SR 169 / SR 900 - Roadside Safety Improvements - Complete September 2010

Project Status - Complete
SR 169 project maps SR 169 rumble strip locations

SR 900 project maps
SR 900 rumble strip locations


Photo of centerline rumble strips Rumble strips are cut into the existing pavement to alert inattentive drivers.

Overview
WSDOT made safety improvements along the SR 169 and SR 900 corridors. Crews installed shoulder and centerline rumble strips, and new guardrail in select locations. These improvements are expected to reduce the likelihood of crossover and run-off-the-road collisions.

How You Benefit
Cross GlyphImproves Safety
Rumble strips and guardrail reduce the likelihood of crossover and run-off-the-road collisions, and the resulting injuries and fatalities.

Partnerships & Cooperation
WSDOT awarded the contract to Coral Construction Co. in March 2010. Construction began in May 2010 and was completed in September 2010.

Funding

Pre-existing funds: $1.2 million