SR 525 - Mukilteo Multimodal Terminal - Project timeline

Project Timeline

2004

  • NEPA Environmental Assessment (EA)
  • EA public scoping meetings and comment period

2006

  • Determine environmental impacts require further analysis in an Environmental Impact Statement (EIS)
  • FTA issues a notice of intent (NOI) to prepare an EIS (February 2006)
  • NEPA EIS scoping process
  • EIS public scoping meetings

2007

  • Washington State Legislature puts Mukilteo Multimodal Project on hold

2007- 2009

  • Study cultural resources and conduct geotechnical investigations
  • Revise concepts to address public comments, minimize effects to sensitive resources, and meet seismic standards

February 2010

  • WSF and FTA reinitiate NEPA/SEPA EIS process

Spring 2010

  • Revise the project purpose and need statement

Fall 2010

  • Conduct NEPA EIS scoping process and comment period
  • Hold public scoping meetings

2011

  • Prepare Draft EIS

January-March 2012

  • Draft EIS public hearings and comment period

June 2013

  • Publish Final EIS

August 2014

  • Issue Record of Decision (ROD)

2014-2016

  • Final design

Spring 2015-Winter 2017 

  • Construction phase 1 (Remove tank farm pier)

2017- 2020

  • Construction phase 2
  • September 2017-September 2018: trestle and bridge seat
  • January-October 2018: deep stormwater utilities
  • December 2018: contract for uplands work awarded to IMCO Construction
  • Early 2019-2020: Main terminal building, holding lanes, toll plaza, promenade

2020

  • Project complete and new terminal opens for service