SR 99 - North of Lincoln Way Sidewalks - Complete April 2008

Project Status - Complete

View larger project map


View more project photos

Overview
In spring 2008 we installed 1,800 feet of new sidewalks in each direction of SR 99 in Everett. We also widened the shoulder of the road and installed new signing, lighting, and drainage.

Contractor Wilder Construction crews began work in January 2008 and completed this project in early April 2008, nearly one month ahead of schedule.

How You Benefit
Cross GlyphImproves Safety
Before this project, pedestrians attempting to access residential developments, restaurants and other businesses in this area were forced to walk on the narrow shoulder of the highway. New sidewalks along this section of SR 99 remove pedestrians from walking near fast-moving traffic and provide a safe walkway through the area.

Partnerships & Cooperation
At WSDOT we seek to address the concerns of the tribal nations using the process outlined in Section 106 of The National Historic Preservation Act and the WSDOT Tribal Consultation Policy adopted in 2003 by the Transportation Commission as part of the WSDOT Centennial Accord Plan.

To learn more about the tribal consultation process please visit WSDOT's Tribal Liaison page, where you'll find links to WSDOT Centennial Accord Plan and WSDOT's Tribal Consultation Policy (Adopted by the Transportation Commission on February 19, 2003).

Funding

2005 Gas Tax (Partnership Funding) - $1.2 million
Existing Funds - $372,000
Total Funding Available From All Sources - $1.6 million

Contact Us
Project Engineer Marlin Lenssen
WSDOT Project Office
PO Box 330310
Seattle, WA 98133-9710
Phone: (425) 225-8796
E-mail: lenssmj@wsdot.wa.gov

or

Communications Aurora Jones
15700 Dayton Avenue North
PO Box 330310 MS: 103
Seattle, WA 98133-9710
Phone: (206) 440-4697
E-mail: jonesa@wsdot.wa.gov

back to top