SR 410 - Additional Lanes and Signal


View entire map  The project is located on SR 410 in the City of Bonney Lake, east Pierce County.

Status

November 2009

Current project work includes:

  • Utility relocation and completion of plans, specifications and estimate.
  • Coordination with the City of Bonney Lake.
  • Final project design.
  • Evironmental documentation and permitting.
  • Right-of-Way purchase.

This project is scheduled to advertise for construction bid in November 2009. Construction is scheduled to be complete in the summer of 2011.

Why is WSDOT widening SR 410?
Current traffic volumes on SR 410 surpass the capacity of a two-lane roadway, reducing mobility and safety. The area around Bonney Lake and east Pierce County has developed tremendously in the last 10 years and SR 410 is feeling the effect of this development. 

The End Result
This 1.49-mile project adds one lane in each direction of SR 410, milepost 15.61 to 17.10, with a raised median separating the eastbound and westbound traffic between 214th and 234th avenues.

WSDOT worked with the City of Bonney Lake to plan three future median access breaks within the project limits. The approximate locations are at the ¼, ½ and ¾ points in the project area, although the exact locations depends on the design of the City’s arterial street system.
 
A new traffic signal and revised traffic movements at the split intersection of 233rd Avenue East and 234th Avenue East will improve safety and mobility.

This projects also adds stormwater treatment facilities, lighting at the traffic signals and bus stop improvements.

Project Benefits

  • Safety. The intersection of 233rd and 234th Avenue is currently identified as a high accident location. This project improves safety by  installing a traffic signal along with rearranging the traffic movements. The traffic volumes for this area are so high there are very few gaps in the traffic flow to make left turns, which causes many people to make risky maneuvers -- leading to collisions.
  • Congestion. By adding one lane in each direction and restricting left turns to intersections with designated turn lanes, the movement for mainline SR 410 will improve significantly.

What is the project timeline?
Preliminary engineering, utility relocations, environmental documentation and right of way acquistitions are currently under way. 

This project will be advertised for construction bid in November 2009. Construction is scheduled to be complete by summer of 2011.

Financial Information

This project is funded through the following sources:

  • 2005 Gas Tax (Partnership Funding) - $17,048,737
  • 2003 Gas Tax (Nickel Funding) - $8,909,792
  • Existing Funds - $2,592,910
  • Other Funds - $788,597
    Murray Hill ($42,098), Parker Pacific ($6,290), Pettitt LLC ($23,220), Foothills Estates ($5,000), Hahto Addition ($51,350), Quadrant Corp ($10,264), Home Depot ($184,000), T&S Properties ($244,000), Harborstone Credit Union ($16,576), Panorama West ($18,233), Mazatlan Restaurant ($20,900), Bonney Lake Marketplace Developers, LLC ($166,667)
  • Total Funding Available From All Sources - $29,340,036

How can I get more information?
Contact:
MaryLou Nebergall, Project Engineer
WSDOT Tumwater Project Engineer Office
PO Box 47447
Tumwater, WA 98504-7447
Phone: 360-570-6750