SR 542 - Fossil Creek to Wells Creek Rd Vicinity - Paving - Complete Fall 2012

Overview
We repaved three miles of Mount Baker Highway east of Glacier between Fossil Creek and Wells Creek Road (mileposts 38-42).

How You Benefit
Cross GlyphImproves Safety
In addition to repaving, we also upgraded a number of the safety features along the highway like striping, reflectors, markers, signs and guardrail. During the dark winter months, drivers will be able to see the centerline and shoulders more easily.

Partnerships & Cooperation

Funding

  • Total funding: $1.9 million (existing funds)

Contact Us
Project Engineer, Chris Damitio
460 Stuart Road,
Bellingham, WA 98226
360-788-7403
Chris.damitio@wsdot.wa.gov

Communications, Bronlea Mishler
1043 Goldenrod Road, Suite 101
Burlington, WA 98233
360-757-5997
Bronlea.Mishler@wsdot.wa.gov