SR 21 - Keller Ferry Replacement

Under construction

 View Entire Map


First weld
Secretary of Transportation, Paula Hammond welding the first piece of the new vessel keel.

Hull Construction Augst 2012
Hull construction in August 2012

More vessel construction photos can be found here.

The Martha S
The current vessel "Martha S." on her way to drydock for repairs in October, 2009. 

Status

April 2013

  • The hull sections are in place and the superstructure will be delivered to Grand Coulee as portions are completed.
  • On June 19, 2012, the Washington State Transportation Commission passed a resolution to name the new Keller Ferry Vessel, "Sanpoil."
  • Vessel construction began on March 28, 2012 with Secretary of Transportation Paula Hammond performing the first "ceremonial" weld. 
  • On Nov. 16, 2011 WSDOT awarded the construction contract to Foss Maritime Co. Read the news release.
  • Details about the replacement vessel are available in the project contract.
  • Keller Ferry operational status is now available on the 511 telephone info system in Washington. Follow the "ferry" options on the menu.

This project includes the repair and refurbishment of the Martha S. and design and construction of a replacement ferry boat with associated vehicles loading terminals.

Why is WSDOT replacing the existing Keller Ferry vessel?
The current vessel, the Martha S., has been in service on this route since 1948.  Replacement parts are no longer being commercially manufactured, they now  must be custom-made as needed.  The vessel has a limited capacity, especially when large trucks are on board.

The End Result
A more reliable vessel with enhanced passenger amenities.

Project Benefits
Reduced service interruptions and increased safety for ferry users.

What is the project timeline?

  • July 2011 – Construction contract advertised for bids
  • Aug. 2011 - Pre-bid site visit for interested contractors
  • Nov. 2011 - Bid opening (three bids received). Contract awarded to Foss Maritime Co.
  • February 2012 - Construction started
  • March 2013 - Modules move to Grand Coulee for final assembly
  • July 2013 – Launch vessel

Financial Information

Project signage will reflect the cost of construction engineering, project bid award and sales tax.

Financial Data for PIN 602110J
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $11,616
Total $11,616

Funding noted above consists of $9,641,000 in federal funds, $361,000 in state funds, and $2 million from the Colville Confederated Tribes.

How can I get more information?
Contact:
Al Gilson, Communications Manager
WSDOT Eastern Region
2714 N. Mayfair
Spokane, WA 99207
509-324-6015
al.gilson@wsdot.wa.gov

Laura Johnson, Communications
WSDOT Ferries Division
2901 3rd Ave., Ste. 500
Seattle, WA 98121
206-515-3913
laura.johnson@wsdot.wa.gov

back to top