Skip Top Navigation

SR 167 - Puyallup River Bridge - Bridge Replacement

Status

July 2014

 

  • On weekdays from 9:30 a.m. to 2 p.m., drivers can expect one-way alternating traffic on 4th Street and Levee Road under the Puyallup River bridge.
  • Watch a time-lapse video of the SR 167 Puyallup River bridge move.

  • Now that the northbound bridge has been relocated, crews will begin to build a new bridge in its place. Construction of the new bridge is scheduled to be complete by late 2015.

  • The WSDOT would like to thank the public for altering their travel plans to help reduce congestion in the area during this phase of the project.

 

This project will use the design-build method of project delivery. WSDOT is completing the preliminary design parameters for the new bridge and alignment, project staging, construction, and ultimate configuration.

WSDOT determined this project will be awarded based on a two-step design-build process due to the complex soil conditions. WSDOT will provide potential design-build teams with a baseline structure and construction staging approach in the Request For Proposals. Design-build teams will be provided an opportunity to propose innovations to the baseline plan.

WSDOT will obtain the right-of-way and environmental permits necessary to complete the project.

Why is WSDOT replacing the SR 167 Puyallup River Bridge?
 The existing steel bridge built in 1925 is structurally deficient and functionally obsolete.

In January of 2011, WSDOT implemented a load restriction requiring vehicles larger than 10,000 pounds gross vehicle weight to use the right lane only. This is due to floor beam deterioration that was detected during a routine bridge inspection. Due to the load restriction and structural deterioration, the replacement of the bridge has been fully funded and advanced ahead of the SR 167 – Tacoma to Edgewood New Freeway Construction project.

Crews previously installed steel plates along the underside of the bridge’s steel truss to reinforce the structure so legal-weight trucks can continue to use the 89-year old bridge until the replacement bridge is complete.

The End Result
This project replaces the existing northbound bridge with a new two lane structure, preserving the structural and functional integrity of the roadway.

The new bridge is designed with the capacity to add new lanes in the future if funding becomes available.

Project Benefits

Improved Structure: The new structure will be designed and built to current engineering and seismic standards.

Safety: Wider shoulder, lanes, and an 8-foot sidewalk will enhance bicycle and pedestrian safety.

What is the project timeline?
WSDOT advertised the Request for Qualifications during spring of 2013.

On October 3, 2013, WSDOT awarded a design-build contract to Atkinson Construction for $23.3 million to design and build a replacement northbound bridge over the Puyallup River.

The Design-Build team of Atkinson/Jacobs has completed design of the new steel plate girder bridge superstructure to allow steel fabrication to beginthis summer.

Construction of the new bridge is scheduled to be complete by late 2015.

Financial Information

Financial Data for PIN 316725A
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $31,242
Total $31,242

Project signage will reflect the cost of construction engineering, project bid award and sales tax.

How can I get more information?
Contact:
Brenden Clarke
Project Manager
360-357-2606

Claudia Bingham Baker
Communications Manager
360-357-2789

back to top