Skip Top Navigation

Olympic Region Weekly Construction and Traffic Updates

Please note: Activities may be subject to weather-related adjustments. If a highway is not listed below, there are no scheduled closures. Please note emergency lane closures may still occur.

Counties: Clallam | Grays Harbor | Jefferson | Kitsap | Mason | Pierce | Thurston


 
Map of Olympic Region area


The following activities are scheduled for Friday, Feb. 9, through Friday, Feb. 16.

View Clallam County construction map (pdf 239 kb)

CONSTRUCTION 

US 101 - Elwha River Bridge
Highway:
US 101 Region: Olympic County: Clallam Location: Milepost(s) 238.7 to 239.5
Contact: Doug Adamson, 360-357-2716
Description:  Bridge is open around the clock with no restrictions.

Crews continue to monitor the bridge. For more information, please visit elwhariverbridge.com.

Lake Crescent Highway Rehab Project
Highway:
US 101 Region: Olympic County: Clallam
Contact: Olympic National Park; Penny Wagner, 360-565-3005
Description: The National Park Service & Federal Highway Administration will rehabilitate 12 miles of Highway 101 around Lake Crescent and 4 miles of East Beach Road to address safety and long‐term maintenance issues.
Work schedule: Work on the Lake Crescent US 101 project is officially shutdown for winter. Travelers around Lake Crescent will not encounter any road work, traffic lights or delays associated with the project until it resumes in mid-March.

There are no traffic signals in place, however, the lanes in that section around milepost 229 will be narrower than usual until further road work is completed.  A reduced speed limit is in effect in that area and road signs warn drivers of the narrow lanes.

The rock scaling and bolting work is now complete. Both lanes in the rock wall area were paved to repair road damage and that section is restored to two lanes.


MAINTENANCE

Highway: US 101 Region: Olympic County: Clallam Location: Milepost(s) 255 to 255.5
Contact: Steve Russell, 360-565-0680
Description: Debris removal
Work Schedule: 8 a.m. to 12 p.m. Thursday, Feb. 22.

Highway: US 101 Region: Olympic County: Clallam Location: Milepost(s) 256 to 256.5
Contact: Steve Russell, 360-565-0680
Description: Debris removal from the intersection of US 101 and Blue Mountain Road.
Work Schedule: 12 p.m. to 4 p.m. Thursday, Feb. 22.

Highway: US 101 Region: Olympic County: Clallam Location: Milepost(s) 267 to 271
Contact: Steve Russell, 360-565-0680
Description: Guidepost maintenance
Work Schedule: 8 a.m. to 4 p.m. each day Tuesday, Feb. 20 through Friday, Feb. 23. 

Highway: US 101 Region: Olympic County: Clallam Location: Milepost(s) 252 to 252.2
Contact: Steve Russell, 360-565-0680
Description: Debris removal. Drivers should expect a right eastbound lane closure.
Work Schedule: 8 a.m. to 3 p.m. Wednesday, Feb. 21.

Highway: SR 112 Region: Olympic County: Clallam Location: Milepost(s) 61 to 38
Contact: Steve Russell, 360-565-0680
Description: Debris removal. Travelers should expect one-way alternating traffic in both directions.
Work Schedule: 8 a.m. to 4 p.m. each week day beginning Tuesday, Feb. 20–Friday, Feb. 23.

toptop

Grays Harbor County


View Grays Harbor County construction map
(pdf 166 kb)

CONSTRUCTION

SR 8 - Middle and East Forks Wildcat Creek - Remove Fish Barriers
Highway: SR 8 Region: Olympic County: Grays Harbor Location: Milepost(s) 4.3 to 7.5
Contact: John Romero, 360-538-8500
Description: The eastbound lanes have been reconfigured to accommodate both directions of traffic. Traffic will remain in this configuration through spring of 2019.  The changes allow crews to remove barriers to fish by constructing bridges across the Middle and East Forks of Wildcat Creek.
Project web page
Work schedule: Around-the-clock traffic switch. 

MAINTENANCE

Highway: SR 8 Region: Olympic County: Grays Harbor Location: Milepost(s) 0 to 20.67
Contact: Brent Schiller, 360-538-8532
Description: Cable barrier inspections.
Work Schedule: 6:30 p.m. each night Friday, Feb. 9 through Sunday, Feb. 25, until 3:30 a.m. each following day.

Highway: US 12 Region: Olympic County: Grays Harbor Location: Milepost(s) 9 to 21
Contact: Brent Schiller, 360-538-8532
Description: Cable barrier inspections.
Work Schedule: 6:30 p.m. each night Friday, Feb. 9 through Sunday, Feb. 25, until 3:30 a.m. each following day.

Highway: US 12 Region: Olympic County: Grays Harbor Location: Milepost(s) 9.4 to 21
Contact: Brent Schiller, 360-538-8532
Description: Shoulder sweeping in both directions. Drivers will see a mobile right lane closure.
Work Schedule: 7:30 a.m. to 4 p.m. Thursday, Feb. 22.

Highway: US 101 Region: Olympic County: Grays Harbor Location: Milepost(s) 73.7 to 73.8
Contact: Brent Schiller, 360-538-8532
Description: Debris removal along northbound US 101. Drivers should expect one way alternating traffic.
Work Schedule: 7:30 a.m. to 4 p.m. each week day beginning Monday, Feb. 19 through Thursday, Feb. 22. 

Highway: SR 107 Region: Olympic County: Grays Harbor Location: Milepost(s) 7.7 to 7.9
Contact: Brent Schiller, 360-538-8532
Description: Guard rail repair in the northbound direction of SR 107. Drivers should expect one way alternating traffic.
Work Schedule: 8 a.m. to 4 p.m. Tuesday, Feb. 20.

toptop

Jefferson County 

View Jefferson County summer construction map  (pdf 239kb)

CONSTRUCTION 

SR 104 – Hood Canal Bridge – Special Repair
Highway: SR 104 Region: Olympic County: Jefferson Location: Milepost(s) 13.9 to 15.4
Contact: Michele Britton, 360-874-3000
Description:  Crews are replacing the internal mechanics of the Hood Canal Bridge draw span.
Project web page 
Work Schedule: No scheduled construction.

Drivers are strongly advised to sign up to receive automated messages for up to date bridge information. 

MAINTENANCE 

Highway: SR 20 Region: Olympic County: Jefferson Location: Milepost(s) 0.1 to 6
Contact: Steve Russell, 360-565-0680
Description: Debris removal.
Work Schedule: 8 a.m. to 4:30 p.m. each Tuesday through Thursday, Feb. 6-Mar. 8.

Highway: SR 116 Region: Olympic County: Jefferson Location: Milepost(s) 0.1 to 3
Contact: Steve Russell, 360-565-0680
Description: Debris removal.
Work Schedule: 8 a.m. to 4 p.m. each Tuesday through Thursday Feb. 6-Mar. 8.

Highway: SR 116 Region: Olympic County: Jefferson Location: Milepost(s) 0.1 to 3
Contact: Steve Russell, 360-565-0680
Description: Debris removal.
Work Schedule: 8 a.m. to 4 p.m. each Tuesday through Thursday, Feb. 13-Mar. 8

top

View Kitsap County construction map (pdf 420kb)

CONSTRUCTION 

SR 104 – Hood Canal Bridge – Special Repair
Highway: SR 104 Region: Olympic County: Kitsap Location: Milepost(s) 13.9 to 15.4
Contact: Michele Britton, 360-874-3000
Description:  Crews are replacing mechanics that operate the Hood Canal Bridge draw span.
Project web page
Work Schedule:  No scheduled construction. Drivers are strongly advised to sign up to receive automated messages for the latest information.

SR 305 – Olympic Drive Non-Motorized Improvements  –  Sound to Olympics Trail 
Highway: SR 305 Region: Olympic County: Kitsap Location: Milepost(s) .01 -.23 and .23 - .97
Contact: City of Bainbridge Island, 206-842-2016
Description: Crews working for the City of Bainbridge Island have two separate projects that will have traffic impacts between High School Road and the Bainbridge Island Ferry terminal.
Project web page


MAINTENANCE 

Highway:
SR 3 Region: Olympic County: Kitsap Location: Milepost(s) 28.2 to 32.54
Contact: James Narramore, 360-570-6747
Description: Utility work. 
Work Schedule:

  • Shoulder closures in both directions: 8 a.m. to 4:30 p.m. each weekday through Friday, Feb. 16.
  • Westbound right lane closure: 8 a.m. to 4:30 p.m. each weekday from Monday through Friday, Feb. 5-9.

Highway: SR 305 Region: Olympic County: Kitsap Location: Milepost(s) 6.7 to 7.2
Contact: Tony Kilmer, 360-357-2763
Description: Bridge maintenance.
Work Schedule: 8:30 a.m. to 3 p.m. Tuesday, Feb 20 through Thursday, Feb. 22. 

Highway: SR 305 Region: Olympic County: Kitsap Location: Milepost(s) 6.7 to 7.2
Contact: Tony Kilmer, 360-357-2763
Description: Bridge maintenance. Drivers should expect one way alternating traffic.
Work Schedule: 8:30 a.m. to 3 p.m. Sunday through Saturday beginning Feb. 20-Mar. 2. Weekend maintenance will begin at 7:30 a.m.

Highway: SR 305 Region: Olympic County: Kitsap Location: Milepost(s)  6.8 to 7
Contact: Doug Adamson, 360-357-2716
Description: WSDOT annual Agate Pass Bridge cleaning and inspection. Traffic will be reduced to one-way alternating traffic.

Drivers are advised to expect up to 30 minutes delays if not longer during the work. 

Work Schedule:

Each day from Tuesday, Feb. 20, through Friday, March 2 
8:45 a.m. to 3 p.m. weekdays
7:45 a.m. to 2 p.m. Saturday and Sunday, Feb. 24-25 

toptop

Mason County


View Mason County summer construction map  (pdf 420kb)

CONSTRUCTION

No scheduled construction activities.

MAINTENANCE

Highway:
SR 3 Region: Olympic County: Mason Location: Milepost(s) 28.2 to 32.5
Contact: James Narramore, 360-570-6747
Description: Shoulder closures for utility work. 
Work Schedule: 8 a.m. to 4:30 p.m. each weekday through Friday, Feb. 16. 

toptop

Pierce County


View Pierce County summer construction map (pdf 307kb)

CONSTRUCTION

Tacoma/Pierce County HOV Program

I-5 - M Street to Portland Avenue - HOV

Highway:
I-5 Region: Olympic County: Pierce Location: Milepost(s) 132.8 - 134.4 
Contact:
Gaius Sanoy, 253-365-6700
Description: This project rebuilds Pacific Avenue and McKinley Way bridges spanning I-5. It builds a new northbound SR 7/I-705 bridge, and widens I-5 to accommodate northbound and southbound HOV lanes from M Street to the vicinity of the L Street bridge.
Project web page

I-5 - SR 16 Realignment - HOV Structure and Connections
Highway(s):
I-5 Region: Olympic County: Pierce Location: Milepost(s) SR 16 0.1 to .7 I-5 130.9 to 133.5 

Contact: Gaius Sanoy, 253-365-6700
Description: This project is the final of a three stage effort to rebuild the Nalley Valley interchange. During the final phase, crews will build ramps that create new HOV lanes between I-5 and SR 16. The project will also realign I-5 to accommodate HOV ramps.
Project web page

I-5 - Portland Avenue to Port of Tacoma Road - Northbound HOV
Highway:
I-5  Region: Olympic  County: Pierce  Location: Milepost(s) 134 - 136
Contacts: Brenden Clarke, 360-412-3420
Description: This project builds new HOV lanes on I-5 in Tacoma and Fife, and a new northbound I-5 Puyallup River Bridge. 
Project web page


Friday, Feb. 16
• Portland Avenue on-ramp to southbound I-5 will close from 11:59 p.m. to 6 a.m. Saturday.
• Southbound I-5 exit to I-705 and 26th Street will close from 11:59 p.m. to 6 a.m. Saturday.

Thursday night lane closures
Overnight drivers in Tacoma will want to pay attention to lane closures on northbound I-5. From 11:59 p.m. Thursday, Feb. 22 to 3 a.m. Friday, Feb. 23, crews will detour all lanes of northbound I-5 through the Portland Avenue interchange and across the new Puyallup River Bridge. Law enforcement will be at the Portland Avenue intersection to assist with traffic control.

Monday, Feb. 19
• Southbound I-5 collector/distributor will close from 10 p.m. to 6 a.m. Tuesday. Drivers heading to I-705, SR 7 and SR 16 will detour via southbound I-5 to the South 56th interchange to northbound I-5.
• Northbound SR 167 ramp to southbound I-5 will close from 10 p.m. to 6 a.m. Tuesday.
• Portland Avenue on-ramp to southbound I-5 will close from 10 p.m. to 6 a.m. Tuesday.
• Southbound I-5 exit to I-705, SR 7 and 26th Street will close from 10 p.m. to 6 a.m. Tuesday.

Tuesday, Feb. 20
• Southbound I-5 collector/distributor will close from 10 p.m. to 6 a.m. Wednesday. Drivers heading to I-705, SR 7 and SR 16 will detour via southbound I-5 to the South 56th interchange to northbound I-5.
• Northbound SR 167 ramp to southbound I-5 will close from 10 p.m. to 6 a.m. Wednesday.
• Portland Avenue on-ramp to southbound I-5 will close from 10 p.m. to 6 a.m. Wednesday.
• Southbound I-5 exit to I-705, SR 7 and 26th Street will close from 10 p.m. to 6 a.m. Wednesday.

Wednesday, Feb. 21
• Southbound I-5 collector/distributor will close from 10 p.m. to 6 a.m. Thursday. Drivers heading to I-705, SR 7 and SR 16 will detour via southbound I-5 to the South 56th interchange to northbound I-5.
• Northbound SR 167 ramp to southbound I-5 will close from 10 p.m. to 6 a.m. Thursday.
• Portland Avenue on-ramp to southbound I-5 will close from 10 p.m. to 6 a.m. Thursday.
• Southbound I-5 exit to I-705, SR 7 and 26th Street will close from 10 p.m. to 6 a.m. Thursday.

Thursday, Feb. 22
• Southbound I-5 collector/distributor will close from 11 p.m. to 6 a.m. Friday. Drivers heading to I-705, SR 7 and SR 16 will detour via southbound I-5 to the South 56th interchange to northbound I-5.
• Northbound SR 167 ramp to southbound I-5 will close from 11 p.m. to 6 a.m. Friday.
• Portland Avenue on-ramp to southbound I-5 will close from 11 p.m. to 6 a.m. Friday.
• Southbound I-5 exit to I-705, SR 7 and 26th Street will close from 11 p.m. to 6 a.m. Friday.

Friday, Feb. 23
• Southbound I-5 collector/distributor will close from 11:59 p.m. to 6 a.m. Saturday. Drivers heading to I-705, SR 7 and SR 16 will detour via southbound I-5 to the South 56th interchange to northbound I-5.
• Northbound SR 167 ramp to southbound I-5 will close from 11:59 p.m. to 6 a.m. Saturday.
• Portland Avenue on-ramp to southbound I-5 will close from 11:59 p.m. to 6 a.m. Saturday.
• Southbound I-5 exit to I-705, SR 7 and 26th Street will close from 11:59 p.m. to 6 a.m. Saturday.


Single and double lane closures are scheduled each night on northbound and southbound I-5 between Port of Tacoma Road to South 38th Street and on the eastbound SR 16 ramp to northbound I-5.

Long-term ramp closure:
The southbound I-5 ramp to SR 7 has reopened. During the closure, crews reconstructed the ramp so it matches the new alignment of I-5. Crews also built permanent stormwater treatment ponds, drainage and electrical components, and advanced work on the McKinley Way overpass.

I-5 Mounts Rd to Center Dr. - Auxiliary Lane Extension
Highway: I-5 Region: Olympic County: Pierce Location: Milepost(s) 116.3 to 118.5
Contact: Jon Keeth, 253-365-6700
Description: Crews will build a new auxiliary lane on northbound I-5 between Mounts Road and Center Drive.
Project web page.
Work Schedule: Overnight single and double lane closures and ramp closures on northbound I-5 for the week of Feb. 12 for striping activities. Work is weather dependent.
Ramp Closures

  • The Mounts Road on ramp to northbound I-5, the weigh station exit and the northbound I-5 exit to Center Drive (#118) will close each night between the hours of 11 p.m. and 4 a.m.

Lane Closures

  • Mon. - Wed. lane closures are from 8 p.m. to 5 a.m. each following day.
  • Thursday - lane closures are from 10 p.m. to 5 a.m. the following day.
  • Friday - lane closures are from 8 p.m. to 8 a.m. the following day.

I-5 Mounts Road Rail Bridge Repair
Highway:
I-5 Region: Olympic County: Pierce Location: Milepost(s) 115.8
Contact: Sound Transit
Description: Crews working for Sound Transit are making operational repairs to the rail bridge.
Work Schedule: No work scheduled.

I-5 Mounts Rd Vicinity VMS Install
Highway:
I-5 Region: Olympic County: Pierce Location: Milepost(s) 116.2
Contact: Jon Keeth, 253-365-6700
Description: Crews are installing a new variable message sign on northbound I-5 before Mounts Road.
Work Schedule: 
No work scheduled.

SR 16, Union Ave to Jackson Ave. - ADA Ramps
Highway:
SR 16 Region: Olympic County: Pierce Location: Milepost(s) 1.9 to 3.5
Contact: Michele Britton, 360-874-3000
Description: Crews will replace existing curb ramps and upgrade crosswalk signs. No current impacts to traffic.

MAINTENANCE  

Highway: I-5 Region: Olympic County: Pierce Location: Milepost(s) 118.1 to 118.2
Contact: Jeff Hastings, 253-983-7550
Description: Environmental cleanup.
Work Schedule: 8 a.m. to 4 p.m. each weekday from Monday, Feb. 19 through Friday, Feb. 23. Drivers should expect to see a northbound left shoulder closure on the on ramp from Center Dr. to northbound I-5.

Highway: I-5 Region: Olympic County: Pierce Location: Milepost(s) 122.4
Contact: Chris Ehresmann, 253-570-6749
Description: Utility work. Drivers can expect northbound I-5 shoulder closure. The northbound I-5 exit to Berkeley will also have a shoulder closure.
Work Schedule: 9 a.m. to 4 p.m. each weekday from Wednesday, Feb. 14 to Friday, March 2. No work scheduled on Monday, Feb. 19.

Highway: I-5 Region: Olympic County: Pierce Location: Milepost(s) 137.65 to 137.67
Contact: Jeff Hastings, 253-983-7550
Description: Shoulder repair. Drivers will see a northbound ramp right shoulder closure.
Work Schedule: 8 a.m. to 3 p.m. Friday, Feb. 23. 

Highway: SR 7 Region: Olympic County: Pierce Location: Milepost(s) 28.1 to 28.3
Contact: Jeff Hastings, 253-983-7550
Description: Vegetation management. Drivers should expect up to 15 minute delays in the northbound direction. 
Work Schedule: 5 a.m. to 11 a.m. Friday, Feb. 23. 

Highway: SR 161 Region: Olympic County: Pierce Location: Milepost(s) 17.58 to 32
Contact: Jeff Hastings, 253-983-7550
Description: Sweeping in both directions. Drivers will see a mobile right lane closure.
Work Schedule: 5 a.m. to 11 a.m. Thursday, Feb. 22. 

Highway: SR 167 Region: Olympic County: Pierce Location: Milepost(s) 5 to 6
Contact: Jeff Hastings, 253-983-7550
Description: Southbound guard rail repair. Drivers will see a static right lane closure.
Work Schedule: 10 p.m. to 4 a.m. Wednesday, Feb 21-Thursday, Feb. 22. 

Highway: SR 410 Region: Olympic County: Pierce Location: Milepost(s) 11 to 10.25
Contact: Jeff Hastings, 253-983-7550
Description: Cable guard repair on westbound SR 410. Drivers will see a static left lane closure.
Work Schedule: 10 p.m. to 4 a.m. Thursday, Feb. 22-Friday, Feb. 23.

Highway: SR 507 Region: Olympic County: Pierce Location: Milepost(s) 35.4 to 35.9
Contact: Jeff Hastings, 253-983-7550
Description: Southbound shoulder sweep.
Work Schedule: 10:30 p.m. to 5 a.m. Saturday, Feb 17 through Sunday, Feb. 18. 

Highway: SR 507 Region: Olympic County: Pierce Location: Milepost(s) 22.0 to 30.9
Contact: Jeff Hastings, 253-983-7550
Description: Bridge sweeping. Drivers will see a slow moving vehicle in the right lane for sweeping.
Work Schedule: 10 p.m. Friday, Feb. 16 to 5 a.m. Saturday, Feb. 17.

Highway: SR 509 Region: Olympic County: Pierce Location: Milepost(s) 2.9 to 2.9
Contact: Jeff Hastings, 253-983-7550
Description: Northbound guard rail repair. Drivers will see a static left lane closure.
Work Schedule: 10:30 p.m. to 5 a.m. Sunday, Feb. 18 through Monday, Feb. 19.

Highway: SR 512 Region: Olympic County: Pierce Location: Milepost(s) 3.06 to 3.06
Contact: Jeff Hastings, 253-983-7550
Description: Westbound guard rail repair on SR 512. Drivers will see a static right lane closure.
Work Schedule: 10:30 p.m. to 5 a.m. Monday, Feb. 19 through Tuesday, Feb. 20.

Highway: SR 512 Region: Olympic County: Pierce Location: Milepost(s) 0 to 12
Contact: Jeff Hastings, 253-983-7550
Description: Sign replacement. Drivers will see a shoulder closure in both directions.
Work Schedule: 9 a.m. to 3 p.m. Tuesday, Feb. 20 through Thursday, Feb. 22.

Highway: SR 512 Region: Olympic County: Pierce Location: Milepost(s) 0 to 12
Contact: Jeff Hastings, 253-983-7550
Description: Drain management.
Work Schedule: 9 a.m. to 3 p.m. Tuesday, Feb. 20.

Highway: SR 706 Region: Olympic County: Pierce Location: Milepost(s) 0.1 to 1.24
Contact: Jeff Hastings, 253-983-7550
Description: Shoulder maintenance. Drivers should expect one way alternating traffic in the eastbound direction on SR 706.
Work Schedule: 6 a.m. to 2 p.m. Saturday, Feb. 24.

toptop

Thurston County


View Thurston County summer construction map  (pdf 216kb)

CONSTRUCTION 

No scheduled activities.

MAINTENANCE 

Highway: I-5 Region: Olympic County: Thurston Location: Milepost(s) 100 to 95
Contact: Jeff Hastings, 253-983-7550
Description: Shoulder sweeping. Drivers will see a mobile left lane closure in the southbound direction.
Work Schedule: 10 p.m. to 5 a.m. Friday, Feb. 23 through Saturday, Feb. 24.

Highway: I-5 Region: Olympic County: Thurston Location: Milepost(s) 106.23 to
Contact: Jeff Hastings, 253-983-7550
Description: Northbound guardrail repair on the left shoulder of the Plum street on ramp.
Work Schedule: 9:30 a.m. to 12 p.m. Thursday, Feb. 22.

Highway: I-5 Region: Olympic County: Thurston Location: Milepost(s) 108 to 111
Contact: Nghia Chau, 360-570-2375
Description: Northbound shoulder closure for roadway sensor maintenance.
Work Schedule: 9 a.m. to 3 p.m. each Monday through Thursday through Wednesday, Feb. 28.

Highway: I-5 Region: Olympic County: Thurston Location: Milepost(s) 108 to 111
Contact: Ken Lakey, 360-570-2374
Description: ITS installation on shoulder of northbound I-5.
Work Schedule: 9 a.m. to 3 p.m. each Monday through Thursday up until Mar. 8.

Highway: SR 8 Region: Olympic County: Thurston Location: Milepost(s) 20.5 to 0
Contact: Brent Schiller, 360-538-8532
Description: Shoulder sweeping in both directions. Drivers will see a mobile right lane closure.
Work Schedule: 7:30 a.m. to 4 p.m. Wednesday, Feb 21.

Highway: SR 510 Region: Olympic County: Thurston Location: Milepost(s) 0 to 1.1
Contact: Chris Ehresmann, 360-570-6749
Description: Utility work. Drivers will see a northbound right lane closure on Marvin Road and at the intersection of Marvin and Quinault Drive.
Work Schedule: 10 p.m. to 5 a.m. each Sunday through Thursday nights beginning February 18 - March 29.

Tips for Driving Through Work Zones

  • Pay attention - Driver inattention is the number one cause of work zone accidents.
  • Leave room between you and the car ahead of you - Most work zone accidents involve someone running into the car ahead of them. Drive defensively - be aware of what is happening around you.
  • Merge before you reach the work zone. 
  • Don't use cell phones or adjust your radio while driving through the work zone.