SR 3 - Pioneer Way and Big Valley Rd - Signals - Complete May 2008

Project Status - Complete
Thumbnail of map
View entire map



New signal systems and lane channelization improves safety at SR 3 and Pioneer Way.

Overview
This project improves channelization and adds two signals on SR 3 at Pioneer Way and Big Valley Road north of Poulsbo. Work began in February 2008, and the project was operationally complete in May 2008.

How You Benefit
Cross GlyphImproves Safety
The addition of signals systems to SR 3 at its intersections with Pioneer Way and Big Valley Road will reduce the number of serious collisions.

Partnerships & Cooperation
WSDOT thanks the people of Kitsap County for their patience and safe driving through the work zones during the project.

Funding

This project is funded from the following sources:

• Federal funds - $1,350,322
State funds -          $17,871

Total Funding Available From All Sources - $1,368,192

Contact Us
MaryLou Nebergall , Project Engineer
WSDOT Tumwater Project Engineer Office
PO Box 47447
Tumwater, WA 98504-7477
Phone: 360-570-6750

back to top