November 2009
- WSDOT engineers are in the early stages of design.
- We will ask contractors to bid on the project in spring 2010.
- Construction will begin in summer 2010 and continue through spring 2011.
If you drive on State Route 520 through Bellevue, one of the things you may not notice is that a good portion of the ride is on bridges that cross a maze of surface streets.
In 2010 the Washington State Department
of Transportation will retrofit 11 of the bridges between Interstate 405 and 148th Avenue NE to better withstand earthquakes.
Why is WSDOT
retrofitting bridges on SR 520?
The Puget Sound region is prone to earthquakes. Most of the SR 520 bridges were built in the 1960s and early 1970s when engineers didn’t know as much about how earthquakes affect these structures.
Lessons learned after the severe California earthquakes of the 1970s and 1980s led to a change in how engineers design bridges to withstand
earthquakes. But most of Washington’s 3000 vehicular bridges were built before these new design standards were incorporated.
WSDOT developed its Seismic Retrofit Program in 1990 in response to the new design standards and to greater understanding of the earthquake risk to the Puget Sound area. In this program WSDOT is strengthening more than 900 bridges and structures across the state.
The End Result
When work is complete in 2010 the following bridges will be better equipped to withstand severe earthquakes.
• SR 520 bridges (2) over 116th Avenue NE (built in 1966)
• SR 520 bridges (2) over BNSF railroad (built in 1966 and 1969)
• SR 520 bridges (2) over Northup Way (built in 1971)
• SR 520 bridges (2) over the NE 124th Street on-ramps (built in 1971)
• SR 520 bridges (2) over 130th Avenue NE (built in 1970)
• SR 520 bridge (1) over NE 24th Street (built in 1970)
Crews will strengthen the bridges by:
• Placing steel jackets over the vertical columns on nine of the 11 bridges
• Installing reinforced concrete bolsters on the horizontal crossbeams of seven of the 11 bridges.
Project Benefits
- Safety: Strengthening bridge columns and crossbeams will reduce the risk of catastrophic failure during an earthquake.
- Environment: Crews will filter storm water runoff during construction.
What is the project timeline?
- We will ask contractors to bid on the project in spring 2010.
- Construction will begin in summer 2010 and continue through spring 2011.
Financial Information
This project is funded through the following sources:
2005 Gas Tax (Partnership Funding) - $5,353,000
Total Funding Available From All Sources - $5,353,000
How can I get more information?
Contact:
Project Engineer Gary L. McKee
15700 Dayton Ave N
Seattle, WA 98133
Phone: 206-440-4612
E-mail: mckeeg@wsdot.wa.gov
Communications Meghan Soptich Pembroke
15700 Dayton Ave N
Seattle, WA 98133
Phone: 206-440-4704
E-mail: pembrom@wsdot.wa.gov
back to top