Overview
Crews repaired the steel stringers that support the bridge deck and sidewalk, replacing a portion of the expansion joint, modifying joints between concrete panels on the bridge deck and repairing the steel trusses. Construction started in May 2008 and was completed in July 2009.
 | Economic Incentive
The work extends the service life of the existing bridge.
|
Partnerships & Cooperation
Mowatt Construction of Woodinville was the contractor on the project.
We appreciate the patient and cooperative travelers who accommodated crews by driving safely during nighttime lane closures.
Funding
This project was funded through the following sources:
Existing Funds -
State MVA, $17,820
Fed Bridge Preservation Fund, $984,632
Total Funding From All Sources - $1,002,452
Contact Us
Neal Uhlmeyer, Project Engineer
WSDOT Lacey Project Office
7912 Martin Way, Suite E
PO Box 47448
Olympia, WA 98504-7440
Phone: 360-412-3421
E-mail: UhlmeyN@wsdot.wa.gov
back to top