Overview
The project strengthened the eastbound and westbound right lanes of I-82 between Union Gap and Granger, and extended the service life of the pavement by installing dowel bars in the wheel paths between each concrete panel.
Crews also replaced severely cracked concrete panels, and ground the surface to improve the ride and improve traction.
WSDOT completed this project ahead of schedule and under budget.
 | Improves Safety
Crews constructed a smoother highway and improved traction. Crews also restored guardrail and pavement markings.
|
 | Economic Incentive
Crews extended the service life of the pavement.
|
Partnerships & Cooperation
This project was constructed on existing WSDOT right-of-way; therefore, no partnerships were necessary.
Funding
| Financial Data for PIN 508207X |
| Funding Source |
Amount ($ in thousands) |
| 2003 Gas Tax (Nickel Funding) |
$0 |
| 2005 Gas Tax (TPA) |
$0 |
| Pre-Existing Funds (PEF) |
$12,583 |
| Total |
$12,583 |
|
Contact Us
Moe Davari, Project Engineer
WSDOT South Central Region Tri-Cities Field Office
1655 North Fowler Street
Richland, WA 99352
Phone: 509-222-2402
back to top