I-5 - I-205 to North Fork Lewis River Bridge – Rehabilitate Pavement

Status

July 2017

  • Get the latest travel information by visiting our travel advisory webpage.
  • Construction contract awarded to Granite Construction Company on Tuesday, May 24, 2016.

Beginning in summer 2016, crews will rehabilitate nearly 10 miles of Interstate 5 between the I-5/I-205 split and the North Fork Lewis River Bridge in Clark County. 

Concrete panel replacement
Crews will replace concrete panels throughout the length of the project. These panels are cracked beyond repair.

Repaving
Asphalt nearing the end of its lifespan will be removed. Crews will grind the top layer of asphalt off the northbound left lane of the interstate and place a new layer. This will create a new driving surface.

Why is WSDOT repaving this stretch of I-5?
Sections of the interstate are showing signs of wear and tear. There are cracks, ruts and potholes in many places along the highway. This $5.1 million project will extend the life of the roadway and provide a smoother surface and safer ride for drivers.

I-5 is the most significant freight freeway on the West Coast, linking markets in Canada, the United States and Mexico and is critical to the regional, state and national economy. It is the busiest commuter roadway in western Washington.

The End Result
Rehabilitating this stretch of I-5 extends the life of the interstate and preserves an important commuter and freight corridor for many years to come. 

Project Benefits

  • Preservation – Repaving this section of I-5 will improve the surface of the roadway and extend the life of the highway. 
  • Safety – Removing ruts and cracks will produce a smoother highway surface, creating a safer ride for drivers. 
  • Economic – Repaving this section of I-5 will reduce the need for costly emergency repairs and maintenance work.

What is the project timeline?
Spring 2016: Project contract will be awarded.
Summer 2016: Estimated construction start date.
Summer 2017: Scheduled construction completion date.

Financial Information

Financial Data for PIN 400515I
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $320
CWA $0
Total $320

Project signage will reflect the cost of construction engineering, project bid award and sales tax.

How can I get more information?
Contact:
Lori Figone
WSDOT  Project Engineer
360-905-1500

Tamara Greenwell 
360-905-2058
WSDOT Communications