May 2012
- The project is currenlty on hold. Work will resume in July.
- The plan, as it stands now, is to install guardrail July 9 through July 27, pave July 23 through Aug. 3, and stripe lane lines Aug. 13 through Aug. 31.
- We repaired and repaved nearly 24 lane miles of northbound I-5 last year between Burlington and Lake Samish, smoothing and preserving the highway for drivers.
Why is WSDOT
repaving northbound I-5 between Burlington and Bellingham?
Large cracks are appearing along 12 miles of northbound I-5 between Burlington and Bellingham (specifically, between mileposts 232 and 244). There are old concrete panels beneath the asphalt that are causing the pavement to crack and separate. The concrete panels date back to when the interstate was first built in the 1960's. They were paved over in the early 90’s, and we haven’t repaved since.
In an effort to temporarily hold the roadway together until permanent repairs can be made in 2011, our maintenance crews have sealed the large cracks the last two summers. This has helped temporarily hold the roadway together the last two winters.
The End Result
To permanently repair the interstate and smooth the roadway for drivers, we will grind out all of the existing asphalt, crack and immobilize the concrete panels, and then repave.
We will repave northbound I-5 from Joe Leary Slough in Skagit County (milepost 231.8) to Nulle Road in Whatcom County (milepost 243.9).
We will also pave all on- and off-ramps in both the north- and southbound directions of I-5 within the project limits.
Project Benefits
Repairing and repaving preserves the interstate and will smooth the roadway, improve safety for drivers, and reduce long term maintenance repairs and costs.
What is the project timeline?
- Spring 2012 - Construction completion anticipated.
- Fall 2011 - Completion of major paving on I-5 northbound
- May 2011 - Construction begins
- Winter 2011 - Contractor Granite Construction Inc. hired to design and build this project.
- Fall 2010 - Advertise project to contractors
Financial Information
| Financial Data for PIN 100573D |
| Funding Source |
Amount ($ in thousands) |
| 2003 Gas Tax (Nickel Funding) |
$0 |
| 2005 Gas Tax (TPA) |
$0 |
| Pre-Existing Funds (PEF) |
$19,541 |
| Total |
$19,541 |
|
How can I get more information?
Contact:
Communications, Dustin Terpening
1043 Goldenrod Road, Suite 101
Burlington, WA 98223
Phone: 360-757-5997
Email: dustin.terpening@wsdot.wa.gov
or
Engineering Manager Jay Drye
1043 Goldenrod Road, Suite 101
Burlington, WA 98223
Phone: 360-757-5993
E-mail: dryej@wsdot.wa.gov