I-90 - Geiger Rd to Spokane Viaduct - PCCP Rehabilitation - Complete July 2013

Overview
This project replaced deteriorated concrete pavement panels, ground concrete pavement to eliminate ruts, bridge deck repairs were made on the Abbot Rd. and Latah Creek Bridges, and upgraded illumination systems, guardrail, and signing were installed.

How You Benefit
Dollar Sign Glyph Economic Incentive
Preserved the public investment in the highway system by smoothing the existing pavement and repairing damaged concrete panels and worn bridge surfaces.

Partnerships & Cooperation
At WSDOT we seek to address the concerns of the tribal nations using the process outlined in Section 106 of The National Historic Preservation Act and the WSDOT Tribal Consultation Policy adopted in 2003 by the Transportation Commission as part of the WSDOT Centennial Accord Plan.

Funding

2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $11,035
Total $11,035