For November 21 - November 29
Updated: 4 p.m., Nov. 19
Contact: Communications Manager Jeff Adamson (509) 667-2815
Click on the project title to visit the project's web page.
Work schedules are always dependant on weather and no construction delays.
The Wenatchee Pipeline pedestrian bridge will be closed Fri. Sat. & Sun, Nov. 20-22. Use the Sellar Bridge.
No construction activity from Thursday 11/26 until Monday 11/30 for the Thanksgiving Holiday.
US 97A (MP 208-212) Wildlife Fence-Stage 1
- Sat. 11/21 & Mon. thru Wed., 7 a.m. to 4 p.m., no delays, but expect shoulder closures where crews are working.
This $895,000 project installs wildlife fencing above the highway, 4-1/2 miles north of Rocky Reach Dam to Spencer Canyon. Construction began July 13 and should be complete in early December.
Project Engineer: Mitch Reister (509) 667-3038
- Sun. night to Mon. morning, 7 p.m. to 6 a.m., expect lane closures on the bridge. A 35 mph reduced speed limit is in effect. Daily work resumes after the Thanksgiving Holiday weekend.
- The south sidewalk and path on the east end of the bridge up to Valley Mall Parkway is open until spring to pedestrians and bicyclists. Free LINK bus service will continue to be available Mon.-Sat.
- The Apple Capital Loop Trail extension south to Hydro Park remains closed between 9th St. and Grant Rd. until spring. Trail users are detoured onto Valley Mall Parkway.
In this $12.9 million project, Max J. Kuney Co. crews are removing the existing sidewalks, reinforcing the bridge structure, building a new eastbound lane and a new cantilever bicycle and pedestrian structure on the south side of the bridge. Construction began May 11 and will continue until winter shut down. The entire project should be complete by the fall of 2010.
Project Engineer: Kevin Waligorski (509) 667-2860
- Project is complete. Thank you for your patience.
In this $3.5 million project, Central Washington Asphalt crews constructed a 2.24 mile passing lane in the Turtle Rock area, a turning lane at the Lincoln Rock state park and paved from Baker Flats to Orondo. Work began June 8 and was complete Nov.18.
Project Engineer: Bob Romine (509) 667-2880
- Project is complete. Thank you for your patience.
In this $6.3 million project, Granite Northwest Inc. crews built 4-1/2 miles of passing lanes and paved the 13 miles of SR 17 and SR 282 between Ephrata and Moses Lake. Work began June 8 and was complete Nov. 19.
Project Engineer: Eric Pierson (509) 667-2870
- Project is complete. Thank you for your patience.
In this $3.24 million project, 5 miles of Interstate 90 through Moses Lake was paved. Guardrail and jersey barrier was upgraded, shoulder rumble strips, recessed pavement markers and guideposts were installed as well as new striping. Central Washington Asphalt crews began work August 24 and was complete Nov. 19.
Project Engineer: Eric Pierson (509) 667-2870