TEAL secured at bridge site. During the
evening hours on Tuesday, October 3, crews successfully moored the TEAL
under the bridge's west side span. This successful attempt followed a
previous mooring attempt on Friday, September 29, during which time one
of four winch anchor lines broke during tension tests. Contractor Tacoma
Narrows Constructors (TNC) has since replaced the winch line and moved
forward with construction activities. TNC has an aggressive lift schedule
planned for the TEAL's 15 deck sections, and this week two deck sections
are expected to be lifted into place. Mariners are advised to watch the
mariner's update for changing restrictions (see mariner's daily update).
» View More