SR 16 - Burley Olalla Interchange - Complete October 2009

Project Status - Complete

View entire map.


The new westbound SR 16 on-ramp from Burley Olalla Road.
The new westbound SR 16 on-ramp from Burley Olalla Road.

View additional construction photos.

Overview
The new SR 16 Burley Olalla Road interchange opened to traffic Oct. 7, 2009.

Two new bridges carry traffic over Burley Olalla Road and accomodate future SR 16 expansion. New on- and off-ramps improve access between Burley Olalla Road and SR 16.

WSDOT completed the project more than nine months ahead of schedule and $1.75 million under budget.

How You Benefit
Cross GlyphImproves Safety
This project improves safety. Vehicles no longer have to cross the median to enter and exit the highway.
Leaf Glyph Protects Environment
Project enhances the environment by rechanneling two streams and installing wider culverts for improved fish passage.

Partnerships & Cooperation

Funding

Financial Information
This project is funded from the following sources:

  • 2003 Gas Tax (Nickel Funding) - $22,469,737
  • State - $106,169
  • Total Funding Available From All Sources - $22,575,906