Project news​

US 395 was resurfaced with hot mix asphalt.  ADA sidewalk work was included.  Some minor corrective items remain.  Central Washington Asphalt of Moses Lake, WA handled the project with a construction bid of $3,491,873.

Needs & benefits

High traffic volumes with normal wear and tear had deteriorated the pavement surface. Resurfacing provides a better experience for drivers with a reduced need for repairs and patching.

Timeline

The project was mostly constructed during 2017.  A few corrective items reamin as of March 27, 2018.

Funding

Financial Data for PIN 639522T
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $4,349
CWA $0
Total $4,349


Contact

Mark Allen, Project Engineer
WSDOT Eastern Region
2714 N. Mayfair
Spokane, WA 99207
509-324-6000

Small Project Locator Map