SR 9 - SR 92 - Intersection Improvements

Status

May 2012

  • Driver alert: The SR 9/SR 92 intersection will close around the clock from 11 p.m. Friday, June 22 to 5 a.m. Monday, June 25. View detour routes
  • We awarded this project Jan. 26 to Guy F. Atkinson Construction of Renton for $3.3 million, 14 percent below the engineer's estimate.
  • Sign up for e-mail updates to learn more about projects in Snohomish County.

This project was originally part of the SR 9/Lundeen to SR 92 project. Instead, WSDOT and the city of Marysville are now partnering to built this project in anticipation of the city constructing a fourth leg to the west of the current SR 9/SR 92 intersection.

Crews will widen the intersection and add lanes to accommodate the planned fourth leg of the intersection.

Why is WSDOT making improvements to the SR 9/SR 92 intersection?
Adding additional through and turn lanes will reduce congestion on to SR 9 and SR 92, making it easier for drivers to make their turns. Reducing congestion will also decrease the number and severity of accidents at this location.

When the city of Marysville completes a new road to the west of SR 9, it will join the SR 9/SR 92 intersection as a fourth leg. These improvements will make it easy to connect this new road to the current intersection.

The End Result
We will add a southbound through lane and southbound left-turn lane on SR 9. On SR 92, we will add a left-turn lane and room for two future through lanes 

The widened roadway on SR 9 at the intersection will accomodate bus pullouts. Crews will also update the illumination and signal system. 

Project Benefits

  • Traffic flow - Adding the extra turn lanes and through lanes will reduce congestion and improve traffic flow for drivers.
  • Safety - Improvements at this intersection will reduce the number of congestion-related accidents like rear-end and sideswipe collisions.

What is the project timeline?
July 2011 - Requested qualifications from interested contractors
September 2011 - Requested proposals from qualified contractors.
Jan. 26, 2012 - We awarded this design-build project to Guy F. Atkinson Construction for $3.3 million.
June 2012 - We expect to begin construction
Fall 2012 - We expect to complete construction

Financial Information

The estimated cost for this project is $5.6 million. Funding will come from the following resources:

  • City of Marysville - $4.5 million
  • 2005 Gas Tax -  $1.1 million

How can I get more information?
Contact:
Bronlea Mishler
WSDOT Communications
mishleb@wsdot.wa.gov 