Revive I-5 weekend closures

Part of the I-5 NB MLK Jr Way to NE Ravenna Br – Pavement Repair & More project.

Weekend ramp closures

The northbound I-5 off-ramp to the West Seattle Bridge/Columbian Way/Spokane Street will be closed from 8 p.m. Friday, Sept. 28 to 5 a.m. Monday, Oct. 1, for repaving work. This work is weather-dependent. Drivers should consider alternative routes, including SR 599 and West Marginal Way.

Upcoming lane reductions

Northbound I-5 will be reduced to two lanes between Martin Luther King Jr. Way and Olive Way in Seattle beginning at 8 p.m.. Friday, Oct. 12, until 5 a.m. Monday, Oct. 15. This work is weather-dependent.

Weekend closures

*NOTE: This section will be updated in the event of weather delays. As we approach each weekend, the work detail and map will be included above.

  • April 20-23: Two lanes open (COMPLETED)
  • May 11-14: Two lanes open (COMPLETED)
  • May 18-21: Two lanes open (COMPLETED)
  • June 1-4: Full northbound I-5 closure (COMPLETED)
  • July 13-16: Full northbound I-5 closure (COMPLETED)
  • Aug. 10-13: Two lanes open (COMPLETED)
  • Sept. 14-17: Two lanes open (POSTPONED)
  • Oct. 12-15: Two lanes open