| The "Suspension" Part of
the Bridge
As compared to building concrete towers 17½
feet at a time, connecting “land to sea” with steel wire is
a fairly simple proposition. Fabrication of the new bridge suspension
system began in summer 2005. In fact, spinning cable wire marked the fourth
phase of new bridge construction.
In July 2005, on the heels of completing the 510-foot tall towers, bridge
workers hauled the first cable wires from the Gig Harbor and Tacoma anchorages
to the top of the towers. Connecting this 5/8-inch “pilot line”
– connecting land to sea – was the first phase in building
a suspension system. On two different days, a workboat on the shoreline
set out to meet a tugboat on the water. The line bound to the anchorage
was ferried across the water and joined with a same-size steel wire lowered
from the tower. When the skiff came alongside the tugboat, deckhands connected
the ends of each cable wire to a steel delta plate. The whole process
– dragging the wire from the anchorage to the beach, lowering a
second wire from a 510-foot tall tower, joining the two ends in the Narrows
and raising the pilot line it into position – took slightly more
than an hour.
Between August and early October, cable crews built two suspended walkways
that climbed from the anchorages on shore to the tower tops, and draped
elegantly across the waterway. Bridge crews used the walkways as work
platforms. Made of steel wire mesh and wooden slats separated one to two
feet apart, the catwalks resembled something of a rustic footbridge.
Cable spinning officially got underway in mid-October 2005 when crews
pulled the first galvanized steel wire from the Tacoma anchorage over
the towers to the Gig Harbor anchorage and back again. The continuous
(and spliced) steel wire made 2,204 roundtrips until crews had spun 19,000
miles of cable wire.
Unless you observe the process firsthand, cable spinning is difficult
to visualize. Spinning wire is a simple mechanical process, essentially
unchanged since the 19th century: A spinning wheel pulled off individual
wires – about half the diameter of a pencil – from large spools
at the Tacoma anchorage, and ferried the lines across the water and back.
As wires were pulled westward four at a time, each one was laid parallel
to the other. The wheel’s guide was a tramway haul rope; when it
moved, the spinning wheel followed. (There were two spinning wheels, by
the way, controlled from inside a dispense center at the east anchorage.)
A total of 24 tram support frames (one every 220 feet across the bridge)
helped align and place the wire as it was spun. When the first 464 wires
made the journey, they became compressed into a single strand. A total
of 19 strands, each containing 464 wires, were compacted and wrapped to
complete one of two suspension cables.
By early March 2006, crews had finished spinning and compacting the south
suspension cable; permanent steel bands where placed every 40 feet around
the 19 strands that comprise the "steel rope." The north main
cable followed suit in mid-April. In April, workers finished installing
264 pairs of suspender cables on both cables. These suspenders –
far sturdier than the kind your grandfather wore – connected the
future deck to the pair of 20.5-inch steel ropes. The suspenders, together
with the main cable, support the weight of the deck
and the traffic crossing the bridge.
See glossary for more bridge engineering terms.
« Back to previous page
|  |
| |
At top speed, the spinning wheels go 12 miles per hour. |
|
| |
Every strand of wire has a precise position
and is laid parallel to one another. |
|
| |
When completed, the two main
cables will each measure 20½ inches in diameter, be more than
a mile long and weigh six million pounds. |
|
| |
Individual cable strands – 19 per cable –
are splayed inside the anchorage to distribute the load of 25 million
pounds exerted on each 20½-inch main cable. |
|
|