January 2013
- When reviewing the Record of Decision for the project that was signed in October of 2007, the project team identified the need for a Supplemental EIS due to the steel truss bridge eligibility for the Registry of Historical Structures. The EIS is a document that discloses potential effects from a proposed project under the requirements of the National Environmental Policy Act (NEPA) and the State Environmental Policy Act (SEPA).
- Links to the draft Supplemental EIS for the project can be in the navigation bar to the left. Comments will be accepted from the public 45 days. Afterward, the SEIS will be finalized and submitted for a new project Record of Decision.
- WSDOT Geotech staff utilized soil investigations, with borings at each conceptual pier location to complete the Geotechnical Data Report for the project. The Geotechnical Baseline Report is under development.
- WSDOT has completed consultation for the historical Puyallup River steel truss bridge. The MOA is being finalized and will be sent for signatures in January. This will complete the Section 106 process. . For more information, visit here.
- WSDOT is working with property owners to acquire right-of-way necessary for the new bridge alignment.
- WSDOT is working with utility owners to develop a relocation plan.
- The WSDOT project team met with permitting staff in late October. At this time, with the Section 106 process nearing completion, the project is on track to obtain permits and advertise the Request for Qualifications by the spring of 2013.
This project will use the design-build method of project delivery. WSDOT is completing the preliminary design parameters for the new bridge and alignment, project staging, construction, and ultimate configuration.
WSDOT determined this project will be awarded based on a two-step design-build process due to the complex soil conditions. WSDOT will provide potential design-build teams with a baseline structure and construction staging approach in the Request For Proposals. Design-build teams will be provided an opportunity to propose innovations to the baseline plan.
WSDOT will obtain the right-of-way and environmental permits necessary to complete the project.
Why is WSDOT
replacing the SR 167 Puyallup River Bridge?
The existing steel bridge built in 1925 is structurally deficient and functionally obsolete.
In January of 2011, WSDOT implemented a load restriction requiring vehicles larger than 10,000 pounds gross vehicle weight to use the right lane only. This is due to floor beam deterioration that was detected during a routine bridge inspection. Due to the load restriction and structural deterioration, the replacement of the bridge has been fully funded and advanced ahead of the SR 167 – Tacoma to Edgewood New Freeway Construction project.
The End Result
This project replaces the existing northbound bridge with a new two lane structure, preserving the structural and functional integrity of the roadway.
Project Benefits
Improved Structure: The new structure will be designed and built to current engineering and seismic standards.
Safety: Wider shoulder, lanes, and an 8-foot sidewalk will enhance bicycle and pedestrian safety.
What is the project timeline?
WSDOT plans to advertise the Request for Qualifications the spring of 2013, the Request for Proposals the summer of 2013, and have a Design-Build team on board by fall of 2013. Design is expected to be complete by the summer 2014 at which time construction will commence. Construction of the new bridge is scheduled to be complete by late 2015.
Financial Information
Project signage will reflect the cost of construction engineering, project bid award and sales tax.
This project is funded from the following sources:
Federal BR – $28,843,153
State – $1,278,009
Total Funding available from all sources: $30,121,162
How can I get more information?
Contact:
Brenden Clarke, Project Manager, (360) 357-2606
WSDOT SR 167 Puyallup River Bridge Replacement
PO Box 47440
Olympia, WA 98504-7440
Claudia Bingham Baker
Communications Manager
WSDOT Olympic Region
5720 Capitol Boulevard SE
Tumwater, WA 98501
Phone: 360-357-2789
back to top