US 395 - Deer Park Corridor Safety Improvements - Roundabouts

Project news

  • The Contract was awarded to Inland Asphalt Paving on May 2nd with a bid of $2,959,959.
  • WSDOT will be holding an Open House in Deer Park the beginning of June to update the residents on the schedule and traffic considerations during construction.

Needs & Benefits

Intersections in the Deer Park area experience a higher than average number of "entering at angle" collisions. These are crashes where drivers enter the roadway into the path of oncoming vehicles.  This project entails construction of single lane roundabouts at the Short/Main and Monroe/Crawford intersections in Deer Park, WA.  Turning modifications will be built at the Burroughs/Dalton intersection.  Roundabouts should reduce the frequency and severity of "entering at angle" collisions at these locations.

Timeline

The contractor is still working out a project schedule, but is anticipating that work will begin mid-June.  The work should be complete by the end of September.

Funding

Federal & State PEF = $4,539,170.

Contact

Tom Brasch, project engineer
WSDOT Eastern region
2714 N. Mayfair
Spokane, WA  99207
509-324-6000

US 395 Deer Park Roundabout Map