Skip Top Navigation

I-90 - West of George Paving - Complete July 2008

Project Status - Complete
Project Area Map View entire map.  This I-90 paving project, from MP 137.82 to MP 148.45, is located in Grant County.

Click to enlarge
View entire photo
This is the repaved lane as the project was completed, August 4th, 2008.
Right lane heading eastbound to be paved View entire photo.  The right lane heading eastbound was resurfaced in this project.

Overview
This preservation project paved 10.6 miles of the right lane heading eastbound between Vantage and George. The eastbound outside lane  needed to be restored due to pavement deterioration. Construction began June 2nd and was complete on July 25, 2008

How You Benefit
Cross GlyphImproves Safety
  • Provides a smoother driving surface.
  • More than 158 thousand feet of new reflective painted striping was included in the project.
  • Almost 15 thousand feet of plastic striping was installed along with 8,900 shoulder recessed pavement markers.
Dollar Sign Glyph Economic Incentive
The project extends the life of the roadway, preventing further deterioration at the least possible "life cycle" cost.

Partnerships & Cooperation

Funding

This project was advertised for private contractor bids on September 24th and bids were opened on October 25th. Contract #7419 was awarded to Central Washington Asphalt on October 29th, 2007 for $1,359,595.95, 9% under the engineering estimate.

This project is funded through the following sources:

  • Pre-Existing Gas Tax - $2.1 million
  • Total funding from all sources - $2.1 million

Contact Us
Project Engineer Eric Pierson
WSDOT North Central Region
P.O. Box 98
Wenatchee, WA 98807
Phone: (509) 667-2870 or
toll free (888) 461-8816
E-mail: piersoe@wsdot.wa.gov

back to top