Eastern Region Intersection Safety Implementation - Completed November 2016

Overview
The project scope was to reduce collision incidence and reduce collision severity at selected intersections through the implementation of low cost countermeasures. The selected improvements included paint striping, durable striping, signing, and foliage removal where required to improve intersection sight distance.

How you benefit

Improves safety
This project addressed safety improvements at 48 intersections located throughout the Eastern Region with a goal of fewer and less severe collisions.

Partnerships & cooperation
WSDOT partnered with several Counties with agreements to place signage within their right of way. The Counties will maintain those signs.

 

Funding

Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $820
CWA $0
Total $820

 

Contact us
Beth Bousley, Communications
WSDOT Eastern Region
2714 N. Mayfair
Spokane, WA  99207
509-324-6015