WSDOT Logo


MODERATE IMPACT
I-5 Southbound - Monday, November 23 Crews will close up to two right lanes on southbound I-5 between Northgate Way and NE 50th Street from 9 p.m. until 5 a.m. for pavement grinding work.
From milepost 173 to milepost 170
MODERATE IMPACT
I-5 Southbound - Construction on I-5 at MAYTOWN (EXIT 95) southbound nightly from 10:00 PM to 5:00 AM beginning 11/23/2009 until 11/25/2009 - expect the southbound I-5 off-ramp at Maytown (exit 95) closed
At milepost 95
MODERATE IMPACT
I-5 Both Directions - Construction on I-5 from THURSTON-LEWIS COUNTY LINE to SR 121 both directions daily from 7:30 AM to 7:00 PM beginning 11/23/2009 until 11/25/2009 - expect rolling slowdowns and up to five-minute delays
From milepost 86 to milepost 95
MODERATE IMPACT
I-5 Northbound - Construction in the right lane on northbound I-5 at Marine View Dr beginning at 11/23/2009 10:00 PM until 11/25/2009 6:00 AM
At milepost 195
MODERATE IMPACT
I-5 Southbound - Construction on the southbound I-5 off ramp to 196th St SW/SR 524 beginning at 11/23/2009 9:00 PM until 11/24/2009 5:00 AM
At milepost 182
MODERATE IMPACT
I-5 Northbound - Construction on I-5 from PORT OF TACOMA ROAD to PIERCE-KING COUNTY LINE northbound nightly from 7 p.m. to 4 a.m. beginning 11/23/2009 until 11/25/2009 - two left lanes closed
From milepost 136 to milepost 139
MODERATE IMPACT
I-5 Northbound - Construction in up to two lanes on northbound I-5 at 88th St NE beginning at 11/23/2009 7:00 PM until 11/25/2009 6:00 AM
At milepost 200
MODERATE IMPACT
I-5 Northbound - Construction in the right lane on northbound I-5 at 172nd St/SR 531 northbound beginning at 11/23/2009 7:00 PM until 11/24/2009 5:00 AM
At milepost 206
MODERATE IMPACT
I-5 Both Directions - Construction on I-5 from SR 11/Chuckanut Drive to SR 542/Sunset Dr both directions beginning at 11/23/2009 8:00 PM until 11/25/2009 6:00 AM Crews will work from 8 PM to 6 AM Monday and Tuesday nights to install cable barrier posts.
From milepost 250 to milepost 255
MODERATE IMPACT
I-5 Southbound - Construction closes the right lane on southbound I-5 at the I-90 interchange beginning at 11/23/2009 9:00 PM until 11/24/2009 5:00 AM
At milepost 164
MODERATE IMPACT
I-5 Southbound - Crews will close the left lane of the southbound collector-distributor to I-90 where it crosses over I-5 beginning at 11/23/2009 9:00 PM until 11/24/2009 5:00 AM for construction work.
At milepost 164
MODERATE IMPACT
I-5 Northbound - Two right lanes closed on northbound I-5 from SR 900 to S Othello St nightly beginning at 11/23/2009 7:00 PM until 11/24/2009 5:00 AM for construction work.
From milepost 157 to milepost 160
MODERATE IMPACT
I-5 Northbound - Two left lanes of northbound I-5 closed from Albro to S Spokane St/W Seattle Freeway/Columbian Way nightly beginning at 11/23/2009 7:00 PM until 11/24/2009 5:00 AM for construction work.
From milepost 161 to milepost 163
MODERATE IMPACT
I-5 Northbound - Construction on northbound I-5 from Mid Boeing Field to Corson closes the left lane nightly beginning at 11/23/2009 7:00 PM until 11/25/2009 5:00 AM
From milepost 160 to milepost 162
MODERATE IMPACT
I-5 Northbound - Exit ramp closed, entrance ramp closed on I-5 Express lanes at Pine Street until further notice.
At milepost 166
MODERATE IMPACT
I-5 - Major road construction, exit ramp closed on I-5 at Olive Way since 10:39 AM, 05/21/09 until further notice
At milepost 166
LOW IMPACT
I-5 Both Directions - I-5, Both directions at the SR 500 Interchange (milepost 1.9) Nov. 23-25: Daytime intermittent shoulder closures for geotechnical work.
At milepost 2
LOW IMPACT
I-5 Northbound - Construction on I-5 from milepost 69.44 to milepost 82.73 northbound beginning at 06/05/2009 10:16 AM until further notice. I-5, Koontz Road to Harrison Avenue - Paving Nov. 23-27: No traffic impacts scheduled. Remaining work on this project is highly weather dependent and will be suspended through the winter season. Work will resume in spring 2010.
From milepost 69 to milepost 83
LOW IMPACT
I-5 Both Directions - Construction on I-5 from milepost 13.39 to milepost 14.60 both directions I-5 SR 501 Ridgefield Interchange Nov. 23-25, 7 a.m.-5:30 p.m.: Daytime intermittent flagging on SR 501 at the I-5 on-and off-ramps for trucks to entering and exiting the work zone. Work will conclude by 12 p.m. on Wednesday, Nov. 25. Nov. 23-24, 6 p.m.-5 a.m.: Nighttime left lane closures both directions on I-5 for pre-construction activities.
From milepost 13 to milepost 15