I-90 - Front Street Bridge Girder Replacement

Project Status - Complete
WSDOT will be repairing a damaged girder on the I-90 Bridge over Front Street in Issaquah starting in January.
View a larger map showing the location where WSDOT contractor crews replaced the damaged girder on the I-90 bridge over Front Street in Issaquah.

An oversized truck punched a hole in the I-90 bridge over Front Street in Issaquah. A project to repair the bridge will begin in January.
An over-height truck punched a hole in the I-90 overpass over Front Street in Issaquah in March. To see other pictures of the bridge strike, check out our Flickr page.

Overview
WSDOT contractor crews replaced a damaged 114-foot bridge girder on the eastbound I-90 Front Street overpass in Issaquah.

The girder was damaged when an over-height garbage truck collided with the overpass in March 2015.

How You Benefit
Cross GlyphImproves Safety
While the damaged bridge girder did not pose a risk to drivers, the overpass would eventually deteriorate to a state where it would be unsafe for vehicles to go on or under the bridge.

Replacing the damaged bridge girder returned the overpass to its original strength and eliminated a visual distraction to drivers in Issaquah.

Partnerships & Cooperation
WSDOT coordinated the road closure schedule and worked closely with the city of Issaquah.

Funding

Financial Data for PIN 109057C
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $1,002
CWA $0
Total $1,002