340
FROM: T. L. Nelson/J. A. Weigel
SUBJECT: Post Tensioning Shop Drawings
For the last few years, Avar Construction Systems, Inc. has been supplying a majority of post tensioning systems for our bridges. Their shop drawings never include the force after anchor set. This for after anchor is required for the following two reasons:
If the measured elongation is not within 7% of the calculated elongation, a force verification lift off is performed. If this force verifications lift off is within -1% of the calculated force after anchor set and .07 fs, the tendon can be accepted. The approved calculated force after anchor set is required to accept[t the stressed tendon.
Section 6-02.3(26)A of the Standard Specifications requires this calculated force after anchor set (lift-off force).
I request that all designers reviewing post tensioning shop drawings be aware of and enforce this contract requirement.
Thank you very much.
TLN/JAW