Washington State Department of Transportation
WSDOT NewsSite IndexContact WSDOTWSDOT Home
Traffic & RoadsProjectsBusinessEnvironmentalMaps & Data
Tacoma Narrows Bridge Project

Project Info
•  

Project Home

•  

Bridge Open

»  

Building the Bridge

•  

Finance & Schedule

•  

History & More

•  

Just the Bridge Facts

•  

Photo Album

•  

Tolls: Good To Go!

•  

Traffic Information

•  Building the New Tacoma Narrows Bridge
TNB Tolling


•  Nighttime noise construction information, (253) 620-4440
•  Contact the TNB Office, 1 (877) 762-7769

Contact us

Lisa Murdock
Olympic Region Communications Manager
  (360) 357-2789
WSDOT Olympic Region
  (360) 357-2600
Contact us and tell us
what you think:
orfeedback@wsdot.wa.gov or
Online Bridge Form

WSDOT
3214 50 Street Court NW, Building D, Suite 302
Gig Harbor, WA 98335

TNC
2110 14th Ave. NW
Gig Harbor, WA 98335


» Unsubscribe

Building the Bridge

Suspension Bridge: Learn more about the Caissons Suspension Bridge: Learn more about the Towers Suspension Bridge: Learn more about Cable Spinning Suspension Bridge: Learn more about the Bridge Deck Suspension Bridge: Learn more about the Anchorage Suspension Bridge

Interactive illustration of a suspension bridge
Hover over the structural elements to learn more

Caissons

Foundations Supporting the Towers

The massive concrete and steel foundations that support the bridge towers of the new suspension bridge are called caissons. Construction of the foundations began on land and ended on the Narrows seabed, some 200 feet below the surface of Puget Sound.

In early 2003, Todd Pacific Shipyards in Seattle built the first part of the caisson called the “cutting edge.” After the caissons made their journey from Seattle to the Port of Tacoma, construction continued on the outer steel skin. By summer of that year, and after reaching 78 feet in height, the monoliths made yet another trip. Four Foss Maritime tugboats hauled what looked like floating cities through Commencement Bay, around Point Defiance and to the Narrows.

Upon their arrival in the Narrows, each rectangular box of waterproof concrete and reinforced steel measured 130-feet long, 80-feet wide and 78-feet high and weighed 14,000 tons. When completed, each caisson weighed in at 85,000 tons and contained six millions pounds of steel along with 40,500 and 37,000 cubic yards of concrete in the Tacoma and Gig Harbor structures, respectively.

After six months of placing concrete within the foundations’ walls, the Gig Harbor and Tacoma caisson touched down on the Narrows seabed in December 2003 and January 2004, respectively. The Gig Harbor caisson touched down first (133 feet below water) as the west Narrows seabed is shallower. And, the Tacoma foundation reached bottom at 154 feet. In the case of both, a global positioning system and laser surveying (beams) positioned these giants with precision.

During the first half of 2004, workers continued building the caisson walls. Shortly thereafter, the caissons were embedded another 62 feet below the Narrows mud line. Workers dredged ton after ton of seabed soil, and as a result of dredging, the massive weight of the caisson pushed it deep below the seabed.

By mid-summer 2004, caisson construction had wrapped up: bridge workers poured a 15-foot concrete seal or distribution cap over the top. That cap became the base for the new bridge towers.

GIG HARBOR CAISSON  
West Narrows Water Depth 133 feet
Depth Below Seabed 57 feet
Total Height of Finished Caisson 190 feet
   
TACOMA CAISSON  
East Narrows Water Depth 154 feet
Depth Below Seabed 62 feet
Total Height of Finished Caisson 216 feet
Tacoma Narrows Bridge caisson construction
Caisson is the engineering term for a suspension bridge's foundation. It's from the French word caisse, meaning box.
A caisson is made of steel-reinforced and waterproof concrete with an open central core.
The Gig Harbor caisson touched down on the Narrows seabed in December 2003, the Tacoma caisson reached bottom in January 2004.
Each completed caisson has six million pounds of steel overall and roughly 40,000 cubic yards of concrete.

See glossary for more bridge engineering terms.


« Back to previous page



  Copyright WSDOT © 2005

    Traffic & Roads | Site Index | Contact WSDOT | WSDOT Business | WSDOT Home