Overview
WSDOT repaved SR 167 between I-405 and Grady Way in Renton and on SR 509 between S. 174th to S. Normandy Road. These areas were cracking and rutting and WSDOT crews were regularly patching the roadway. Repaving has reduced the need for costly and inconvenient maintenance.
Project timeline:
November 2010: Project advertised to contractors.
April 2011: Paving began on SR 167 from I-405 to Grady Way.
May 2011: Paving began on SR 509 from 174th to S. Normandy Road.
June 2011: Paving complete.
 | Improves Safety
The new pavement provides a smoother surface for motorists and eliminated cracked sections of roadway. Crews also upgraded guardrail, pavement markings and signing.
|
Partnerships & Cooperation
WSDOT worked with local communities impacted during construction.
Funding
| Financial Data for PIN 116718P |
| Funding Source |
Amount ($ in thousands) |
| 2003 Gas Tax (Nickel Funding) |
$0 |
| 2005 Gas Tax (TPA) |
$0 |
| Pre-Existing Funds (PEF) |
$1,082 |
| Total |
$1,082 |
|
Contact Us
Hien Trinh
WSDOT Project Engineer - Construction
425-956-2100
TrinhH@wsdot.wa.gov
Communications
WSDOT Communications
NWpublicAffairs@wsdot.wa.gov
206-440-4697
back to top