Washington State Department of Transportation
WSDOT NewsSite IndexContact WSDOTWSDOT Home
Traffic & RoadsProjectsBusinessEnvironmentalMaps & Data
Tacoma Narrows Bridge Project

Project Info
•  

Project Home

•  

Bridge Open

»  

Building the Bridge

•  

Finance & Schedule

•  

History & More

•  

Just the Bridge Facts

•  

Photo Album

•  

Tolls: Good To Go!

•  

Traffic Information

•  Building the New Tacoma Narrows Bridge
TNB Tolling


•  Nighttime noise construction information, (253) 620-4440
•  Contact the TNB Office, 1 (877) 762-7769

Contact us

Lisa Murdock
Olympic Region Communications Manager
  (360) 357-2789
WSDOT Olympic Region
  (360) 357-2600
Contact us and tell us
what you think:
orfeedback@wsdot.wa.gov or
Online Bridge Form

WSDOT
3214 50 Street Court NW, Building D, Suite 302
Gig Harbor, WA 98335

TNC
2110 14th Ave. NW
Gig Harbor, WA 98335


» Unsubscribe

Building the Bridge

Suspension Bridge: Learn more about the Caissons Suspension Bridge: Learn more about the Towers Suspension Bridge: Learn more about Cable Spinning Suspension Bridge: Learn more about the Bridge Deck Suspension Bridge: Learn more about the Anchorage Suspension Bridge

Interactive illustration of a suspension bridge
Hover over the structural elements to learn more

Cable

The "Suspension" Part of the Bridge

As compared to building concrete towers 17½ feet at a time, connecting “land to sea” with steel wire is a fairly simple proposition. Fabrication of the new bridge suspension system began in summer 2005. In fact, spinning cable wire marked the fourth phase of new bridge construction.

In July 2005, on the heels of completing the 510-foot tall towers, bridge workers hauled the first cable wires from the Gig Harbor and Tacoma anchorages to the top of the towers. Connecting this 5/8-inch “pilot line” – connecting land to sea – was the first phase in building a suspension system. On two different days, a workboat on the shoreline set out to meet a tugboat on the water. The line bound to the anchorage was ferried across the water and joined with a same-size steel wire lowered from the tower. When the skiff came alongside the tugboat, deckhands connected the ends of each cable wire to a steel delta plate. The whole process – dragging the wire from the anchorage to the beach, lowering a second wire from a 510-foot tall tower, joining the two ends in the Narrows and raising the pilot line it into position – took slightly more than an hour.

Between August and early October, cable crews built two suspended walkways that climbed from the anchorages on shore to the tower tops, and draped elegantly across the waterway. Bridge crews used the walkways as work platforms. Made of steel wire mesh and wooden slats separated one to two feet apart, the catwalks resembled something of a rustic footbridge.

Cable spinning officially got underway in mid-October 2005 when crews pulled the first galvanized steel wire from the Tacoma anchorage over the towers to the Gig Harbor anchorage and back again. The continuous (and spliced) steel wire made 2,204 roundtrips until crews had spun 19,000 miles of cable wire.

Unless you observe the process firsthand, cable spinning is difficult to visualize. Spinning wire is a simple mechanical process, essentially unchanged since the 19th century: A spinning wheel pulled off individual wires – about half the diameter of a pencil – from large spools at the Tacoma anchorage, and ferried the lines across the water and back. As wires were pulled westward four at a time, each one was laid parallel to the other. The wheel’s guide was a tramway haul rope; when it moved, the spinning wheel followed. (There were two spinning wheels, by the way, controlled from inside a dispense center at the east anchorage.)

A total of 24 tram support frames (one every 220 feet across the bridge) helped align and place the wire as it was spun. When the first 464 wires made the journey, they became compressed into a single strand. A total of 19 strands, each containing 464 wires, were compacted and wrapped to complete one of two suspension cables.

By early March 2006, crews had finished spinning and compacting the south suspension cable; permanent steel bands where placed every 40 feet around the 19 strands that comprise the "steel rope." The north main cable followed suit in mid-April. In April, workers finished installing 264 pairs of suspender cables on both cables. These suspenders – far sturdier than the kind your grandfather wore – connected the future deck to the pair of 20.5-inch steel ropes. The suspenders, together with the main cable, support the weight of the deck and the traffic crossing the bridge.

See glossary for more bridge engineering terms.


« Back to previous page


At top speed, the spinning wheels go 12 miles per hour.
Every strand of wire has a precise position and is laid parallel to one another.
When completed, the two main cables will each measure 20½ inches in diameter, be more than a mile long and weigh six million pounds.
Individual cable strands – 19 per cable – are splayed inside the anchorage to distribute the load of 25 million pounds exerted on each 20½-inch main cable.

  Copyright WSDOT © 2005

    Traffic & Roads | Site Index | Contact WSDOT | WSDOT Business | WSDOT Home