Skip Top Navigation

US 12 - White Pass - Slope Stabilization Projects

Status

January 2012

The project to stabilize slopes on US 12 west of White Pass has been completed.

  • WSDOT and contractor Janond Inc. of Dorian, Quebec, Canada stabilized the slopes on US 12, west of White Pass, from milepost 143 to 154.5.
  • View the map for project locations.

  • Work on slopes east of White Pass near Clear Creek Falls (mileposts 154.34 to 154.38) and Rimrock Lake tunnel (mileposes 164.97 to 165.02) is schedule to start in the early summer and completed in the fall of 2012.

When the planned projects are completed, WSDOT will have stabilized eleven slopes in a 25 mile corridor on US 12 near White Pass. The series of unstable slope projects will be on going each summer from 2006 to 2013.

View the map for project locations.

Next summer, work will consist of removing loose rock, potentially hazardous timber and other debris from the slopes. Rock anchor bolts will be used to hold large rocks on the slopes. Wire mesh slope protection fencing will be installed to protect motorists from potential rockfall onto the highway.

Why is WSDOT stabilizing these slopes?
The slopes identified on US 12 are considered high risk sites. WSDOT uses a statewide unstable slope prioritization process to identify and rate potential slide areas. We evaluate a number of factors to determine the "slope rating" of each location. The higher the slope rating, the higher the risk of a slide.

The End Result
WSDOT will evaluate the unstable slopes, remove loose rocks, timber, and debris, and stabilize the slopes using bolts and protective fencing.

Project Benefits

  • Safety. By removing unstable material and installing rock bolts and protective fencing, WSDOT will reduce the potential for future rockslides.
  • Mobility. This project will reduce the possibility of emergency closures and traffic delays due to rock slides.

What is the project timeline?
WSDOT plans to have slope stabilization construction work on US 12 through 2013.

Work on the first three sections started late summer 2006 and was completed in 2007.

Work on the second two sections (MP 162 & 162.2) was completed in 2008.

Work on the third section of slopes, west of White Pass (MP 141.8 to 142) and (MP 144.3 to 144.4), was completed in August 2009. 

Work on slopes west of White Pass (MP 142.99-143.27 & 144.13-146.90) was completed in November 2011. Work on this project was featured on a National Geographic Channel show called Rock Starts in December 2011.

Work on slopes east of White Pass near Clear Creek Falls (mileposts 154.34 to 154.38) and Rimrock Lake tunnel (mileposes 164.97 to 155.02) is schedule to be completed in the fall of 2012.

Financial Information

Funding Source Amount
Pre-Existing Funds (PEF)
Total $16.9 million 

How can I get more information?
Contact:
Bill Preston,  Project Engineer
WSDOT South Central Project Office
PO Box 12560
Yakima, WA 98909
Phone: (509) 577-1810

back to top