SR 155 - Omak Eastward - Chip Seal - Complete August 2009

Project Status - Complete
SR 155 Omak Eastward
View entire map This project chip sealed 16 miles of SR 155 from MP 62.8 to MP 78.82 from Omak, east to 5 miles below the Disautel Pass summit.

Click to Enlarge
View entire photo 
Before - SR 155 outside Omak.

Overview
This project and two other pavers on SR 243 and 262 have been combined into one contract called NCR Seal 2009 Stage 2. Construction began May 26 and was complete August 6, 2009. (Read the news release). 16 miles of SR 155 in eastern Okanogan County were resurfaced. Chip sealing repaired pavement damage and extends the life of the roadway. This treatment improves safety for drivers by creating a skid-resistant surface and reducing glare.

How You Benefit
Cross GlyphImproves Safety
Providing new signage, striping and a smoother ride.
Dollar Sign Glyph Economic Incentive
Reduces maintenance costs, extends roadway life and supported 30 jobs during construction.

Partnerships & Cooperation
In February 2009, President Barack Obama signed into law the American Recovery and Reinvestment Act. This project translated the federal recovery funding into job creation and highway improvements.

Funding

The project was advertised for private contractor bids on April 6, 2009. Two bids were opened April 30th. On May 4, contract #7733 was awarded to Central Washington Asphalt, Inc. for $2,983,566.25, 9-1/2% under the engineering estimate.

Funding for this project is provided by:

• 2009 American Recovery and Reinvestment Act (ARRA): $0.94 million

Contact Us
Project Engineer Bob Romine