| Contract Status | Contract Number | Federal Aid Number | State Route | Contract Title | Contractor Name | Bid Amount | WSDOT Engineer Name | Region | Bid Opening Date | Awarded Date | Execution Date | Substantial Completion Date | Physical Completion Date | Engineer's Estimate | Prime Bid Amount | Amount Paid to Date | Original Working Days Count | Authorized Days Count | Remaining Working Days Count | Contract State Routes | Delivery Method | RunDate |
| Active | 006525 | BR-0104(033) | 104 | Sr 104 / Hood Canal Bridge East Half | Kiewit-General, A Joint Venture | $204,000,000.00 | AMITY TROWBRIDGE | OR | 06/18/03 | 06/24/03 | 07/30/03 | 03/21/10 | 10/04/10 | $191,755,918.00 | $204,000,000.00 | $393,478,219.94 | 735 | 152 | -81.75 | 104 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007163 | IM-0054(264) | 005 | I-5, S Everett Freeway Station 112th Street Se I-5 | Guy F. Atkinson Construction, Llc | $24,152,278.70 | JANICE FAHNING | NW | 06/28/06 | 07/14/06 | 08/23/06 | 09/21/08 | $23,634,192.44 | $24,152,278.70 | $24,841,054.73 | 531 | 531 | 0 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007217 | NICKEL-STATE&LOCA | 090 | I-90, 2-Way Transit & Hov Operations Stage 1 | Max J. Kuney Company | $22,459,943.06 | ALETA BORSCHOWA | NW | 01/18/07 | 02/27/07 | 03/08/07 | 05/26/09 | 01/05/13 | $18,312,567.52 | $22,459,943.06 | $23,871,590.41 | 350 | 410 | 0 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007264 | STATE | 090 | I 90, Eastbound Ramps To Sr 202 Roundabout | Tri-State Construction, Inc. | $1,163,880.80 | MESSAY SHIFERAW | NW | 02/14/07 | 02/16/07 | 03/08/07 | 10/01/07 | $1,137,689.10 | $1,163,880.80 | $1,163,545.17 | 130 | 130 | 19 | 090, 202 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007350 | NH-0518(008) | 518 | Sr 518, Sr 509 To I-5/I-405 - Widening | Tri-State Construction, Inc. | $26,631,265.90 | MARK SAWYER | NW | 06/13/07 | 06/18/07 | 07/11/07 | 10/21/11 | 09/11/12 | $26,625,174.75 | $26,631,265.90 | $27,654,140.78 | 320 | 321 | -4 | 509, 518 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007417 | (AC)HP-4053(855&8 | 405 | Ne 10th St Bridge Crossing, Stage 2 | Max J. Kuney Company | $13,866,639.00 | ALETA BORSCHOWA | NW | 11/28/07 | 12/03/07 | 12/17/07 | 02/16/10 | $15,540,015.80 | $13,866,639.00 | $14,194,883.47 | 355 | 355 | 0 | 405 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007431 | STPUL0522(042) | 522 | Sr522, U/W Bothell Cascadia South Access | Mowat Construction Company | $36,650,726.20 | JANICE FAHNING | NW | 12/12/07 | 01/17/08 | 02/08/08 | 01/22/10 | 01/06/13 | $31,307,541.20 | $36,650,726.20 | $37,963,893.38 | 470 | 470 | 57.5 | 405, 522 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007465 | NICKEL/LOCAL | 005 | I-5 Grand Mound-Maytown Stg 1-Add Lanes | Scarsella Bros., Inc. | $61,494,605.66 | MCNUTT/ENGEL | OR | 03/05/08 | 03/17/08 | 04/07/08 | 08/19/11 | $68,294,765.61 | $61,494,605.66 | $65,904,394.11 | 530 | 568 | 0 | 005, 012 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007495 | STATE | 005 | I-5, 5th Avenue Ne To Ne 92nd - Noise Wall | Granite Construction Company | $3,315,000.12 | MIKE ASKARIAN | NW | 03/19/08 | 03/24/08 | 04/22/08 | 11/04/09 | $5,514,509.00 | $3,315,000.12 | $3,395,351.84 | 230 | 235 | 30 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007538 | STATE | 005 | Boston - E Shelby, Westside Noisewalls | C.A. Carey Corporation | $5,375,508.00 | MIKE ASKARIAN | NW | 05/21/08 | 05/27/08 | 06/04/08 | 05/08/09 | $3,609,783.00 | $5,375,508.00 | $5,487,733.51 | 180 | 189 | 0 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007553 | STATE/NICKEL/LOCA | 900 | Sr 900, Se 78th St Vic To Newport Way Vic And I-90 | Icon Materials,A Division Of Cpm Corp. | $19,354,286.62 | DAVE LINDBERG | NW | 06/25/08 | 06/30/08 | 07/14/08 | 04/14/10 | $22,596,893.55 | $19,354,286.62 | $19,167,045.73 | 320 | 320 | 0.5 | 090, 900 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007569 | STATE | 161 | Sr 161/ Stone Creek Noise Wall | Tri-State Construction, Inc. | $959,281.00 | ALETA BORSCHOWA | NW | 06/18/08 | 06/23/08 | 07/11/08 | 01/26/10 | $927,721.00 | $959,281.00 | $900,312.90 | 60 | 72 | 11 | 161 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007577 | BR-0101(276) | 101 | Purdy Creek Bridge - Replacement | Quigg Bros. Inc. | $7,697,284.00 | NEAL UHLMEYER | OR | 06/25/08 | 06/30/08 | 07/09/08 | 03/03/10 | 03/11/13 | $9,601,976.52 | $7,697,284.00 | $7,470,206.60 | 333 | 333 | 0 | 101 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007610 | STATE | 395 | Us 395, Nsc - Us 2 Lowering | Graham Construction & Management, Inc. | $42,849,073.80 | BOB HILMES | ER | 10/16/08 | 10/21/08 | 11/13/08 | 11/28/11 | 11/05/12 | $59,750,499.10 | $42,849,073.80 | $46,159,738.56 | 620 | 645.5 | 0 | 395 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007624 | STATE | 405 | I-405, I-5 To Sr 169 Stage 2 Widening And Sr 515 I | I-405 Corridor Design Builders | $83,599,000.00 | LISA HODGSON | NW | 02/04/09 | 02/24/09 | 03/16/09 | 07/07/11 | 12/20/11 | $109,999,985.00 | $83,599,000.00 | $84,638,187.58 | 900 | 900 | 0 | 405 | Design Build | 2013-04-05 05:52:47.283 |
| Active | 007631 | IM-0054(276) | 005 | I-5, 172nd St Ne (Sr 531) Interchange Modification | Northwest Construction, Inc. | $12,975,831.69 | CHAD BROWN | NW | 01/07/09 | 01/12/09 | 01/30/09 | 07/15/10 | 01/14/13 | $21,408,553.10 | $12,975,831.69 | $12,445,951.48 | 240 | 240 | 0 | 005, 531 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007637 | STATE | 520 | Sr 520/ W Lake Sammamish Pkwy To Sr 202 Hov And Sr | Pcl Construction Services, Inc. | $37,736,270.05 | HIEN TRINH | NW | 03/04/09 | 03/09/09 | 03/30/09 | 03/14/11 | $53,661,574.08 | $37,736,270.05 | $37,711,397.55 | 485 | 485 | 0 | 520 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007649 | STATE/LOCAL | 005 | I-5, Mountlake Terrace Freeway Station | Mid-Mountain Contractors, Inc. | $17,747,153.15 | CHAD BROWN | NW | 02/19/09 | 03/17/09 | 04/03/09 | 03/17/11 | 12/14/12 | $21,926,500.41 | $17,747,153.15 | $16,881,393.45 | 450 | 465 | 0.5 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007677 | STATE | 285 | Sr 285, George Sellar Bridge Additional Eb Lane | Max J. Kuney Company | $12,884,988.00 | KEVIN WALIGORSKI | NC | 03/19/09 | 03/24/09 | 04/13/09 | 07/22/11 | 11/15/11 | $10,596,977.40 | $12,884,988.00 | $12,750,399.74 | 322 | 388 | 0.75 | 285 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007726 | ARRA-4053(858) | 405 | I-405, Ne 8th St To Sr 520 Braided Ramps- Intercha | Guy F. Atkinson Construction, Llc | $107,500,000.00 | SEEMA JAVERI | NW | 11/04/09 | 11/09/09 | 11/25/09 | 06/01/12 | $175,100,000.00 | $107,500,000.00 | $109,497,144.74 | 929 | 929 | 0 | 405 | Design Build | 2013-04-05 05:52:47.283 | |
| Active | 007775 | STPF-0410(051) | 410 | Sr410 Clay Crk Outfall Washout Repair | Weber Construction, Inc. | $444,988.40 | JEFF MINNICK | SC | 06/10/09 | 06/15/09 | 07/06/09 | 11/03/09 | 10/10/12 | $460,081.25 | $444,988.40 | $425,232.24 | 35 | 35 | 0 | 410 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007777 | STATE | 395 | Nsc Us 2 To Wandemere Vicinity | Graham Construction & Management, Inc. | $37,540,555.55 | DARREL MCCALLUM | ER | 07/23/09 | 07/29/09 | 08/17/09 | 06/11/12 | $50,519,317.75 | $37,540,555.55 | $39,428,808.10 | 420 | 470 | -20 | 395 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007779 | ARRA-IM-0053(948) | 005 | I-5, Port Of Tacoma Road To King County Line - Hov | Tri-State Construction, Inc. | $31,015,383.05 | RUMINA SUAFOA | OR | 07/08/09 | 07/13/09 | 07/23/09 | 05/31/11 | 05/02/12 | $41,349,337.02 | $31,015,383.05 | $35,225,458.81 | 425 | 405 | 0 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007786 | STATE | 090 | I90 Hi Point To Preston Ped/Bike Trail | Klb Construction Inc. | $1,971,676.50 | JOHN CHI | NW | 07/15/09 | 07/20/09 | 08/11/09 | 11/04/10 | 12/02/11 | $2,421,770.30 | $1,971,676.50 | $2,177,715.95 | 90 | 90 | 0 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007798 | STATE | 005 | I-5 5th Ave-Ne 92nd Noise Wall Stg 2 Noise Wall - | Massana Construction, Inc. | $1,475,061.00 | BRYANT BULLAMORE | NW | 07/22/09 | 07/31/09 | 08/24/09 | 05/20/10 | $1,870,056.50 | $1,475,061.00 | $1,510,537.87 | 90 | 113 | 1.5 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007826 | BR-0520(043) | 520 | Sr 520 Pontoon Construction Design-Build Project | Kiewit-General, A Joint Venture | $367,330,000.00 | DEWAYNE MATLOCK | OR | 12/23/09 | 01/08/10 | 02/12/10 | $600,000,006.00 | $367,330,000.00 | $228,354,542.15 | 1,529 | 1,529 | 400 | 520 | Design Build | 2013-04-05 05:52:47.283 | ||
| Active | 007835 | STATE | 005 | I-5, Sr 432, Talley Way Interchange | Northwest Construction, Inc. | $20,528,756.00 | LORI FIGONE | SW | 12/02/09 | 12/15/09 | 01/05/10 | 11/15/11 | $30,928,998.66 | $20,528,756.00 | $21,284,115.46 | 400 | 438.5 | 0 | 005, 432 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007844 | STATE | 099 | Sr 99 Et Al, 1st Ave S To S 112th St And S 120th S | Signal Electric Inc | $2,482,582.10 | DAVE LINDBERG | NW | 11/18/09 | 11/23/09 | 12/14/09 | 10/18/10 | $2,938,514.90 | $2,482,582.10 | $2,648,846.84 | 180 | 190 | 0 | 099, 509, 599 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007847 | PNRS-0099(096)97( | 099 | Sr 99, Alaskan Way Viaduct - Replacement S Holgate | Skanska Usa Civil West California Distri | $114,569,194.25 | PAUL JOHNSON | Urban | 04/14/10 | 05/12/10 | 05/24/10 | 10/23/12 | 10/29/12 | $152,620,104.46 | $114,569,194.25 | $121,491,250.64 | 1,303 | 1,123 | 262 | 099 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007852 | STATE | 090 | I-90, Hyak To Snowshed Vicinity Phase 1b- Add Lane | Max J. Kuney Company | $76,699,232.66 | WILL SMITH | SC | 01/21/10 | 01/27/10 | 02/08/10 | $110,365,251.05 | $76,699,232.66 | $81,452,714.21 | 519 | 568.5 | 217.5 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 007857 | NH-0002(287) | 002 | Us 2, Stevens Pass Summit- Pedestrian Safety | Tri-State Construction, Inc. | $1,785,325.20 | PIERSON/PATRICK | NC | 12/17/09 | 12/21/09 | 01/11/10 | 06/13/11 | 12/14/11 | $2,511,246.70 | $1,785,325.20 | $1,861,348.50 | 135 | 137 | 0 | 002 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007858 | ARRA-0822(128) | 082 | I-82, Valley Mall Blvd. Interchange Rebuild Interc | Apollo, Inc. | $19,079,869.61 | JEFF MINNICK | SC | 01/13/10 | 02/19/10 | 03/10/10 | 11/14/11 | 11/07/12 | $23,320,934.19 | $19,079,869.61 | $21,451,279.89 | 283 | 313 | 2 | 082 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007859 | STATE | 011 | Sr 11, I-5 Interchange - Josh Wilson Rd Rebuild In | Interwest Construction Inc | $4,794,882.15 | HAMMER/SPAHR | NW | 01/27/10 | 02/01/10 | 02/19/10 | 11/05/10 | $7,215,951.90 | $4,794,882.15 | $4,687,007.43 | 150 | 154 | 0 | 005, 011, 020 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007862 | NH-0906(210) | 090 | I-90 Spokane Poe Weigh Station Relocation | Selland Construction, Inc. | $6,704,332.55 | CHAD SIMONSON | ER | 02/04/10 | 02/17/10 | 03/05/10 | 11/07/11 | 12/20/11 | $10,333,570.25 | $6,704,332.55 | $6,826,569.99 | 325 | 327 | 1 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007866 | STATE | 410 | Sr 410/ 214th Ave E To 234th Ave E- Widening | J. R. Hayes & Sons, Inc. | $6,783,945.32 | MARYLOU NEBERGALL | OR | 02/03/10 | 02/08/10 | 03/01/10 | 03/07/12 | $11,315,537.50 | $6,783,945.32 | $7,909,424.82 | 175 | 214 | 0 | 410 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007870 | LOCAL&SOUNDTRANSI | 090 | I-90, Two-Way Transit & Hov Operations Stage 2 | Gary Merlino Construction Co., Inc. | $11,578,632.30 | SAWYER/TRINH | NW | 02/10/10 | 03/01/10 | 03/22/10 | 04/15/12 | $15,290,112.50 | $11,578,632.30 | $13,377,192.96 | 380 | 496.5 | 0 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007874 | CBI-IMD-OO55(227) | 005 | I-5, Blaine Exit Interchange Improvements | Interwest Construction Inc | $2,765,789.35 | CHRIS DAMITIO | NW | 01/27/10 | 02/05/10 | 03/02/10 | 08/31/10 | $4,662,787.58 | $2,765,789.35 | $3,588,464.63 | 118 | 120 | 0 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007895 | ARRA-BH-0433(010) | 433 | Sr 433, Lewis And Clark Bridge Superstructure Pain | Odyssey/Geronimo Joint Venture | $33,774,714.00 | LORI FIGONE | SW | 03/17/10 | 04/30/10 | 06/08/10 | $36,461,689.00 | $33,774,714.00 | $25,551,809.70 | 500 | 500 | 183.5 | 433 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 007903 | STATE | 005 | I-5, Blakeslee Junction Rr Xing To Grand Mound I/C | Tri-State Construction, Inc. | $19,730,514.90 | COLIN NEWELL | SW | 04/07/10 | 04/15/10 | 05/10/10 | 02/24/12 | $28,025,229.50 | $19,730,514.90 | $22,383,491.15 | 220 | 246 | 0 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007911 | STATE | 542 | Sr 542, Gallup Creek Bridge Replacement | Scarsella Bros., Inc. | $2,707,707.07 | CHRIS DAMITIO | NW | 03/31/10 | 04/09/10 | 04/28/10 | 11/11/11 | 11/15/12 | $4,071,887.45 | $2,707,707.07 | $2,629,124.71 | 237 | 237 | 0 | 542 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007916 | STATE | 002 | Us 2 Safety Improvements | Vetch Construction Inc. | $2,932,708.10 | DAVE CRISMAN | NW | 04/14/10 | 04/28/10 | 05/18/10 | 09/02/11 | $4,326,328.00 | $2,932,708.10 | $3,282,169.03 | 80 | 99 | 10.5 | 002 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007917 | IM-0901(461) | 090 | I90, Sunset Way Connection I/C Mods | Tri-State Construction, Inc. | $1,305,983.00 | HIEN TRINH | NW | 04/14/10 | 04/28/10 | 05/19/10 | 11/10/11 | $1,730,961.25 | $1,305,983.00 | $1,193,347.67 | 75 | 75 | 0 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007919 | STPUL0054(279) | 005 | I-5, 164th St Sb Off Ramp Channelization | Signal Electric Inc | $155,778.30 | CHAD BROWN | NW | 04/07/10 | 04/12/10 | 04/27/10 | 09/23/10 | 04/21/11 | $282,111.50 | $155,778.30 | $137,005.71 | 20 | 20 | 0 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007920 | STATE | 009 | Sr 9, Lundeen Parkway To Sr 92 Intersection Improv | Granite Construction Company | $10,921,000.00 | DAVE CRISMAN | NW | 05/05/10 | 05/17/10 | 06/10/10 | 10/28/11 | $16,571,849.37 | $10,921,000.00 | $12,022,820.17 | 180 | 207 | 9.5 | 009, 092 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007926 | BR-0303(005) | 303 | Sr 303, Manette Bridge 303/4a - Bridge Replacement | Manson-Mowat, A Joint Venture | $44,127,374.00 | JEFF COOK | OR | 05/19/10 | 06/15/10 | 06/24/10 | 02/27/13 | $42,337,364.00 | $44,127,374.00 | $49,234,731.05 | 382 | 428 | 3 | 303 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007936 | STATE | 005 | I-5, Sr 161/Sr 18 Interchange Improvements | Mowat Construction Company | $50,778,922.50 | ALETA BORSCHOWA | NW | 06/09/10 | 06/21/10 | 07/08/10 | $64,553,797.24 | $50,778,922.50 | $51,882,253.65 | 660 | 660 | 38 | 005, 018, 161 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 007938 | STATE | 522 | Sr 522, Us 2 Interchange Flyover Ramp | Scarsella Bros., Inc. | $15,514,435.30 | CHAD BROWN | NW | 05/26/10 | 06/01/10 | 06/15/10 | 06/21/12 | $22,322,279.40 | $15,514,435.30 | $15,673,631.10 | 350 | 351 | 0 | 002, 522 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007945 | STATE | 005 | I-5, 196th St (Sr 524) I/C Sb Braided Ramp | Northwest Construction, Inc. | $18,727,000.00 | MARK SAWYER | NW | 06/23/10 | 06/28/10 | 07/15/10 | $31,389,404.89 | $18,727,000.00 | $19,723,795.58 | 360 | 362 | 1 | 005, 525 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 007946 | STATE | 005 | I-5, Portland Ave To Port Of Tacoma Rd - Nb Hov St | Scarsella Bros., Inc. | $16,392,704.34 | NEAL UHLMEYER | OR | 06/09/10 | 06/14/10 | 07/07/10 | 07/30/12 | $22,136,273.50 | $16,392,704.34 | $16,284,490.03 | 270 | 275 | -18.5 | 005, 167 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007948 | STATE | 529 | Sr 529, Ebey Slough Br - Replace Bridge | Granite Construction Company | $21,541,000.00 | MARK SAWYER | NW | 06/09/10 | 06/16/10 | 07/02/10 | $28,057,110.00 | $21,541,000.00 | $20,211,748.52 | 763 | 763 | 106.5 | 529 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 007959 | NH-0099(109) | 099 | Sr 99, S Hudson St To Ward St Automated Viaduct Cl | Signal Electric Inc | $1,434,793.73 | DAVE LINDBERG | Urban | 06/16/10 | 07/28/10 | 08/18/10 | 03/16/11 | 12/05/12 | $1,974,764.50 | $1,434,793.73 | $1,176,090.51 | 90 | 97 | 0 | 099 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007962 | IM-ITS-0055(238) | 005 | I-5 Downtown Bellingham On/Off Ramps - Ramp Recons | Vetch Construction Inc. | $4,439,672.03 | CHRIS DAMITIO | NW | 07/14/10 | 08/18/10 | 09/07/10 | 12/19/12 | $5,930,296.14 | $4,439,672.03 | $4,569,225.53 | 160 | 160.5 | -49 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007963 | STATE | 520 | Sr 520, Eastside Transit And Hov Project A Design | Eastside Corridor Constructors | $306,278,000.00 | MARK ALLISON | Urban | 09/16/10 | 10/29/10 | 11/29/10 | $422,064,082.00 | $306,278,000.00 | $237,273,216.82 | 1,115 | 1,115 | 279 | 520 | Design Build | 2013-04-05 05:52:47.283 | ||
| Active | 007967 | TIGER-0395(091) | 395 | Us 395, Nsc - Freya St To Farwell Rd Sb Additional | Graham Construction & Management, Inc. | $21,455,920.65 | BOB HILMES | ER | 07/22/10 | 07/28/10 | 08/17/10 | 10/05/12 | $24,484,745.50 | $21,455,920.65 | $21,863,224.92 | 310 | 311 | 1.5 | 395 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007971 | ARRA/IM-0902(315) | 090 | I-90, Lake Easton Vic To Big Creek Br Vic Eb - Rep | Icon Materials,A Division Of Cpm Corp. | $14,807,102.55 | JEFF MINNICK | SC | 07/28/10 | 07/30/10 | 08/18/10 | $16,361,717.55 | $14,807,102.55 | $15,287,790.12 | 260 | 260 | 8 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 007974 | STATE | 005 | I-5 Tacoma Hov Mitigation | Scarsella Bros., Inc. | $1,487,229.43 | RUMINA SUAFOA | OR | 07/08/10 | 07/12/10 | 07/30/10 | 02/24/12 | 02/25/13 | $2,764,535.50 | $1,487,229.43 | $1,130,588.99 | 162 | 162 | 0 | 005, 167 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 007984 | STPF-0105(020) | 105 | Sr 105, Norris Slough Culvert Replacement | Boss Construction Inc | $1,765,584.61 | COLIN NEWELL | SW | 08/11/10 | 08/13/10 | 09/07/10 | 05/11/12 | $1,676,121.00 | $1,765,584.61 | $1,617,442.13 | 160 | 207 | -21.5 | 105 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 007998 | NICKEL_FUNDS | 005 | I-5, Grand Mound To Maytown Stage Two - Replace In | Tri-State Construction, Inc. | $15,517,831.55 | ENGEL/NEBERGALL | OR | 11/03/10 | 11/22/10 | 12/14/10 | 11/13/12 | $22,367,513.91 | $15,517,831.55 | $16,614,844.50 | 198 | 292 | 0 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008012 | STATE | 020 | Sr 20, Red Cabin Creek - Ced | Interwest Construction Inc | $1,939,941.40 | HAMMER/SPAHR | NW | 10/20/10 | 10/25/10 | 11/16/10 | 05/08/12 | 11/20/12 | $2,868,960.80 | $1,939,941.40 | $1,789,132.39 | 101 | 101 | 0 | 020 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008016 | IM-0055(242) | 005 | I-5, Joe Leary Slough To Nulle Rd Vic Paving Desig | Granite Construction Company | $14,553,000.00 | PATRICK FULLER | NW | 01/14/11 | 02/04/11 | 02/18/11 | 10/31/12 | 11/09/12 | $14,553,000.00 | $14,553,000.00 | $14,137,167.08 | 367 | 367 | 18 | 005 | Design Build | 2013-04-05 05:52:47.283 |
| Active | 008018 | IM-0906(225) | 090 | I-90 Geiger Rd To Spokane Viaduct Pccp Rehab Pccp | Acme Concrete Paving, Inc. | $7,849,447.77 | CHAD SIMONSON | ER | 10/21/10 | 10/28/10 | 11/22/10 | $12,620,894.81 | $7,849,447.77 | $8,931,953.30 | 180 | 206.5 | 10.5 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008022 | NH-0906(226) | 090 | I-90 Sullivan Rd To Barker Rd Additional Lanes Add | Acme Concrete Paving, Inc. | $14,949,578.24 | DARREL MCCALLUM | ER | 11/10/10 | 12/13/10 | 12/22/10 | 06/11/12 | $17,891,733.30 | $14,949,578.24 | $15,765,434.20 | 150 | 154.5 | -26.5 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008029 | STATE/LOCAL | 823 | Sr 823, Selah Vicinity - Reroute Highway (Re-Ad) | Hurst Construction, Llc | $3,573,162.05 | JEFF MINNICK | SC | 11/10/10 | 11/18/10 | 12/08/10 | 05/10/12 | 06/06/12 | $4,887,184.51 | $3,573,162.05 | $4,523,990.91 | 215 | 215 | 17 | 823 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008031 | STPF-0017(039) | 017 | Sr 17, Moses Lake Vicinity - Median Barrier | Tri-State Construction, Inc. | $1,257,232.00 | PIERSON/PATRICK | NC | 11/18/10 | 11/22/10 | 12/13/10 | 10/06/11 | 10/11/11 | $1,273,245.00 | $1,257,232.00 | $1,333,602.41 | 55 | 63 | 0 | 017 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008033 | STATE | 012 | Us 12, Sr 124 Intersection - Build Interchange | Selland Construction, Inc. | $11,478,642.61 | MOE DAVARI | SC | 02/02/11 | 02/07/11 | 02/25/11 | 10/26/12 | $15,614,038.38 | $11,478,642.61 | $12,388,141.95 | 300 | 300 | 13.5 | 012, 124 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008047 | STATE | 005 | I-5, Exit 111 Lacey Vic. Noise Walls | Mowat Construction Company | $2,867,054.20 | MARYLOU NEBERGALL | OR | 01/05/11 | 01/10/11 | 01/28/11 | 02/03/12 | 02/04/13 | $4,712,004.50 | $2,867,054.20 | $3,257,698.05 | 95 | 115 | 0 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008053 | STATE | 405 | I-405, Ne 116th Street Interchange And Street Impr | Gary Merlino Construction Co., Inc. | $10,693,960.80 | HIEN TRINH | NW | 02/02/11 | 02/28/11 | 03/25/11 | $13,407,331.75 | $10,693,960.80 | $12,943,225.87 | 425 | 432.5 | 12.5 | 405 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008055 | NH-STPF-9999(611) | 167 | Sr 167 / I-405 I/C Vic To S Grady Way & Sr 509 / S | Lakeside Industries | $694,858.95 | HIEN TRINH | NW | 01/05/11 | 01/14/11 | 02/01/11 | 09/29/11 | 12/05/11 | $854,769.00 | $694,858.95 | $718,030.71 | 20 | 20 | 0 | 167, 509 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008060 | ER-0601(007) | 530 | Sr 530, Skaglund Hill Slide - Permanent Repair | Vetch Construction Inc. | $3,297,816.00 | DAVE CRISMAN | NW | 01/12/11 | 02/11/11 | 02/25/11 | 11/05/12 | $3,505,187.30 | $3,297,816.00 | $3,493,469.17 | 90 | 129 | -10.5 | 530 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008065 | STATE | 530 | Sr 530, Sauk River Bank Erosion Realign Roadway | Trimaxx Construction | $2,480,567.66 | HAMMER/SPAHR | NW | 01/12/11 | 01/18/11 | 02/04/11 | 12/14/11 | $3,230,573.15 | $2,480,567.66 | $2,402,125.54 | 145 | 160 | 0 | 530 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008066 | BRNHSTPF0520(047) | 520 | Sr 520 / I-5 To Medina - Evergreen Point Floating | Kiewit General Manson Joint Venture | $586,561,000.00 | DAVE BECHER | Urban | 08/10/11 | 08/11/11 | 08/31/11 | $640,769,000.00 | $586,561,000.00 | $215,416,074.26 | 1,429 | 1,429 | 853 | 520 | Design Build | 2013-04-05 05:52:47.283 | ||
| Active | 008077 | STATE | 011 | Sr 11, Chuckanut Park And Ride | Interwest Construction Inc | $3,198,800.80 | HAMMER/SPAHR | NW | 02/02/11 | 02/10/11 | 03/07/11 | $3,540,188.50 | $3,198,800.80 | $3,645,945.95 | 67 | 162 | 21 | 011 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008079 | NH-0500(016) | 500 | Sr 500, St. Johns Blvd - Interchange | Tapani Underground, Inc. | $27,237,397.12 | LEON WINGER | SW | 03/02/11 | 04/29/11 | 05/20/11 | $33,403,982.85 | $27,237,397.12 | $26,488,449.86 | 440 | 492.5 | 21 | 500 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008080 | STPF-BH-0099(101) | 099 | Sr 99, Aurora Ave - G Washington Memorial Br Seism | Massana Construction, Inc. | $6,157,383.00 | JOHN CHI | NW | 02/24/11 | 04/05/11 | 04/27/11 | $8,707,615.00 | $6,157,383.00 | $6,077,668.47 | 310 | 315 | -114 | 099 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008081 | STPF-0020(165) | 020 | Sr 20, North Cascades Highway - Chip Seal | Central Washington Asphalt, Inc. | $2,664,395.23 | PIERSON/PATRICK | NC | 02/17/11 | 02/22/11 | 03/08/11 | 09/13/11 | 09/19/11 | $2,601,429.22 | $2,664,395.23 | $2,849,115.76 | 70 | 70 | 3 | 020 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008086 | STATE | 542 | Sr 542, Everson Goshen Rd Vic To Sr 9 Vic Intersec | Boss Construction Inc | $2,740,818.32 | CHRIS DAMITIO | NW | 03/02/11 | 03/07/11 | 03/24/11 | 08/03/12 | 03/25/13 | $3,485,512.50 | $2,740,818.32 | $2,698,826.46 | 106 | 106 | -3 | 539, 542 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008087 | BH-0410(054) | 410 | Sr 410, White River Bridge - Bridge Scour | Scarsella Bros., Inc. | $217,236.75 | JON DEFFENBACHER | OR | 02/24/11 | 03/03/11 | 03/17/11 | 12/07/11 | 02/01/13 | $281,230.00 | $217,236.75 | $90,357.11 | 25 | 25 | 8 | 410 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008101 | STPE-1140(030) | 219 | Sr 519 / I-90 To Sr 519 Pedestrian Trail | Tri-State Construction, Inc. | $1,107,911.00 | DAVE LINDBERG | NW | 03/23/11 | 04/05/11 | 04/27/11 | 11/01/11 | $1,288,266.80 | $1,107,911.00 | $1,247,656.44 | 45 | 59 | 0 | 219 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008102 | IM-0053(955) | 005 | I-5, Express Lane Automation | Elcon Corporation | $3,419,556.00 | JOHN CHI | NW | 03/30/11 | 04/04/11 | 04/28/11 | $3,419,601.86 | $3,419,556.00 | $4,781,080.56 | 200 | 200 | -52 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008105 | STATE | 014 | Sr 14, Camas / Washougal - Add Lanes And Build Int | Tapani Underground, Inc. | $28,618,803.65 | CHRIS TAMS | SW | 04/13/11 | 04/18/11 | 05/11/11 | $34,500,833.10 | $28,618,803.65 | $25,546,561.20 | 360 | 369 | 22 | 014, 500 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008113 | BH-0518(011) | 518 | Sr 518, Bridges - Seismic Retrofit | Graham Construction & Management, Inc. | $3,707,899.00 | ALETA BORSCHOWA | NW | 04/20/11 | 04/27/11 | 05/18/11 | 08/06/12 | $4,197,734.50 | $3,707,899.00 | $3,377,105.75 | 235 | 245 | 0 | 518 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008114 | STPF-0515(013) | 515 | Sr 515/Sr 516 To Se 232nd St Vic Paving | Lakeside Industries | $1,394,858.88 | HIEN TRINH | NW | 04/20/11 | 04/25/11 | 05/12/11 | 10/06/11 | 10/10/11 | $1,679,449.00 | $1,394,858.88 | $1,560,509.35 | 70 | 70 | 0 | 515, 516 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008119 | NH-STPUS-0022(013 | 022 | Sr 22/I-82 To Toppenish - Safety Improvements | Granite Construction Company | $2,144,144.00 | BILL PRESTON | SC | 04/20/11 | 04/27/11 | 05/13/11 | 06/26/12 | 07/10/12 | $2,270,401.25 | $2,144,144.00 | $2,539,360.18 | 80 | 99 | -9 | 022 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008127 | STATE | 090 | I-90, Snowshed To Keechelus Dam Phase 1c - Replace | Guy F. Atkinson Construction, Llc | $177,144,342.66 | WILL SMITH | SC | 07/27/11 | 08/19/11 | 08/19/11 | $197,988,768.70 | $177,144,342.66 | $39,040,768.05 | 750 | 926 | 794 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008128 | NICKEL | 522 | Sr 522, Snohomish River Bridge To Us 2 Vic Widenin | Scarsella Bros., Inc. | $73,138,890.32 | JANICE FAHNING | NW | 05/18/11 | 05/26/11 | 06/16/11 | $86,169,502.10 | $73,138,890.32 | $44,591,715.57 | 850 | 850 | 429.5 | 522 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008129 | NH-9999(620) | 005 | I-5 And Sr 16, Stormwater Retrofit | Catworks Llc | $471,404.50 | NEAL UHLMEYER | OR | 05/04/11 | 05/09/11 | 06/01/11 | 11/07/11 | 11/14/12 | $569,262.00 | $471,404.50 | $481,884.26 | 45 | 47 | 4 | 005, 016 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008130 | STPF-0020(164) | 020 | Sr 20, Barrier Creek Culvert Replacement | Razz Construction, Inc. | $1,521,958.00 | HAMMER/SPAHR | NW | 05/04/11 | 05/09/11 | 05/18/11 | $1,433,869.50 | $1,521,958.00 | $1,436,250.63 | 67 | 78 | 0 | 020 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008139 | BR-0002(283) | 002 | Us 2, Tumwater Canyon Bridge Replacements | Selland Construction, Inc. | $8,485,707.28 | BOB ROMINE | NC | 05/19/11 | 06/24/11 | 07/13/11 | $8,838,512.74 | $8,485,707.28 | $5,514,926.27 | 275 | 275 | 47 | 002 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008140 | STATE | 009 | Sr 9, 212th St Se To 176th St Se Stage 3 Widening | Northwest Construction, Inc. | $24,297,000.00 | JOHN CHI | NW | 06/08/11 | 06/23/11 | 07/12/11 | $32,543,138.80 | $24,297,000.00 | $14,388,903.38 | 505 | 505 | 176 | 009 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008141 | NH-0020(105) | 020 | Sr 20/Sr 525, Libbey Rd Vic To Sidney St Vic Reali | Interwest Construction Inc | $2,269,936.16 | DAVE CRISMAN | NW | 05/18/11 | 05/23/11 | 06/13/11 | 11/09/11 | $2,067,148.98 | $2,269,936.16 | $2,061,060.44 | 60 | 60 | 3 | 020, 525 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008142 | NH-0018(037) | 018 | Sr 18, Military Rd Vic To Auburn Black Diamond Rd | Tucci & Sons, Inc. | $1,182,402.24 | HIEN TRINH | NW | 05/18/11 | 05/23/11 | 06/14/11 | 04/10/12 | 05/04/12 | $1,337,801.75 | $1,182,402.24 | $1,128,906.41 | 45 | 45 | 0 | 018 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008144 | ER-0902(252)/(331 | 161 | Sr 161, Mashel River Bridge - Bridge Scour And Slo | Stan Palmer Construction, Inc. | $1,612,149.00 | JON DEFFENBACHER | OR | 05/25/11 | 05/31/11 | 06/21/11 | 03/06/13 | $1,791,346.00 | $1,612,149.00 | $3,074,960.04 | 85 | 141 | 9 | 161 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008145 | IM-0052(204) | 005 | I-5 / Sr 121 To Tumwater Blvd Paving | Granite Construction Company | $1,839,306.00 | MARYLOU NEBERGALL | OR | 05/25/11 | 05/31/11 | 06/21/11 | 11/10/11 | 01/06/12 | $2,114,349.00 | $1,839,306.00 | $1,977,245.92 | 40 | 46.5 | 0 | 005, 121 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008150 | IM-0051(285) | 005 | I-5, E Fork Lewis River Bridge To Todd Road Vicini | Granite Construction Company | $4,250,250.00 | LORI FIGONE | SW | 06/15/11 | 06/27/11 | 07/12/11 | $5,157,579.39 | $4,250,250.00 | $4,584,699.95 | 60 | 74 | 0 | 005, 503 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008153 | STATE | 005 | I-5 / I-205, Ne 134th St Interchange (I-5 / I-205) | Rotschy, Inc. | $19,949,910.16 | LEON WINGER | SW | 06/08/11 | 06/22/11 | 07/01/11 | 02/08/13 | $20,598,245.39 | $19,949,910.16 | $20,431,907.91 | 175 | 192 | 0 | 005, 205 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008166 | NH0028(045) | 028 | Sr 28, E. End Of The George Sellar Br. Construct B | Klb Construction Inc. | $16,363,377.90 | KEVIN WALIGORSKI | NC | 06/23/11 | 07/08/11 | 07/19/11 | $15,772,791.07 | $16,363,377.90 | $13,875,401.07 | 270 | 301 | 61 | 028, 285 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008177 | NH-0002(313) | 002 | Us 2, Rice Road Intersection - Safety Improvements | Lakeside/Tri-State Joint Venture | $2,170,507.00 | CHAD BROWN | NW | 08/24/11 | 09/07/11 | 10/05/11 | 07/02/12 | $2,750,002.00 | $2,170,507.00 | $2,367,526.50 | 266 | 266 | 0 | 002 | Design Build | 2013-04-05 05:52:47.283 | |
| Active | 008182 | STPF-0020(165) | 020 | Sr 20, North Cascades Highway - Drainage Repair | Trimaxx Construction | $298,194.00 | PIERSON/PATRICK | NC | 06/30/11 | 07/05/11 | 07/27/11 | 10/20/11 | 11/07/12 | $386,444.00 | $298,194.00 | $266,623.30 | 22 | 22 | 0 | 020 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008184 | STATE | 009 | Sr 9, 212th St Se To 176th St Se Stage 3 Wetland M | Tri-State Construction, Inc. | $1,252,399.90 | JOHN CHI | NW | 07/07/11 | 07/14/11 | 08/05/11 | 11/16/12 | $2,190,755.50 | $1,252,399.90 | $1,001,328.96 | 125 | 125 | 0 | 009 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008189 | STATE | 005 | I-5 / Sr16, Eastbound Nalley Valley I/C - Hov | Mowat Construction Company | $74,687,777.28 | NEAL UHLMEYER | OR | 08/31/11 | 09/22/11 | 10/13/11 | $92,457,289.58 | $74,687,777.28 | $39,358,588.88 | 610 | 610 | 278.5 | 005, 016 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008195 | TIGER0395(091) | 395 | Us395 Nsc Parksmith Interchange | Max J. Kuney Company | $6,917,161.46 | BOB HILMES | ER | 08/18/11 | 09/07/11 | 09/21/11 | 10/19/12 | $6,801,315.50 | $6,917,161.46 | $7,190,802.53 | 185 | 185 | -26 | 395 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008198 | STATE | 519 | Seattle Terminal Elect Distrib Sstm Upgrade System | Mcclure And Sons Inc. | $2,969,687.60 | JOHN CALLAHAN | WSF | 08/17/11 | 08/24/11 | 09/21/11 | $4,506,128.66 | $2,969,687.60 | $2,821,755.18 | 240 | 314 | -4 | 519 | Marine Terminal | 2013-04-05 05:52:47.283 | ||
| Active | 008199 | CM-0161(029) | 161 | Sr 161, 24th St East To Milton Way Widening | Tri-State Construction, Inc. | $11,927,623.80 | JEFF COOK | OR | 08/10/11 | 08/17/11 | 09/07/11 | $12,285,768.14 | $11,927,623.80 | $7,459,911.86 | 278 | 433 | 144 | 161 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008204 | STATE | 405 | I-405, Ne 6th St To I-5 Widening And Express Toll | Flatiron Constructors Inc | $155,500,001.00 | LISA HODGSON | NW | 01/06/12 | 01/11/12 | 02/01/12 | $249,999,996.00 | $155,500,001.00 | $38,829,293.19 | 1,330 | 1,330 | 922 | 405 | Design Build | 2013-04-05 05:52:47.283 | ||
| Active | 008216 | STATE | 009 | Sr 9 / Sr 92 Intersection Improvements Design Buil | Guy F. Atkinson Construction, Llc | $3,346,888.00 | SEEMA JAVERI | NW | 01/19/12 | 01/26/12 | 02/15/12 | 08/20/12 | $3,919,498.49 | $3,346,888.00 | $3,494,226.18 | 237 | 237 | 0 | 009, 092 | Design Build | 2013-04-05 05:52:47.283 | |
| Active | 008222 | STATE | 009 | Sr 9/Sr 531, 172nd St Ne & Eaglefield Dr Intersect | Interwest Construction Inc | $4,995,958.40 | HAMMER/SPAHR | NW | 11/09/11 | 11/18/11 | 12/08/11 | 01/24/13 | $5,637,723.50 | $4,995,958.40 | $4,472,936.34 | 93 | 101 | -0.5 | 009, 531 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008223 | NH-0901(466) | 090 | I-90, East Fork Issaquah Creek Fish Passage | Tri-State Construction, Inc. | $1,451,881.70 | HIEN TRINH | NW | 11/02/11 | 11/07/11 | 11/28/11 | 11/21/12 | $1,542,787.00 | $1,451,881.70 | $1,922,361.22 | 110 | 110 | -4.5 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008229 | NH-0002(282) | 002 | Us 2, Stevens Pass West Slope Stabilization | Midwest Rockfall, Inc. | $5,291,071.20 | KEVIN WALIGORSKI | NC | 12/22/11 | 12/29/11 | 01/20/12 | $6,202,171.00 | $5,291,071.20 | $2,695,973.76 | 230 | 230 | 122.5 | 002 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008231 | IMD-0051(268) | 005 | I-5, Columbia River Crossing Drilled Shaft And Dri | Max J. Kuney Company | $4,220,000.00 | FRANK GREEN | SW | 12/14/11 | 12/19/11 | 01/09/12 | 11/21/12 | $4,072,627.05 | $4,220,000.00 | $4,119,835.72 | 82 | 98.5 | -17 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008232 | STPF-0097(145) | 097 | Us 97a, 0.5 Mile So. Of Rocky Reach Dam Slope Stab | Janod, Inc. | $3,110,680.96 | BOB ROMINE | NC | 12/21/11 | 12/29/11 | 01/26/12 | 06/20/12 | 07/02/12 | $2,996,424.00 | $3,110,680.96 | $3,000,918.56 | 82 | 87.5 | 0 | 097 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008234 | NH-0101(325) | 101 | Us 101, S Of Beacon Point Dr Culvert Replacement | Thompson Bros. Excavating, Inc. | $260,401.25 | JERRY MOORE | OR | 01/05/12 | 01/10/12 | 01/26/12 | 11/06/12 | $297,574.00 | $260,401.25 | $241,030.34 | 45 | 45 | 0 | 101 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008239 | CBI-0055(240) | 005 | I-5, Samish Way And Northwest Ave To Birch Bay Lyn | Valley Electric Co. Of Mt Vernon | $5,343,782.60 | CHRIS DAMITIO | NW | 02/08/12 | 03/21/12 | 04/10/12 | 12/07/12 | $5,848,658.00 | $5,343,782.60 | $5,243,955.81 | 65 | 71 | 1 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008240 | ER-1001(003) | 410 | Sr 410, Nile Valley Landslide - Re-Construct Route | Apollo, Inc. | $4,083,066.15 | JEFF MINNICK | SC | 01/25/12 | 02/07/12 | 02/21/12 | $6,254,481.75 | $4,083,066.15 | $4,307,265.10 | 100 | 111 | 4 | 410 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008241 | CBI0021,STPF0021019 | 021 | Sr21 Curlew St Pk To N Of Rincon Cr Rd Pave N Of R | Poe Asphalt Paving, Inc. | $4,235,606.62 | CHAD SIMONSON | ER | 01/26/12 | 01/26/12 | 02/24/12 | 10/25/12 | $4,581,555.90 | $4,235,606.62 | $3,954,497.83 | 44 | 45 | 3.5 | 021 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008244 | BR-NH-0097(084) | 097 | Us 97, Satus Creek Vicinity - Replace Br. 97/106 A | William Charles Construction, Llc | $8,830,731.60 | MOE DAVARI | SC | 02/08/12 | 02/13/12 | 03/05/12 | $8,788,576.51 | $8,830,731.60 | $6,785,546.79 | 177 | 183 | 25.5 | 097 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008246 | HP-0501(022) | 501 | Sr 501, Ridgefield Interchange Stage Ii - Roadway | Nutter Underground Utilities, Inc. | $2,823,532.22 | CHRIS TAMS | SW | 03/07/12 | 03/15/12 | 04/04/12 | 10/23/12 | 12/12/12 | $2,975,111.90 | $2,823,532.22 | $3,476,408.57 | 90 | 117 | 0 | 501 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008250 | IBRD-9999(509) | 005 | I-5, North 45th St Vicinity Sign Bridge Replacemen | M J Hughes Construction | $376,213.00 | JOHN CHI | NW | 02/23/12 | 02/27/12 | 03/19/12 | 11/14/12 | 11/29/12 | $401,861.00 | $376,213.00 | $624,072.03 | 34 | 44 | 2 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008252 | STATE | 020 | Sr20 Vehicle Reservation Ph1 Its Systems Its Syste | Valley Electric Co. Of Mt Vernon | $696,460.00 | HAMMER/SPAHR | NW | 03/07/12 | 03/15/12 | 04/13/12 | 01/18/13 | $741,157.00 | $696,460.00 | $771,922.65 | 40 | 49 | 11 | 005, 020, 525 | Marine Terminal | 2013-04-05 05:52:47.283 | |
| Active | 008254 | STATE | 020 | Sr 20, Port Townsend Ferry Terminal Slip 1 Transfe | American Construction Co., Inc. | $2,027,079.00 | JOHN CALLAHAN | WSF | 03/14/12 | 03/20/12 | 04/10/12 | $1,640,308.00 | $2,027,079.00 | $1,745,230.00 | 144 | 144 | -81 | 020 | Marine Terminal | 2013-04-05 05:52:47.283 | ||
| Active | 008258 | BH-0901(481) | 090 | I-90 / Sr 18 Interchange Wb Bridge Bridge Deck Reh | C.A. Carey Corporation | $459,481.50 | HIEN TRINH | NW | 03/28/12 | 04/04/12 | 04/24/12 | 06/30/12 | 07/06/12 | $510,006.00 | $459,481.50 | $432,752.38 | 25 | 25 | 0 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008260 | ER-0801(007) | 405 | I-405 / Sr 167, Thunder Hills Creek Mitigation Fis | Scarsella Bros., Inc. | $3,164,254.80 | SEEMA JAVERI | NW | 03/28/12 | 04/06/12 | 04/27/12 | $3,212,221.00 | $3,164,254.80 | $3,149,264.44 | 100 | 100 | 0 | 405 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008261 | BH-0010(010) | 010 | Sr 10, Bristol Fill Bridge Deck Replacement | Conway Construction Company | $1,375,769.80 | MOE DAVARI | SC | 04/04/12 | 04/10/12 | 04/30/12 | 11/14/12 | 12/11/12 | $2,363,118.50 | $1,375,769.80 | $1,283,693.06 | 110 | 114 | 0 | 010 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008263 | IM-0053(965) | 005 | I-5, Mounts Rd Vicinity To Berkley St Median Barri | Construction Ahead, Inc. Dba | $1,008,538.71 | DENNIS ENGEL | OR | 04/04/12 | 04/16/12 | 05/07/12 | 10/09/12 | 10/09/12 | $1,169,466.65 | $1,008,538.71 | $991,299.94 | 25 | 25 | -0.5 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008266 | NH-0012(208) | 012 | Us12 Stabilize Slopes Clear Creek Vic | Ais Construction Company | $1,951,774.31 | BILL PRESTON | SC | 04/11/12 | 05/11/12 | 06/06/12 | $1,832,141.00 | $1,951,774.31 | $634,366.09 | 85 | 85 | 38 | 012 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008267 | BH-0008(013) | 101 | Sr 8 / Us 101 Overcrossing - Seismic Retrofit | M J Hughes Construction | $545,208.00 | DENNIS ENGEL | OR | 04/11/12 | 04/17/12 | 05/07/12 | 10/17/12 | 11/19/12 | $699,388.50 | $545,208.00 | $658,500.46 | 45 | 72.5 | -7 | 008, 101 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008268 | STATE | 009 | Sr 9, 176th St Se Vic To Sr 96 Paving | Cemex Construction Materials Pacific | $2,508,376.28 | JOHN CHI | NW | 04/18/12 | 04/23/12 | 05/14/12 | $2,667,995.00 | $2,508,376.28 | $2,213,739.23 | 91 | 91 | 12 | 009 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008269 | STATE | 530 | Sr 530, Fortson Creek Culvert - Fish Barrier | Ram Construction Gen Contractors | $811,871.00 | DAVE CRISMAN | NW | 04/11/12 | 04/18/12 | 05/09/12 | 10/30/12 | $1,337,641.44 | $811,871.00 | $823,232.98 | 33 | 33 | 0.5 | 530 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008270 | NH-0002(829) | 002 | Us 2, Stevens Pass Variable Message Signs | Colvico, Inc. | $1,407,513.00 | KEVIN WALIGORSKI | NC | 04/19/12 | 04/30/12 | 05/24/12 | $1,396,448.64 | $1,407,513.00 | $1,436,369.32 | 45 | 52 | 2 | 002 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008272 | STATE | 005 | I-5, Mellen Street To Blakeslee Junction - Stage 1 | Cascade Bridge, Llc | $21,596,149.85 | COLIN NEWELL | SW | 04/25/12 | 04/30/12 | 05/21/12 | $27,943,652.95 | $21,596,149.85 | $19,623,284.96 | 300 | 325 | 57.5 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008276 | NH-9999(632) | 005 | I-5, Lewis County Detour For Freight Mobility Its | Mill Plain Electric | $1,335,692.00 | CHAD HANCOCK | SW | 05/16/12 | 05/24/12 | 06/14/12 | 01/04/13 | 03/22/13 | $1,521,504.00 | $1,335,692.00 | $1,323,342.07 | 70 | 78 | 0 | 005, 006, 007, 012, 161, 508, 512, 706 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008278 | NH-0014(604) | 014 | Sr 14, Clark Co Line To Prindle Vic. Paver | Kerr Contractors,Inc. | $2,123,175.00 | CHRIS TAMS | SW | 04/25/12 | 04/30/12 | 05/21/12 | 10/18/12 | 12/14/12 | $2,127,904.50 | $2,123,175.00 | $2,184,994.15 | 50 | 52 | 0 | 014 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008279 | IM-0054(282) | 005 | I-5, Dayton Ave N To 128th St Sw Its Rehabilitatio | Elcon Corporation | $1,291,496.00 | MARK SAWYER | NW | 04/25/12 | 04/30/12 | 05/21/12 | 01/08/13 | 02/06/13 | $1,817,156.00 | $1,291,496.00 | $1,279,362.71 | 70 | 70 | 0 | 005, 099 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008280 | IM-0053(964) | 005 | I-5, 48th St To M St Bridge Concrete Pavement Reha | C.A. Carey Corporation | $2,233,510.00 | JON DEFFENBACHER | OR | 05/16/12 | 05/21/12 | 06/13/12 | 09/26/12 | 03/29/13 | $1,674,787.75 | $2,233,510.00 | $2,179,534.46 | 55 | 55 | 0 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008286 | NH-0002(311) | 002 | Us 2, Bickford Ave I/C Safety And Culvert Replacem | Granite Construction Company | $14,311,311.00 | MARK SAWYER | NW | 05/09/12 | 06/08/12 | 06/11/12 | $15,490,448.45 | $14,311,311.00 | $7,674,242.53 | 300 | 308 | 155 | 002 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008288 | STATE | 520 | Sr 520, Evans Creek Eastside Wetland Mitigation | Goodfellow Bros Inc | $3,856,069.00 | ALETA BORSCHOWA | NW | 05/09/12 | 05/17/12 | 06/11/12 | $5,055,879.25 | $3,856,069.00 | $511,426.43 | 215 | 215 | 124 | 520 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008289 | NH0195(053) | 195 | Babbit Road To Colfax Paving | Central Washington Asphalt, Inc. | $1,961,182.40 | DARREL MCCALLUM | ER | 05/03/12 | 05/10/12 | 06/04/12 | $2,303,988.91 | $1,961,182.40 | $1,889,834.18 | 34 | 34 | 0 | 195 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008290 | BR-0099(119) | 099 | Sr 99, Awv S Holgate St To S King St Stage 3 - Atl | Guy F. Atkinson Construction, Llc | $29,371,123.00 | PAUL JOHNSON | NW | 05/23/12 | 05/30/12 | 06/20/12 | $35,642,736.50 | $29,371,123.00 | $12,005,162.42 | 410 | 410 | 235 | 099 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008292 | BR-0101(312) | 101 | Us 101, Bone River Bridge Replace Bridge | Cascade Bridge, Llc | $5,715,393.20 | LORI FIGONE | SW | 05/16/12 | 05/24/12 | 06/15/12 | $6,317,645.00 | $5,715,393.20 | $3,821,340.21 | 220 | 220 | 66 | 101 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008293 | STATE | 097 | Us 97, North Of Goldendale, Wildlife Habitat Conne | Rotschy, Inc. | $2,113,354.68 | CHRIS TAMS | SW | 05/16/12 | 05/21/12 | 06/11/12 | $2,106,341.00 | $2,113,354.68 | $1,789,754.33 | 145 | 145 | 27.5 | 097 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008294 | IM0905(101) | 090 | Bn Rr Br To Vic Geiger Rd Paving | Inland Asphalt Company | $1,667,683.18 | DARREL MCCALLUM | ER | 05/17/12 | 06/12/12 | 07/05/12 | 09/11/12 | 11/06/12 | $2,273,276.00 | $1,667,683.18 | $1,722,946.45 | 30 | 31 | 1 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008295 | BH-0395(096) | 395 | Us 395, Pioneer Memorial Bridge Joint Repair | C.A. Carey Corporation | $1,141,183.00 | MOE DAVARI | SC | 05/09/12 | 05/17/12 | 06/08/12 | 12/02/12 | 12/02/12 | $777,977.00 | $1,141,183.00 | $1,139,860.00 | 20 | 20 | -7 | 395 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008296 | NH0395(098) | 395 | Nsc Francis Avenue Improvements | Graham Construction & Management, Inc. | $14,045,942.90 | DARREL MCCALLUM | ER | 06/21/12 | 08/03/12 | 08/23/12 | $15,958,985.00 | $14,045,942.90 | $3,986,552.07 | 350 | 350 | 226 | 395 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008299 | STATE | 502 | Sr 502 / I-5 To Battle Ground Add Lanes Stage 1 | Tapani Underground, Inc. | $5,194,042.60 | CHRIS TAMS | SW | 05/31/12 | 06/06/12 | 06/26/12 | $7,151,300.75 | $5,194,042.60 | $5,298,106.51 | 75 | 75 | -9 | 502 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008301 | BH-0012(218) | 012 | Us 12 Et Al, 2012 Scr Region Wide Deck Rehabilitat | Penhall Company | $1,264,595.15 | JEFF MINNICK | SC | 05/23/12 | 06/06/12 | 06/26/12 | 11/02/12 | 11/02/12 | $1,569,149.25 | $1,264,595.15 | $1,350,816.82 | 65 | 65 | 0.5 | 012, 022, 261 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008302 | STPF-9999(646) | 012 | Us 12 Et Al, 2010-2011 Scr Region Wide Safety | Coral Construction Company | $849,929.00 | MOE DAVARI | SC | 05/23/12 | 05/29/12 | 06/20/12 | 09/27/12 | 12/12/12 | $800,661.65 | $849,929.00 | $897,270.65 | 40 | 40 | -6.5 | 012, 022, 024, 082, 097, 124, 223, 240, 821, 823 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008303 | BH-0529(018) | 529 | Sr 529, Sb Snohomish River Bridge Special Bridge R | Pcl Civil Constructors Inc | $1,711,104.00 | MARK SAWYER | NW | 05/23/12 | 05/29/12 | 06/19/12 | $2,898,854.00 | $1,711,104.00 | $0.00 | 35 | 35 | 1 | 529 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008304 | STPF-0100(011) | 100 | Sr 100/Sr 100 Spur - Paving | Granite Construction Company | $747,747.00 | LORI FIGONE | SW | 05/23/12 | 05/29/12 | 06/15/12 | 09/25/12 | 01/10/13 | $665,178.30 | $747,747.00 | $685,622.28 | 23 | 24 | 0 | 100 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008305 | STPF-0503(025) | 503 | Sr 503, Ham Rd Vic To Rudy Ross Rd Vic Resurfacing | Granite Construction Company | $1,849,849.00 | LORI FIGONE | SW | 05/23/12 | 05/29/12 | 06/15/12 | 09/11/12 | 11/05/12 | $1,833,417.01 | $1,849,849.00 | $1,771,471.65 | 38 | 38 | 0 | 503 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008306 | NH-STPF-9999(597) | 002 | Sr Us 2/97, Sr 97a, West Of Wenatchee Paving And I | Central Washington Asphalt, Inc. | $2,891,203.15 | BOB ROMINE | NC | 05/17/12 | 05/24/12 | 06/13/12 | $2,655,685.10 | $2,891,203.15 | $2,902,817.77 | 65 | 67 | -18 | 002, 097, 285 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008307 | HSIP-0096(004) | 096 | Sr 96, Dumas Road Channelization | Marshbank Construction, Inc | $297,788.50 | MARK SAWYER | NW | 05/31/12 | 06/06/12 | 06/29/12 | 11/03/12 | 12/21/12 | $308,066.00 | $297,788.50 | $242,713.49 | 20 | 20 | 0 | 096 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008308 | HP-9999(415) | 182 | I-182 / I-90, Rd 100 Vic. And N Bend To Ellensburg | Aztech Electric, Inc. | $1,748,420.86 | JEFF MINNICK | SC | 05/31/12 | 06/06/12 | 06/25/12 | $1,950,184.50 | $1,748,420.86 | $1,423,177.58 | 80 | 90 | 22 | 182 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008310 | STATE | 285 | Sr 285, W End Of George Sellar Bridge Intersection | Selland Construction, Inc. | $9,787,325.01 | BOB ROMINE | NC | 06/14/12 | 06/18/12 | 07/09/12 | $10,182,525.01 | $9,787,325.01 | $4,162,865.40 | 255 | 255 | 132.25 | 028, 285 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008311 | STATE | 005 | I-5 / I-205, Ne 134th St. Interchange(I-5/I-205) S | Max J. Kuney Company | $43,416,928.50 | LEON WINGER | SW | 06/20/12 | 06/29/12 | 07/19/12 | $51,761,282.71 | $43,416,928.50 | $14,865,739.74 | 480 | 480 | 330 | 005, 205 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008312 | NH-0101(338)(340) | 101 | Us 101 / Sr 110, State Highways In Clallam County | Granite Construction Company | $2,784,000.00 | SCOTTY IRELAND | OR | 05/31/12 | 06/06/12 | 06/26/12 | 10/19/12 | 10/22/12 | $2,818,249.05 | $2,784,000.00 | $2,630,443.08 | 60 | 60 | 0 | 101, 110 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008314 | IM-0053(961) | 005 | I-5, Military Rd To Ne 117th St Pavement Repair | Interstate Improvement, Inc. | $5,004,744.22 | HIEN TRINH | NW | 06/06/12 | 06/11/12 | 07/03/12 | $4,831,928.05 | $5,004,744.22 | $3,387,097.95 | 96 | 96 | 40 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008318 | STATE | 005 | Toutle River Sra Water System Repairs | Construction Solutions, Inc. | $130,850.80 | Not Specified | HQ | 06/06/12 | 06/11/12 | 07/06/12 | $126,100.00 | $130,850.80 | $140,568.78 | 130 | 0 | 0 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008320 | BH0395(097) | 395 | Us395 Col River Bridge Deck Rehab Bridge Deck | Razz Construction, Inc. | $1,165,284.00 | BOB HILMES | ER | 06/14/12 | 06/20/12 | 06/27/12 | 11/26/12 | 11/26/12 | $1,580,808.60 | $1,165,284.00 | $1,504,525.57 | 60 | 75 | -24 | 395 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008321 | BH-0006(022) | 006 | Sr 6, Chehalis River Riverside Bridge - Deck Overl | Quigg Bros. Inc. | $350,492.50 | COLIN NEWELL | SW | 06/13/12 | 06/18/12 | 07/09/12 | 09/12/12 | 09/12/12 | $358,693.45 | $350,492.50 | $294,545.17 | 15 | 15 | 8 | 005, 006, 101 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008323 | STATE | 016 | Sr 16 / I-5, Two Year Plant Establishment | Terra Dynamics, Inc | $300,223.00 | MARYLOU NEBERGALL | OR | 05/25/12 | 05/29/12 | 06/18/12 | $287,589.00 | $300,223.00 | $144,511.86 | 60 | 0 | 0 | 005, 016 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008325 | STATE | 005 | I-5, Port Of Tacoma Rd To King Co Line Floodplain | Scarsella Bros., Inc. | $478,358.90 | MARY LOU NEBERGALL | OR | 06/20/12 | 06/25/12 | 07/16/12 | 12/21/12 | $557,648.75 | $478,358.90 | $462,826.46 | 25 | 28 | 2.5 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008328 | NH-HSIP-0014(040) | 014 | Sr 14, Marble Rd Vic Safety Improvements | Nutter Underground Utilities, Inc. | $3,835,534.22 | CHRIS TAMS | SW | 06/27/12 | 07/18/12 | 07/31/12 | $3,844,523.35 | $3,835,534.22 | $2,500,452.69 | 70 | 70 | 10.5 | 014 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008329 | CM0906(219) | 090 | I90 Vic Idaho Rd-State Line Its | Colvico, Inc. | $530,434.00 | DARREL MCCALLUM | ER | 06/28/12 | 07/09/12 | 08/06/12 | $478,979.00 | $530,434.00 | $240,499.32 | 66 | 66 | 59 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008331 | STATE | 020 | Lopez Island Term Trestl Rehab Timber Trestle Reha | Interwest Construction Inc | $264,868.50 | JOHN CALLAHAN | WSF | 06/27/12 | 07/02/12 | 07/23/12 | $287,055.00 | $264,868.50 | $21,136.00 | 40 | 40 | 21 | 020 | Marine Terminal | 2013-04-05 05:52:47.283 | ||
| Active | 008333 | STATE | 020 | Pt Townsend Transfer Span Replace Transfer Span Re | American Construction Co., Inc. | $3,068,815.00 | JOHN CALLAHAN | WSF | 07/11/12 | 07/17/12 | 08/09/12 | $2,616,081.50 | $3,068,815.00 | $2,041,181.75 | 133 | 133 | 25.5 | 020 | Marine Terminal | 2013-04-05 05:52:47.283 | ||
| Active | 008334 | HSIP-0507(023) | 507 | Sr 507, 8th Ave S To 208th St E Safety | Miles Resources Dba Woodworth & Co | $889,752.75 | MARYLOU NEBERGALL | OR | 07/05/12 | 07/09/12 | 07/30/12 | $992,886.25 | $889,752.75 | $865,005.00 | 45 | 45 | 1 | 507 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008335 | IM-0901(483) | 090 | I-90, Asahel Curtis Vicinity Eb - Culvert Repair | Trimaxx Construction | $323,524.50 | JEFF MINNICK | SC | 07/05/12 | 07/09/12 | 07/30/12 | 10/04/12 | 10/17/12 | $305,771.00 | $323,524.50 | $307,970.35 | 28 | 28 | 4 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008338 | STATE | 028 | I-90 / Sr 28, Ncr Major Electrical 2012 | Aztech Electric, Inc. | $395,403.75 | KEVIN WALIGORSKI | NC | 07/12/12 | 07/16/12 | 08/06/12 | 03/01/13 | $489,179.00 | $395,403.75 | $395,399.75 | 50 | 50 | 0 | 028, 090 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008341 | STATE | 002 | Sr2 Update Ped Fac To Meet Ada Stndrds | Cameron-Reilly, Llc | $204,209.80 | DARREL MCCALLUM | ER | 07/12/12 | 07/18/12 | 08/03/12 | $201,649.50 | $204,209.80 | $217,851.03 | 35 | 36.5 | 1.5 | 002, 395 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008342 | STATE | 021 | S Nanamkin Crk Culvert Replace Nt | West Company, Inc. | $597,957.50 | DARREL MCCALLUM | ER | 07/26/12 | 07/31/12 | 08/20/12 | $685,982.70 | $597,957.50 | $69,285.00 | 30 | 0 | 0 | 021 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008344 | BR-0101(207) | 101 | Us 101, Middle Nemah Riv Br. Replace Bridge | Sb Structures, Llc | $3,253,051.05 | LORI FIGONE | SW | 07/25/12 | 07/31/12 | 08/10/12 | $3,367,988.50 | $3,253,051.05 | $0.00 | 224 | 224 | 224 | 101 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008345 | BR-0105(022) | 105 | Sr 105, Smith Creek And North River Replace Bridge | Scarsella Bros., Inc. | $15,345,188.11 | LORI FIGONE | SW | 08/22/12 | 08/31/12 | 09/25/12 | $16,577,947.78 | $15,345,188.11 | $4,688,451.42 | 355 | 355 | 252 | 105 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008346 | NH-0902(437) | 090 | I-90, S Cle Elum Rd Bridge Eb - Approach Slab Repa | M J Hughes Construction | $299,193.00 | JEFF MINNICK | SC | 07/25/12 | 07/30/12 | 08/20/12 | 11/08/12 | 11/08/12 | $347,051.00 | $299,193.00 | $277,086.51 | 16 | 16 | 2 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008351 | 9999(631) | 906 | Sr 906, Travelers Rest Building Renovation | Thornberg Construction Company, | $390,364.00 | Not Specified | HQ | 07/25/12 | 07/30/12 | 08/29/12 | $338,500.00 | $390,364.00 | $405,826.17 | 90 | 0 | 0 | 906 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008352 | IM-0053(960) | 005 | I-5, Spokane Street Interchange Vic Special Bridge | Mowat Construction Company | $2,400,400.00 | ALETA BORSCHOWA | NW | 08/08/12 | 08/15/12 | 09/04/12 | $2,562,993.00 | $2,400,400.00 | $1,322,767.08 | 120 | 120 | 36 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008354 | BH-0012(216) | 012 | Us 12, Railroad Bridge Seismic Retrofit | Massana Construction, Inc. | $150,288.00 | SCOTTY IRELAND | OR | 08/08/12 | 08/14/12 | 09/06/12 | 02/01/13 | 02/06/13 | $204,754.00 | $150,288.00 | $148,650.22 | 30 | 30 | 0 | 012 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008358 | STATE | 161 | Sr 161, Ohop Valley Extension Rd To S. Of 304th St | Totem Electric Of Tacoma, Inc. | $864,988.71 | DENNIS ENGEL | OR | 08/08/12 | 08/14/12 | 09/04/12 | $867,488.40 | $864,988.71 | $913,049.80 | 45 | 69 | 9 | 161 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008361 | STATE | 020 | Sr 20, West Of Twisp Wire Mesh Repair | Hi-Tech Rockfall Construction, Inc. | $158,851.00 | KEVIN WALIGORSKI | NC | 08/16/12 | 08/20/12 | 09/11/12 | 10/18/12 | 10/18/12 | $153,404.00 | $158,851.00 | $162,597.26 | 15 | 15 | 2 | 020 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008362 | STATE | 002 | Us 2 Et Al, Statewide Durable Striping Re-Advertis | Specialized Pavement Marking, Inc. | $1,874,250.67 | JEFF MINNICK | SC | 08/15/12 | 08/20/12 | 09/11/12 | $2,388,409.25 | $1,874,250.67 | $1,602,824.60 | 40 | 40 | 17 | 002, 005, 012, 205, 240, 395 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008363 | STATE | 009 | Sr 9, Pilchuck Creek Replace Bridge | Granite Construction Company | $8,891,323.69 | DAVE CRISMAN | NW | 09/19/12 | 10/09/12 | 10/29/12 | $12,204,445.60 | $8,891,323.69 | $371,053.86 | 270 | 270 | 270 | 009 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008366 | STPE-0104(047) | 104 | Sr 104, Hood Canal Bridge Shoulder Retrofit | Razz Construction, Inc. | $916,323.00 | JEFF COOK | OR | 08/29/12 | 09/13/12 | 10/03/12 | 03/11/13 | $956,923.00 | $916,323.00 | $835,947.28 | 50 | 50 | -32.5 | 104 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008368 | STPF9999(637) | 021 | Sr 21 Et Al, Eastern Region - Safety Res | Frank Gurney, Inc. | $1,273,710.25 | DARREL MCCALLUM | ER | 09/20/12 | 10/05/12 | 11/02/12 | $1,607,796.50 | $1,273,710.25 | $52,260.46 | 75 | 75 | 70 | 021, 027, 028, 194, 231, 260, 261, 263, 271, 272, 274, 278 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008369 | IM-0052(206) | 005 | I-5, Barnes Road And Us 12 Interchanges Illuminati | Travers Electric Inc. | $179,997.10 | LORI FIGONE | SW | 08/29/12 | 09/04/12 | 09/28/12 | $253,559.00 | $179,997.10 | $0.00 | 27 | 27 | 17 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008371 | ER(NH)-1201(001) | 090 | I-90, Raging River Bridge Vicinity Slope Stablizat | Carter & Company Inc Dba | $354,900.25 | HIEN TRINH | NW | 09/19/12 | 09/20/12 | 10/10/12 | 02/08/13 | $490,007.00 | $354,900.25 | $345,448.00 | 30 | 30 | 0 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008375 | BH-0024(018) | 024 | Sr 24, S Of Othello Sagehill Wasteway Deck Repair | Penhall Company | $312,822.50 | KEVIN WALIGORSKI | NC | 10/11/12 | 10/16/12 | 11/28/12 | $235,544.00 | $312,822.50 | $0.00 | 20 | 20 | 20 | 024 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008376 | BR-NH-0101(307) | 101 | Us 101, Shore Rd To Kitchen-Dick Rd Widening | Scarsella Bros., Inc. | $27,069,690.00 | JERRY MOORE | OR | 11/07/12 | 11/21/12 | 12/11/12 | $33,989,672.79 | $27,069,690.00 | $879,686.41 | 543 | 543 | 485 | 101 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008377 | BH-0020(170) | 020 | Sr 20, Snc Railroad Bridge Seismic Retrofit | Nordland Construction | $204,776.00 | JERRY MOORE | OR | 10/17/12 | 10/22/12 | 12/03/12 | 03/25/13 | 03/25/13 | $228,192.50 | $204,776.00 | $135,744.00 | 54 | 54 | 0 | 020 | Design Bid Build | 2013-04-05 05:52:47.283 |
| Active | 008378 | HSIP0195(054) | 195 | Cheney-Spokane Road New I/C - New Interchange | Selland Construction, Inc. | $6,408,374.60 | CHAD SIMONSON | ER | 11/01/12 | 11/09/12 | 12/07/12 | $8,374,454.20 | $6,408,374.60 | $165,898.90 | 150 | 150 | 138 | 195 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008379 | BH/STPF0099(102) | 099 | Spokane St O/Cross Timber Replace | Mid-Mountain Contractors, Inc. | $9,213,158.00 | HIEN TRINH | NW | 11/15/12 | 11/29/12 | 12/19/12 | $12,395,530.00 | $9,213,158.00 | $1,028,594.25 | 310 | 310 | 255 | 099 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008380 | BH0016(025) | 016 | Tnb Special Repair | Mowat Construction Company | $434,604.00 | MARYLOU NEBERGALL | OR | 10/31/12 | 11/07/12 | 11/28/12 | $380,784.00 | $434,604.00 | $0.00 | 10 | 0 | 0 | 016 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008381 | CM-HSIP-STPE0099(110 | 099 | Sr 99, Lincoln Way Vic To Airport Rd Vic Sb Sidewa | Interwest Construction Inc | $1,278,347.10 | MARK SAWYER | NW | 12/12/12 | 12/17/12 | 01/08/13 | $1,248,573.40 | $1,278,347.10 | $0.00 | 80 | 0 | 0 | 099 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008383 | IM0906229 | 090 | I-90, Spokane Viaduct Latah Creek To Divison St - | Northeast Electric, Llc | $1,193,973.67 | BOB HILMES | ER | 11/15/12 | 11/21/12 | 12/12/12 | $1,428,293.00 | $1,193,973.67 | $194,231.20 | 75 | 75 | 46 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008384 | STATE | 020 | Sr 20, Challenger Rd Vicinity - Unstable Slope Uns | Trimaxx Construction | $354,903.50 | SHANE SPAHR | NW | 11/07/12 | 11/14/12 | 12/11/12 | $377,786.00 | $354,903.50 | $0.00 | 20 | 20 | 11 | 020 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008385 | NH0002(825) | 002 | Us2 E Of Coles Corner Box Culvert Box Culvert | Selland Construction, Inc. | $644,193.20 | ROBERT ROMINE | NC | 12/06/12 | 12/11/12 | 12/31/12 | $929,103.00 | $644,193.20 | $0.00 | 30 | 0 | 0 | 002 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008386 | IM0906(228) | 090 | I-90 Div St To Lib Park Illumin Rebuild Liberty Pa | Northeast Electric, Llc | $1,196,590.00 | BOB HILMES | ER | 12/06/12 | 12/13/12 | 01/03/13 | $1,010,262.00 | $1,196,590.00 | $61,638.00 | 60 | 60 | 60 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008387 | STPF0101(345) | 101 | Us 101, Commercial Street Signal Replacement | Mill Plain Electric | $339,135.00 | Not Specified | SW | 12/19/12 | 12/24/12 | 01/14/13 | $455,026.00 | $339,135.00 | $0.00 | 36 | 36 | 36 | 101 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008388 | HSIP9999(440) | 005 | I-5 Or Redirectional Landform Mitig Mitigation | Petersen Brothers, Inc. | $179,962.01 | DENNIS ENGEL | OR | 12/05/12 | 12/10/12 | 12/31/12 | 03/20/13 | $195,159.00 | $179,962.01 | $154,654.01 | 12 | 12 | 0 | 005, 016 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008390 | HSIP-0016(026) | 016 | Sr 16, S Of Burnham Dr To Sr 302 Safety Improvemen | Petersen Brothers, Inc. | $286,732.50 | JEFF COOK | OR | 11/28/12 | 12/03/12 | 12/14/12 | 02/22/13 | $401,555.00 | $286,732.50 | $285,574.15 | 22 | 22 | 7 | 016 | Design Bid Build | 2013-04-05 05:52:47.283 | |
| Active | 008392 | NHHSIP0097(160) | 097 | Us97 N Of Daroga State Park Turn Lanes Turn Lanes | Selland Construction, Inc. | $227,055.00 | ROBERT ROMINE | NC | 11/29/12 | 12/10/12 | 12/31/12 | $289,101.50 | $227,055.00 | $0.00 | 25 | 0 | 0 | 097 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008393 | IM/NHS-9999(460) | 405 | Concrete Pavement Rehabilitation | Guy F. Atkinson Construction, Llc | $7,277,888.00 | JANICE FAHNING | NW | 02/07/13 | 02/12/13 | 03/04/13 | $8,300,000.00 | $7,277,888.00 | $0.00 | 247 | 247 | 223 | 405, 518 | Design Build | 2013-04-05 05:52:47.283 | ||
| Active | 008394 | CM9999(639) | 090 | Variable Message Signs Replacement Replacement - I | Colvico, Inc. | $790,104.00 | BOB HILMES | ER | 12/13/12 | 12/20/12 | 01/11/13 | $758,604.00 | $790,104.00 | $0.00 | 60 | 0 | 0 | 002, 090 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008395 | BH0904(121) | 090 | I90 2013 Er Bridge Deck Replace | Mowat Construction Company | $497,991.50 | Not Specified | ER | 12/20/12 | 01/02/13 | 01/22/13 | $666,666.20 | $497,991.50 | $0.00 | 30 | 0 | 0 | 090 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008397 | STPF0009(067) | 009 | Sr 9, Np Creek Fish Passage Barrier Removal | Stremler Gravel Inc 250 Bay-Lyn Drive 98 | $351,486.00 | SHANE SPAHR | NW | 01/09/13 | 01/14/13 | 02/05/13 | $521,000.00 | $351,486.00 | $0.00 | 19 | 0 | 0 | 009 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008399 | NH0832(093) | 082 | Us12 To Valley Mall Vic Paving Paving | Columbia Asphalt & Gravel, Inc. | $2,671,716.65 | BILL PRESTON | SC | 01/16/13 | 01/22/13 | 02/13/13 | $3,039,628.50 | $2,671,716.65 | $0.00 | 51 | 51 | 51 | 082 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008402 | FBD0021(022) | 021 | Keller Ferry Terminal Rehab Terminal Rehabilitatio | Max J. Kuney Company | $1,930,000.00 | BOB HILMES | ER | 01/24/13 | 01/31/13 | 02/20/13 | $1,885,624.00 | $1,930,000.00 | $0.00 | 60 | 60 | 60 | 021 | Marine Terminal | 2013-04-05 05:52:47.283 | ||
| Active | 008403 | IM-4053(962) | 405 | Nb Sr167 Ramp-Nb 405 Major Drainage Rep Major Drai | Active Construction Inc. | $489,405.21 | Not Specified | NW | 01/24/13 | 02/01/13 | 03/05/13 | $504,021.00 | $489,405.21 | $0.00 | 32 | 0 | 0 | 405 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008404 | STPF0730(003) | 730 | Us730 Spur Paving - Paving | Inland Asphalt Company | $1,332,332.32 | MOE DAVARI | SC | 01/30/13 | 02/08/13 | 02/28/13 | $1,455,759.00 | $1,332,332.32 | $0.00 | 35 | 35 | 35 | 730 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008405 | IM0053(940) | 005 | Sign Replace/Lane Electrical & Express Lane Electr | Valley Electric Co. Of Mt Vernon | $4,878,672.00 | HIEN TRINH | NW | 01/16/13 | 01/29/13 | 02/19/13 | $4,611,226.91 | $4,878,672.00 | $0.00 | 170 | 170 | 157 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008406 | IM0053(968) | 005 | Sr510-Sr512 Its Fiber Improvements I-5 | Magnum Power Llc 6902 Ne 219th St, Battl | $1,104,454.09 | MARYLOU NEBERGALL | OR | 01/24/13 | 02/04/13 | 02/25/13 | $1,339,355.00 | $1,104,454.09 | $8,058.82 | 85 | 85 | 75 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008407 | CMAQ2009(39) | 005 | I5 Traveler Info/Incident Mgmt Ph2 Incident Manage | Northeast Electric, Llc | $157,534.00 | Not Specified | SW | 01/09/13 | 01/10/13 | 01/30/13 | $169,498.00 | $157,534.00 | $0.00 | 12 | 0 | 0 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008408 | GBT8081 | 163 | Pt Defiance/Tahlequa Trans Span O/Lays Physical Se | Dalton Electric Co. | $399,949.00 | Not Specified | WSF | 01/09/13 | 01/18/13 | 02/20/13 | $451,054.00 | $399,949.00 | $0.00 | 70 | 70 | 58 | 163 | Marine Terminal | 2013-04-05 05:52:47.283 | ||
| Active | 008409 | CBI0097(155) | 097 | N Ov Riverside Nb Passing Lane Nb Passing Lane | Selland Construction, Inc. | $829,108.19 | KEVIN WALIGORSKI | NC | 01/10/13 | 01/14/13 | 02/04/13 | $957,729.80 | $829,108.19 | $0.00 | 35 | 35 | 35 | 097 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008411 | NH/STPF-0000(635) | 012 | Us12 Scr Region-Wide Safety | Construction Ahead, Inc. Dba | $376,897.75 | MOE DAVARI | SC | 01/24/13 | 01/28/13 | 02/09/13 | $397,257.50 | $376,897.75 | $0.00 | 30 | 30 | 17 | 012, 014, 097, 127, 129, 241, 261 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008413 | NH-0101(162) | 101 | Us101 Ennis St Signal Rebuild Rebuild Signal | Taurus Industries Inc 1036 73rd Ave Se | $256,646.00 | JERRY MOORE | OR | 02/06/13 | 02/11/13 | 03/04/13 | $281,510.00 | $256,646.00 | $0.00 | 30 | 0 | 0 | 101 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008415 | HSIP0026(026) | 026 | Sr26 Othello @1st St Ph 2 Phase 2 | Granite Construction Company | $1,043,493.44 | Not Specified | NC | 02/21/13 | 02/25/13 | 03/18/13 | $1,107,984.40 | $1,043,493.44 | $0.00 | 35 | 0 | 0 | 026 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008417 | STATE | 017 | Ncr Ada Rural Upgrades Sr 017, 028 | Halme Builders, Inc. | $169,178.00 | ROBERT ROMINE | NC | 02/14/13 | 02/19/13 | 03/11/13 | $175,199.50 | $169,178.00 | $0.00 | 25 | 25 | 25 | 017, 028 | Design Bid Build | 2013-04-05 05:52:47.283 | ||
| Active | 008422 | IM0052209 | 005 | Maytown-Scatter Creek Roof & Skylight Replacement | DW Not Applicable | $169,186.00 | Not Specified | HQ | 02/27/13 | 03/04/13 | 03/25/13 | $186,374.00 | $169,186.00 | $0.00 | 005 | Design Bid Build | 2013-04-05 05:52:47.283 | |||||
| Active | 008424 | CBI0097158 | 097 | North Of Brewster Passing Lane | DW Not Applicable | $979,499.91 | Not Specified | NC | 03/07/13 | 03/13/13 | 04/02/13 | $1,105,122.35 | $979,499.91 | $0.00 | 097 | Design Bid Build | 2013-04-05 05:52:47.283 | |||||
| Active | 008429 | ITS2003062 | 014 | Traveler Information Enhancements Phase Ii | DW Not Applicable | $146,654.00 | Not Specified | SW | 03/06/13 | 03/21/13 | 04/02/13 | $168,804.00 | $146,654.00 | $0.00 | 014, 197 | Design Bid Build | 2013-04-05 05:52:47.283 |