All hands on deck!
In June, bridge crews will turn their attention to deck
assembly work. A total of 46 individual deck sections, each averaging
120-by-70 feet, will be shipped from Korea to Puget Sound. Deck assembly
will take place between mid-June and October.
May 16, 2006: Korean ship carrying the first deck sections
and bound for Puget Sound departs from Koji Island.
June 12, 2006: First deck sections arrive by ship in
Commencement Bay.
June 19, 2006: (Give or take a day), the ship sails to
the Narrows channel and the first section is lifted into place.
Note: Ship departure and arrival dates may vary by a few days.