I-90 - Sullivan Rd to Barker Rd

Status

April 2012

  • Weekly Traffic and Construction Update
  • This project was awarded to Acme Concrete Paving Inc. of Spokane with a construction bid of $14,949,578.
  • On winter suspension.  Work should resume later this month.

 

This project will fully reconstruct I-90, adding a third lane in each direction and converting the surface to Portland Cement Concrete Pavement.

Why is WSDOT Rebuilding I-90?
Increased traffic volume on I-90 has neccessitated the addition of one lane in each direction.

The End Result
A six-lane freeway with a more durable concrete surface.

Project Benefits
Reduced congestion and a longer-lasting pavement surface.

What is the project timeline?
The contractor will resume work in April 2012.  The project should be complete later in the spring of 2012.

Financial Information

Financial Data for PIN 609049N
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $19,123
Total $19,123

How can I get more information?
Contact:
Darrel McCallum, project engineer
WSDOT Eastern Region
2714 N. Mayfair
Spokane, WA 99207
(509)323-8412