The current road surface was deteriorating in this eight-mile section. Repaving preserves the existing pavement structure and extends pavement service life. The end result is a safer highway, a smoother driving surface and extended roadway life. This was achieved by overlaying the existing pavement with about 2 inches inches of Hot Mix Asphalt (HMA).
 | Economic Incentive
Preserves the roadway foundation by repaving the driving surface. Also provides a smoother ride for motorists.
|
Partnerships & Cooperation
Funding for the work came through a partnership with the Federal Highway administration.
Funding
This project was funded through the following sources:
State & Federal Funds - Construction bid $1,732,000